Free Motion for Leave to File - District Court of Federal Claims - federal


File Size: 228.5 kB
Pages: 53
Date: January 13, 2005
File Format: PDF
State: federal
Category: District
Author: unknown
Word Count: 10,457 Words, 65,643 Characters
Page Size: Letter (8 1/2" x 11")
URL

https://www.findforms.com/pdf_files/cofc/13239/899-4.pdf

Download Motion for Leave to File - District Court of Federal Claims ( 228.5 kB)


Preview Motion for Leave to File - District Court of Federal Claims
Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 1 of 53

IN THE UNITED STATES COURT OF FEDERAL CLAIMS YANKEE ATOMIC ELECTRIC COMPANY, Plaintiff, v. THE UNITED STATES, Defendant. ) ) ) ) ) ) ) ) )

No. 98-126C (Senior Judge Merow)

DEFENDANT'S RESPONSE TO PLAINTIFFS' INITIAL POST-TRIAL BRIEFS1 Pursuant to this Court's order dated September 21, 2004, defendant, the United States, respectfully submits its response to the plaintiffs' initial post-trial briefs. SUMMARY OF ARGUMENT In our initial post-trial brief, we discussed in great detail the significant and insurmountable problems with the Yankees' evidence regarding any causal link between the partial breach by the Department of Energy ("DOE") and the damages that they are claiming. As we established in that post-trial brief, the Yankees have attempted to recover damages of almost four times the amounts that they have paid in fees pursuant to their Standard Contracts, relying upon a single spent nuclear fuel ("SNF") acceptance scenario that is supported only by a speculative hypothetical model of "exchanges" of SNF acceptance allocations that lacks specific detail and is based upon numerous assumed facts in conflict with reality. The Yankees made a conscious decision not to present any alternative damages scenarios and to rest their case, upon which they have the burden of proof, solely upon the SNF acceptance scenario that Mr. Graves presented. The Government requests that this post-trial response brief also be deemed applicable in Connecticut Yankee Atomic Power Co. v. United States, No. 98-154C, and Maine Yankee Atomic Power Co. v. United States, No. 98-474C.
1

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 2 of 53

In their own post-trial brief, however, the Yankees have retreated significantly from Mr. Graves' analysis and findings. Even though virtually all of their trial evidence and testimony focused upon establishing that DOE was obligated to remove Yankee Atomic's SNF by 1999, Connecticut Yankee's by 2001, and Maine Yankee's by 2002, and that the incurrence of damages were tied to those "fuel-out" dates, the Yankees now argue that this Court need not decide "fuelout" dates, or even an SNF acceptance schedule, at all. Instead, they contend, since the Court has already found liability for a partial breach, causation is established, without the need for any further fact-finding. Apparently, the Yankees' entire case now rests upon their contention that the Standard Contract required DOE to accept all of the Yankees' SNF immediately after January 31, 1998, so as to preclude them from having to incur any SNF storage costs. The Standard Contract does not contain the requirement that the Yankees propose. In fact, in earlier briefing in this case, the Yankees alleged that the SNF acceptance rate that the Standard Contract requires would be fast enough to allow the Yankees to exchange SNF acceptance allocations with other contract holders and, through exchanges, obtain earlier "fuelout" dates than would otherwise be required under the contract. Now, however, they apparently are arguing ­ without any admissible support ­ that the contract actually required even faster acceptance by DOE. The Yankees' new argument would require DOE to abandon the contractually mandatory "oldest fuel first" ("OFF") allocation system for SNF acceptance or, alternatively, would require DOE (to operate under OFF while removing SNF in the time frames that the Yankees now propose) to accept more than 24,000 Metric Tons Uranium ("MTU") of SNF from contract holders in the first two years of the program of SNF acceptance. In making this argument, which depends upon the Court's incorporation into the contract of unwritten -2-

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 3 of 53

requirements that, at best, are identified as program goals in a few program documents, the Yankees have also misinterpreted the program goals upon which they rely to support their argument. Contrary to the Yankees' assertions, the non-contractual and non-binding program goal to which they refer was never intended to create the kind of acceptance rates or program policy that the Yankees now advocate. Given the wholly unsupported nature of the Yankees' post-trial shift in strategy, the Court should summarily reject their new theory that requires the Court to assume the existence of causation following a determination of breach. Further, given that the Yankees failed to present evidence at trial establishing causation for its claimed damages based upon any acceptance scenario other than the one presented by Mr. Graves, their claims should be dismissed. DISCUSSION I. AS WE ESTABLISHED IN OUR INITIAL POST-TRIAL BRIEF, THE YANKEES BEAR THE BURDEN OF PROVING EVERY ELEMENT OF THEIR DAMAGES CLAIMS, INCLUDING LIABILITY, CAUSATION, AND RESULTANT DAMAGE

As we explained in our initial post-trial brief, to recover damages, a plaintiff "must prove the requirements for an award of damages by a preponderance of the evidence," and these "requirements include: causation, foreseeability, and reasonable certainty in the amount of damages." Alaska Pulp Corp. v. United States, 59 Fed. Cl. 400, 413-14 (2004). According to the precedent of this circuit, the Yankees bore the burden of introducing clear proof that they were injured as a direct result of DOE's delay in accepting their SNF. Myerle v. United States, 33 Ct. Cl. 1, 27 (1897). The venerable decision in Myerle continues to represent the binding standard of this circuit. Glendale Federal Bank v. United States, 239 F.3d 1374, 1382 (Fed. Cir. 2001) (non-

-3-

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 4 of 53

breaching party may recover reliance "damages for any losses actually sustained as a result of the breach"). Further, the "measure of damages to be applied in the particular case is irrelevant until the claimant has established the fact of losses that were the natural and proximate result of the breach of contract." Willems Indus., Inc. v. United States, 155 Ct. Cl. 360, 376, 295 F.2d 822, 831 (1961). "Absent tangible proof of damages, [a party] may not recover for an alleged injury." Roseburg Lumber Co. v. Madigan, 978 F.2d 660, 667 (Fed. Cir. 1992). II. THE YANKEES HAVE FAILED TO ESTABLISH CAUSATION FOR ANY OF THEIR ALLEGED DAMAGES A. The Yankees Have Misstated The Test For Determining Causation

According to the precedent of this circuit, the Yankees bear the burden of introducing clear proof that they were injured as a direct result of DOE's partial breach of the Standard Contract. Myerle v. United States, 33 Ct. Cl. 1, 27 (1897); see also Wells Fargo Bank v. United States, 88 F.3d 1012, 1022-23 (Fed. Cir. 1996) (plaintiff can recover lost profits only if it proves damages would have "accrued and grown out of the contract itself, as the direct and immediate results of its fulfillment"); Quiman, S.A. v. United States, 39 Fed. Cl. 171, 183 (1997) (plaintiff bears burden of showing with clear proof that it was injured as direct result of breach), aff'd, 178 F.3d 1313 (Fed. Cir. 1999). In their post-trial briefs, the Yankees assert that causation is established if they show that the breach is a "substantial factor" in their increased costs. YA Br. 5-6 (citing Bluebonnet Sav. Bank v. United States, 266 F.3d 1348, 1356 (Fed. Cir. 2001)). That test, however, finds its roots in tort law. W. Keeton, et al., Prosser and Keaton on the Law of Torts 266-68 (5th ed. 1984). The well-established contract law test for causation in contract cases before this Court is whether

-4-

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 5 of 53

the claimed damages were "attributable solely to," J.D. Hedin Constr. Co. v. United States, 197 Ct. Cl. 782, 808, 456 F.2d 1315, 1330 (1972), and, thus, "directly related" to, the breach. Wells Fargo, 88 F.3d at 1022; see Southern Pac. Co. v. Darnell-Taenzer Lumber Co., 245 U.S. 531, 533-34 (1918) ("[t]he general tendency of the law, in regard to damages at least, is not to go beyond the first step"). However, even in tort cases, the substantial factor test has not "replaced the need for each liable defendant to be a but-for and substantial contributor to the indivisible injury," Menne v. Celotex Corp., 861 F.2d 1453, 1461 (10th Cir. 1988), and the courts have made clear that, when the claimed damages could have resulted from multiple factors, the plaintiff "must establish that the breach alone would have been sufficient" to cause the claimed damage and that it would not have occurred "but for" the breach. Point Productions A.G. v. Sony Music Entertainment, Inc., 215 F. Supp. 2d 336, 344 (S.D.N.Y. 2002).2 This United States Court of Appeals for the Federal Circuit requires application of both tests, even in the tort context. Shyface v. Secretary of Health and Human Servs., 165 F.3d 1344, 1352 (Fed. Cir. 1999). Thus, the "substantial factor" test may only be applied in place of a "but for" test if doing so would "generally yield identical results." Abbott Labs. v. Brennan, 952 F.2d 1346, 1352-53 (Fed. Cir. 1992). Indeed, the Court in Columbia First Bank v. United States, 60 Fed. Cl. 97 (2004), determined that, under the

The importation of tort causation principles into contract law, without the limiting doctrines that restrict tort liability in multiple cause situations, would result in a lower causation standard in contract law than in tort law. Even in strict liability tort cases, most jurisdictions apply doctrines of contributory or comparative negligence to limit the tortfeasor's liability to the extent of its own actions and not for damage that resulted from other causes. See generally Parks v. Alliedsignal, Inc., 113 F.3d 1327 (3d Cir. 1997); Coats v. Penrod Drilling Corp., 61 F.3d 1113 (5th Cir. 1995); Pan-Alaska Fisheries, Inc. v. Marine Constr. & Design Co., 565 F.2d 1129 (9th Cir. 1977). -5-

2

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 6 of 53

"substantial factor" test, the plaintiff must still prove that the "breaching provisions directly and primarily caused the . . . damages it seeks." Id. at 105. B. Regardless Of The Test Applied, The Yankees' Assertion That The Court Should, In Essence, Assume Causation Is Faulty 1. The Yankees' Argument That, Because A Breach Of Contract Exists, The Court Should Simply Assume Causation Is Unfounded

Regardless whether the Court applies the traditional "but for" test or the "substantial factor" test in analyzing causation, the Yankees have failed to establish causation for any of the costs that they are seeking in this litigation. In our initial post-trial brief, we established that the Yankees have based the entirety of their cases upon their position that DOE was required to remove the last of their SNF from their facilities in 1999 (from Yankee Atomic), 2001 (from Connecticut Yankee), and 2002 (from Maine Yankee). To reach these "fuel-out" dates, the Yankees rely solely upon the testimony of Mr. Frank Graves and his hypothetical model of exchanges of SNF acceptance allocations. Yet, as we established in our initial post-trial brief, Mr. Graves' model is based upon pure speculation and, in fact, is often based upon assumed facts that conflict with reality. As we established in our initial post-trial brief, Mr. Graves' model cannot form the basis of a causation finding.3 In their initial post-trial briefs, the Yankees appear to have distanced themselves from their sole evidence of causation, barely mentioning Mr. Graves' hypothetical exchanges model or

The Yankees alternatively attempted to argue in pre-trial filings that DOE would have provided them with priority in the acceptance of their SNF, pursuant to the provisions of Article VI.B.1(b) of the Standard Contract. As we established in our initial post-trial brief, the Yankees have no basis for making any such argument. -6-

3

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 7 of 53

his "fuel-out" dates discussing causation. See YA Br 12.4 Instead, they identify two factors and assert that, based upon those two factors, "[c]ausation is therefore established." YA Br. 7. First, the Yankees assert that they have established causation because, in 1987, 1989, 1994, or 1996, DOE made statements that provided the utilities with "a good idea" that the January 31, 1998 deadline would not be met. YA Br. 6. Yet, at best, the Yankees' representations only indicate the possibility of a future breach. In any event, as much as the Yankees might want the existence of a breach automatically to create a presumption of causation for any damage alleged, no such presumption exists. The question of causation is separate from the initial question of whether a breach exists, San Carlos Irrig. & Drainage Dist. v. United States, 877 F.2d 957, 959 (Fed. Cir. 1989), and the plaintiff bears the burden of proving both elements by a preponderance of the evidence. Id. The Yankees' attempt merely equate "breach" with "automatic causation" lacks any support. Second, the Yankees assert that this Court, in its June 28, 2004 order, already determined that the Yankees were entitled to recover their damages for providing extended on-site storage of their SNF and that the Court, in that order, effectively decided causastion. YA Br. 6-7. A review of the Court's June 28, 2004 order indicates no such thing, and, in fact, the Court could not have prejudged the existence of causation before any evidence was submitted. Obviously, regardless of DOE's delay, the plaintiffs would have incurred costs for on-site SNF storage up until the point in time when DOE was obligated to complete the removal of their SNF. "As in all breach

With regard to Mr. Graves, the Yankees assert in a conclusory fashion that his testimony "bolsters the other evidence showing that Yankee Atomic's damages were caused by DOE's breach, but [that] proof of the precise date DOE would have removed [the Yankees'] SNF is not necessary to make the causation showing." YA Br. 12. -7-

4

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 8 of 53

of contract cases, the proper measure of damages for defendant's breaches is the amount of plaintiff's extra costs directly attributable to said breaches." Boyajian v. United States, 191 Ct. Cl. 233, 423 F.2d 1231, 1235 (1970) (emphasis added). The Yankees are "not entitled to recover 'expenses which would properly have been incurred regardless of the [breach].'" Id., 423 F.2d at 1236 (quoting Saddler v. United States, 152 Ct. Cl. 557, 564, 287 F.2d 41, 415 (1961)). The issue here, then, is at what point, absent a breach of the Standard Contract, was DOE obligated to have removed all of the Yankees' SNF from their facilities and at what point, absent a breach of the Standard Contract, would the Yankees have otherwise stopped having to pay for the continuing storage of their SNF (and GTCC waste). Absent those findings, this Court cannot determine whether particular costs are "extra" costs that would not have been incurred absent the breach and, therefore, cannot determine causation. The Yankees' assertion that this Court has prejudged causation is unsupportable. 2. The Yankees' Assertion That They Can Establish Causation Without Reference To The Date By Which DOE Was Contractually Obligated To Remove Their SNF Is Unfounded

The Yankees argue that, to establish causation, they "are not required to establish exactly when DOE would have removed [their] SNF in the non-breach world." YA Br. 9. They claim that "[w]hat matters to causation in this case is that DOE would have removed Yankee Atomic's SNF in a reasonable time frame starting in January 1998, not precisely when DOE would have done so," id., and that, since DOE did not accept all of their SNF in a "reasonable" time frame, they are entitled to a causation finding. Accordingly, it appears that the Yankees' current causation argument is based solely upon its position that DOE was required under the terms of the Standard Contract to remove its SNF "beginning not later than January 31, 1998 on a -8-

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 9 of 53

schedule that was robust, efficient and calculated to help utilities avoid additional on-site storage costs after that date." YA Br. 9-10. Based upon this purported contract provision, this Court then is asked to simply assume that, had DOE begun SNF acceptance by January 31, 1998, it somehow would have removed all of Yankee Atomic's SNF by 1999, Connecticut Yankee's by 2001, and Maine Yankee's by 2002. The Yankees' efforts to obscure the facts necessary to find causation strongly indicate that absence of any causation for the claimed damages. As an initial matter, throughout this litigation, the Yankees' arguments regarding the speed at which DOE was required under the Standard Contract to accept contract holders' SNF have focused upon the Yankees' exchanges of SNF acceptance allocations. In their "Pretrial Brief Of Legal Points And Authorities Relied Upon," submitted to the Court on June 30, 1999, the Yankees asserted that the Standard Contract required DOE to pursue an acceptance schedule "that was economically efficient, reasonable, and allowed the utilities to arrange the specific acceptance scheduled themselves, through consensual 'swaps' of sequential acceptance slots" (emphasis added); that, through "swaps," the utilities would be able to "allocate the sequence of removal efficiently among themselves;" and that, through the Standard Contract's "swaps" or exchanges mechanism, or alternatively through the contract's priority provision, the Yankees would have achieved fuel-out dates of 1999, 2001, and 2002. See YA Pretrial Brief, at 10-11, 15 (submitted June 30, 1999). In their post-trial initial brief, however, the Yankees argue that DOE had to accept SNF, apparently without reference to exchanges, at a rate (1) sufficient "to prevent the nuclear utilities from having to construct or maintain additional at-reactor storage facilities for SNF after January 31, 1998; and (2) . . . that permitted DOE to keep up with the rate of production of SNF and reduce the existing SNF backlog." YA PFOF ¶ 61. They assert, without -9-

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 10 of 53

support, that, "[a]t the time of formation of the Contract, the parties understood that an industrywide acceptance rate of 3000 MTU per year would be appropriate to accomplish" these objectives. YA PFOF ¶ 62 (emphasis added). Unfortunately, absent the Yankees' reliance upon exchanges and Mr. Graves, the 3,000 MTU rate upon which the Yankees rely does not achieve the goals that the Yankees have identified. If a strict 3,000 MTU rate was applied to an acceptance queue developed in accordance with the "oldest fuel first" requirement of the Standard Contract, assuming that SNF acceptance began in 1998, and according to the testimony of the Yankees' own expert, Mr. Graves, Yankee Atomic would not have all of its SNF removed until 2007, and Connecticut Yankee and Maine Yankee would not have their SNF removed until 2011. DPFOF ¶¶ 127-128. Yet, the Yankees did not present any evidence at trial to establish that, with "fuel-out" dates of 2007 and 2011, they would not have built dry storage facilities. See, e.g., Def's Response to YA PFOF ¶ 106. Accordingly, even assuming that the Court accepted the Yankees' 3,000 MTU rate argument, the Yankees failed to prove causation under that rate, absent reliance upon Mr. Graves' hypothetical exchanges model. Further, the 3,000 MTU rate that the Yankees allege "accomplishes" the goal of precluding additional at-reactor storage costs at the Yankees does no such thing. As the Court is aware, since the Standard Contract was an industry-wide contract (see DPFOF ¶ 21), DOE could not begin waste acceptance from all utilities on January 31, 1998. Instead, the Standard Contract contemplates the development of an acceptance queue, which DOE was required to implement in performing its contractual obligations, based upon the age of each contract holder's SNF. See DPFOF ¶¶ 53, 89 (discussing "oldest fuel first" acceptance queue ("OFF")). While the contract - 10 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 11 of 53

allows DOE to exercise its discretion to accept SNF outside of the OFF queue (see DX 6, 7, 8, at Art. VI.B.3 (priority), Art. V.D. (emergency), Article V.E. (exchanges)), the OFF queue is the contractually mandated order of acceptance. DPFOF ¶¶ 53, 89. Assuming that DOE was required to remove all of Yankee Atomic's SNF by January 1999, DOE, to comply with the OFF requirement in the Standard Contract, would had to have accepted more than 24,000 MTUs of SNF in the first year of SNF acceptance. DX 218 (internal Yankee memo from Mr. Buchheit to Mr. Mellor: "on an oldest fuel first basis, 24,000 MTU of SNF will have to be accepted by the CRWMS before all Yankee SNF will be removed from the Rowe site"). Similarly, as evidenced by adding the total MTUs accepted between 1998 and 2011 identified in Mr. Graves' model, to accept all of Connecticut Yankee's SNF by 2001 assuming no exchanges, DOE, if it also complied with the Standard Contract's OFF requirement, would had to have accepted approximately 36,000 MTUs of SNF in the first four years of the acceptance program. See DPFOF ¶¶ 125, 126, & 128. The enormous amounts of SNF that DOE would have to accept early in the SNF acceptance program to satisfy the Yankees' proposed yet unwritten "contract requirement" while, at the same time, complying with actual written contract requirements, not only shows the irrelevance of the Yankees' reliance upon a 3,000 MTU acceptance rate, but also evidences the ridiculous nature of the Yankees' argument about this unwritten requirement. The Yankees have not explained how DOE could ever realistically satisfy their unwritten "no additional at-reactor storage" requirement while also satisfying the contract requirement to allocate SNF acceptance positions based upon OFF. "Construction of the terms of a contract . . . should 'avoid absurd and

- 11 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 12 of 53

whimsical results.'" Northwest Marine Iron Works v. United States, 203 Ct. Cl. 629, 493 F.2d 652, 657 (1974) (quoting Anderson v. United States, 203 Ct. Ct. 412, 490 F.2d 921, 928 (1974)). Most importantly, and as discussed in detail in our post-trial initial brief, the absence of any language in the Standard Contract creating the vague and ill-defined "requirement" to preclude additional at-reactor storage that the Yankees propose destroys the Yankees' argument. Tellingly, the Yankees cannot identify a single contract provision that creates the obligation that they propose. The only contract language to which they have referred is a "Whereas" clause which indicates that DOE should take title to SNF "as expeditiously as practicable," but only "following commencement of operation of a repository." YA Br. 10. Since DOE had no statutory or contractual obligation to have a repository operational by January 31, 1998, see Def's Response to YA PFOF ¶ 49 & Indiana Michigan Power Co. v. Department of Energy, 88 F.3d 1272, 1276 (D.C. Cir. 1996), the Yankees' citation is irrelevant to the Yankees' current damages claims.5 The Standard Contract also contains an integration clause, which expressly provides that "[a]ny representation, promise, or condition not incorporated in this contract shall not be binding on either party" and that "[n]o course of dealing or usage of trade or course of performance shall be relevant to explain or supplement any provision contained in this contract." DX 6, 7, 8, Art. XXII.A. For the reasons set forth in our post-trial initial brief, the Standard Contract does not contain any requirement that DOE accept SNF at a rate sufficient to preclude

Further, "it is standard contract law that a Whereas clause, while sometimes useful as an aid to interpretation, 'cannot create any right beyond those arising from the operative terms of the document.'" Grynberg v. Federal Energy Regulatory Comm'n, 71 F.3d 413, 416 (D.C. Cir. 1995) (quoting Abraham Zion Corp. v. Lebow, 761 F.2d 93, 103 (2d Cir. 1985)). - 12 -

5

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 13 of 53

each and every nuclear utility from having to maintain additional at-reactor SNF storage after 1998, precluding the Yankees' request that the Court presume causation. The only other evidence to which the Yankees cite to support the existence of their proposed unwritten contract requirement are documents relating to various non-contractual goals of the program over the course of time. However, as we established in our initial post-trial brief, none of those program goals was ever incorporated into the Standard Contract or otherwise made binding against DOE. Accordingly, it would be inappropriate to consider such parol evidence to create additional unwritten contract requirements. See Def. Br. 13-15; see also National ByProducts, Inc. v. United States, 186 Ct. Cl. 546, 570-71, 405 F.2d 1256, 1270 (1969) (program goals do not become contractually binding unless in form of contractual promise). Nevertheless, even if the Court considered this parol evidence, the alleged program goal advanced by the Yankees ­ that DOE obligated itself to preclude all additional SNF storage costs after January 31, 1998 ­ far overstates DOE's actual program goals. At one point, DOE hoped to be able to accept SNF at a rate that would be sufficient to eliminate out-of-pool at-reactor storage costs "in the aggregate." DX 23 (emphasis added). The Yankees have taken that "goal" and eliminated the "in the aggregate" language, assuming that DOE actually would have increased its acceptance rate to preclude additional at-reactor storage by every individual utility. The Yankees have identified no contemporaneous evidence establishing that DOE ever considered accepting SNF at a rate sufficient to preclude every single utility from requiring additional at-reactor storage. Further, the cited "program goal" specifically references the elimination of the "need for additional at-reactor, out-of-pool storage starting in 1998" (DX 23 (emphasis added)), a goal that would be inapplicable to the Yankees as shutdown reactors. By focusing upon "need," the - 13 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 14 of 53

alleged program goal does not support the contention that shutdown reactors, with sufficient storage space in their wet pools, should be prevented from incurring costs for on-site storage after January 31, 1998, in those wet pools. Accordingly, even if the Yankees could take various program goals and turn them into binding contract obligations, their mischaracterization of DOE's past program goals does not provide a basis for the Yankees' litigation theories. 3. The Yankees' Causation Argument Renders The Standard Contract's Priority Provision Meaningless

It is well-settled that, "[w]hen interpreting the language of a contract, a court must give reasonable meaning to all parts of the agreement and not render any portion meaningless, or interpret any provision so as to create a conflict with other provisions of the contract." Fortec Constructors v. United States, 760 F.2d 1288, 1292 (Fed. Cir. 1985); see United States v. Johnson Controls, Inc., 713 F.2d 1541, 1555 (Fed. Cir.1983). As discussed above, the Standard Contract obligates DOE to accept SNF upon an OFF basis. However, the Standard Contract allows DOE to grant priority outside the OFF acceptance queue to shutdown reactors. DX 6, 7, 8, Art. VI.B.1.(b). DOE holds the exclusive right to grant priority, and, for reasons discussed in our prior post-trial filings, DOE has never granted priority. DPFOF ¶ 114. Indeed, Yankee Atomic repeatedly sought priority treatment under the Standard Contract and industry support in implementing priority, but it failed in its efforts. See, e.g., DPFOF ¶¶ 117, 119, 191. Here, instead of arguing priority treatment under the Standard Contract, the three Yankees seek this Court's rejection of the OFF acceptance schedule and the imposition of an acceptance schedule that would preclude any shutdown utility from incurring additional at-reactor storage costs after January 31, 1998. However, imposing the Yankees' "no additional at-reactor storage"

- 14 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 15 of 53

requirement upon DOE would render the permissive priority provision meaningless by forcing DOE to grant priority in SNF acceptance to shutdown reactors, rather than making it a discretionary decision by DOE. This Court should not interpret the Standard Contract to provide acceptance rights to the Yankees that conflict with DOE's unambiguous right to grant ­ or refuse to grant ­ priority to shutdown reactors. Since allowing the Yankees to recover under an expedited schedule based upon their shutdown status outside of the priority provision would render the priority provision meaningless, such a finding would be improper as a matter of law. 4. The Yankees' Request That The Court Assume A "Reasonable" Acceptance Schedule, Without Reference To The Deference That The Contract Provides DOE In Creating That Schedule, Is Mistaken

The Yankees' contention that the Court should merely assume the existence of a "reasonable" acceptance schedule, which would have resulted in acceptance of all of the Yankees' SNF by 1999, 2001, and 2002, see YA Br. 10, asks this Court to ignore the provisions within the Standard Contract that grant DOE the right to establish the rate, subject only to review by the Energy Board of Contract Appeals. As we explained in our initial post-trial brief, the SNF acceptance schedule provisions of the Standard Contract create a form of "alternative contract," providing DOE with the right to establish the acceptance schedule subject to a review only for abuse of discretion. Def. Br. 19-23. When contracts of that nature are breached, and no choice between the various available alternatives has yet been made, "the measure of damages . . . is the value of the alternative least onerous to the defendant." 11 W. Jaeger, Williston on Contracts § 1407, at 593 (3d ed. 1968) (emphasis added). Here, to the extent that the Yankees are asking this Court to add a "reasonable" schedule to the Standard Contract, the Court cannot identify a

- 15 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 16 of 53

"reasonable" schedule without reference to the nature of the contract provisions relating to schedule. To the contrary, any effort by the Court to establish a "reasonable" schedule, without identifying "the alternative least onerous to the defendant," would conflict with the nature of this contract. Because the Standard Contract does not create the obligations that the Yankees have asserted, the Yankees' requested "reasonable" schedule certainly does not constitute "the alternative least onerous to the defendant" and, therefore, cannot form the basis of causation for the Yankees' damages.6 C. Any Delay In The Yankees' Fuel-Out Dates Beyond Those About Which Mr. Graves Opined Defeats Causation 1. Any Delay In The Fuel-Out Dates Defeats Causation For The Yankees' ISFSI Construction

The causation evidence associated with the Yankees' damages claims for ISFSI construction, as presented to the Court at trial, was wholly dependent upon the fuel-out dates about which Mr. Graves opined. All of the testimony by the Yankees' witnesses in support of causation for the ISFSI construction was predicated upon those fuel-out dates. See Def's The Yankees also argue that, based upon the United States Court of Appeals for the Federal Circuit's decision in Roedler v. Department of Energy, 255 F.3d 1347 (Fed. Cir. 2001), the Court should implement the purpose of the NWPA in defining the acceptance schedule applicable to the Yankees' damages claims. YA Br. 11. However, as we established in our initial post-trial brief and our responses to the Yankees' proposed post-trial findings of fact, it was not the purpose of the NWPA to ensure that nuclear utilities would not be required to incur additional at-reactor storage costs after January 31, 1998. See also 42 U.S.C. § 10131 (identifying purposes of NWPA). Further, the NWPA only mandated that DOE's contracts for SNF disposal contain two specific provisions, neither of which was a requirement that DOE accept SNF at a rate sufficient to preclude utilities from incurring additional at-reactor storage after January 31, 1998. See 42 U.S.C. § 10222(a)(5). The remaining contract terms were left to DOE's discretion, and, as established in our initial post-trial brief, DOE did not include any such requirement in the Standard Contract. Accordingly, the Yankees' request that the Court refer to the NWPA to create obligations that do not otherwise exist in the Standard Contract does not affect this case. - 16 6

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 17 of 53

Responses to CYPFOF ¶ 103, YAPFOF ¶ 106, & MYPFOF ¶ 96. Not a single witness testified that the Yankees would not have constructed dry storage assuming, for example, a 2007 fuel-out date. Absent this evidence, the Yankees have failed to prove that their decisions to pursue dry storage were "caused" by DOE's delay, rather than by a separate decision to pursue dry storage simply because, even without the delay, SNF would remain on their property for several years. In addition to the absence of evidence from the Yankees establishing causation between DOE's breach and their decisions to pursue dry storage, the evidence affirmatively demonstrates that any delay in the fuel-out dates beyond those that Mr. Graves proposed would have resulted in the construction of ISFSIs by the Yankees, even assuming no delay by DOE. See, e.g., DPFOF ¶¶ 119.c (Yankee Atomic informing DOE that, barring grant of priority, an ISFSI would be constructed); DX 471 (DOE breach added only three years of additional on-site storage); 130132; and 283-299. Indeed, there is significant evidence that, assuming fuel-out dates under an OFF allocation schedule, each of the Yankees planned to construct an ISFSI and, in fact, would have constructed an ISFSI. DPFOF ¶¶ 283-299. For example, Yankee Atomic's decommissioning studies that assume timely DOE performance all also assume the construction of an ISFSI. See, e.g., DPFOF ¶¶ 284-286. Likewise, Yankee Atomic's goal to decommission its facility by 2007 (DPFOF ¶ 112), the Yankees' desires to promptly generate and dispose of lowlevel waste at Barnwell (DPFOF ¶ 293.a-d), the Yankees' desires to minimize costs associated with low-level waste disposal (DPFOF ¶ 293.e-h); their desires to utilize existing personnel in decommissioning efforts (DPFOF ¶ 295), and their desires to reduce decommissioning costs (DPFOF ¶ 292), among others, all support the conclusion that, barring an expedited fuel-out date,

- 17 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 18 of 53

the Yankees would have constructed ISFSIs even absent DOE's delay.7 Additionally, removal of SNF from the wet pool was cited as a requirement for site re-use by both Connecticut Yankee and Maine Yankee. DPFOF ¶ 296. Because the Yankees failed to prove that DOE was contractually obligated to remove their SNF by the dates that Mr. Graves proposed, their claims for ISFSI construction fail for lack of causation.8 This Court should reject the Yankees' fall-back position in their trial briefs that marginalize the relevance of Mr. Graves' testimony to their damages claims. The Yankees elected to pursue damages based upon an aggressive acceptance scheme, supported only by Mr. Graves' model. The Yankees presented no evidence of what their damages would have been, or what costs they would have had to have incurred regardless of any delay, had the fuel-out dates mandated by the Standard Contract been "2003 or 2007," YA Br. 27, or any later date. Because the Graves model provides no basis for defining contractually required fuel-out dates, the

The Yankees contend that there is "no evidence that, if DOE had commenced performance by January 1998, DOE would have delayed accepting Yankee Atomic's SNF for up to 20 years." YA Br. 29 (italics in original). The Yankees goes even further, calling such a concept "a figment of the government's imagination." Id. While causation is defeated assuming any date after 1999 for Yankee Atomic, 2001 for Connecticut Yankee, and 2002 for Maine Yankee (since all of the causation testimony that the Yankees' witnesses offered is based upon those dates), the Government introduced evidence from all three Yankees that demonstrates that each plaintiff assumed that DOE's acceptance could take as long as 20 years. See, e.g., DPFOF ¶¶ 110, 118, 127, 299. A 20-year acceptance schedule under OFF neither is unsupported nor is a figment of the Government's imagination. This contrasts with Mr. Graves' fuel-out dates ­ a litigation-driven conclusion ­ that find no support within the Yankees' historical documents. DPFOF ¶ 131. For the reasons set forth above, the Yankees cannot rely upon the alleged DOE program goal of no additional at-reactor storage after January 31, 1998, to establish causation. Moreover, the evidence demonstrates that the Yankees never assumed that this alleged program goal ­ which figures prominently in their damages claim ­ would result in an expedited fuel-out date in the "non-breach" world. See, e.g., DPFOF ¶¶ 110, 118, 127, 299. - 18 8

7

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 19 of 53

Yankees, by virtue of the risky litigation position that they took, have failed to satisfy their burden to prove causation. 2. Any Delay In The Fuel-Out Dates Defeats Causation For Operating And Maintenance Costs

The Yankees' causation for the operation and maintenance ("O&M") costs associated with their wet spent fuel pools, and even their ISFSI O&M costs, are wholly dependent upon the fuel-out dates that Mr. Graves defined. The Yankees' damages expert, Dr. Wise, recognized that the "existence . . . of all of the wet pool damages are dependent on the accuracy of [Mr. Graves'] non-breach fuel-out dates." Tr. 3329:9-14 (Wise). Even the Yankees admit that Mr. Graves "provided the only evidence presented at trial of a specific non-breach world pool-empty date." YA Br. 15. Quite simply, until all SNF would be removed from a site, the same O&M costs would have to be incurred to maintain the remaining SNF. Tr. 767:8-768:7 (Graves). Until the date by which DOE was obligated to remove all SNF arrives, the Yankees could not suffer any incremental O&M costs. Dr. Wise's testimony supports the conclusion that, barring proof of the 1999, 2001, and 2002 fuel-out dates, the Yankees have not established causation for their damages for wet pool O&M. Since it is clear that, under any extended fuel-out dates, DOE would not yet have been obligated ­ as of 2005 ­ to have completed removing SNF from any of the Yankees' sites, any award of damages for future O&M costs is unnecessary and, for the reasons discussed in our post-trial initial brief, unwarranted.

- 19 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 20 of 53

D.

The Yankees' Efforts To Establish Causation For "Mitigation" Activities By Reference To Actions In The 1980s And Early 1990s, Years Before The Actual Breach Of Contract, Ignores The Nature Of The Breach That The Yankees Are Claiming 1. The Court Has Not Concluded That The Yankees Satisfied Their Burden of Proving Causation For Pre-Breach Or Post-Breach Mitigation

The Yankees claim that they satisfied their causation burden when the Court "recognized the relationship between causation and mitigation" in one of its June 28, 2004 orders. YA Br. 7. The Yankees have misconstrued the Court's order. In the cited order, the Court was addressing the Government's motion in limine in which the Government was seeking to preclude evidence regarding the Yankees' damages that were inconsistent with its partial breach theory. Yankee Atomic Electric Company v. United States, No. 98-126, 2004 WL 1535688, at * 1 (Fed. Cl. June 28, 2004). Thus, the Court was required to decide whether the Yankees should be permitted to present evidence of their pre-breach damages at the trial that was scheduled to begin two weeks after issuance of the Court's order. While noting that the Yankees had not chosen to pursue a single theory of recovery, either partial breach or restitution, the Court concluded that it would not preclude the Yankees from submitting evidence of damages that would be recoverable pursuant to the restitution theory even if it were not recoverable upon a partial breach theory, specifically noting that it was not "prejudging whether or to what extent pre-1998 damages are appropriate or whether restitution may be granted." Id. at *5. The Court also stated that the Yankees would not be precluded from offering evidence regarding their reracking costs, which were incurred prior to 1998, despite the fact that such damages are inconsistent with a partial breach theory because doing so was

- 20 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 21 of 53

inconsistent with the Yankees' duty to mitigate damages. Id. at *7 - *8. Consequently, the Yankees were not precluded from presenting evidence of damages incurred prior to DOE's failure to commence acceptance in 1998. Id. However, the Court never suggested that, by allowing the Yankees to submit evidence regarding their reracking costs at trial, the Yankees had already established causation. Indeed, in distinguishing the decision in Indiana Michigan, upon which the Government relied to preclude evidence regarding the Yankees' plaintiff's pre-breach damages, this Court specifically stated that the plaintiff in that case had "failed to establish that [DOE's] breach was the reason any costs, either pre- or postbreach were incurred [and that] . . . the [Indiana Michigan] court's discussion and rejection of any damages incurred before December 1998 was dicta." Id. at *8. Similarly, in discussing the decision in Tennessee Valley Authority, this Court noted that a utility can establish damages only "to the extent that [the utility] is able to show at trial that it has incurred damages as a result of DOE's failure to act . . . ." Id. at *6 (quoting Tennessee Valley Authority v. United States, 60 Fed. Cl. 665, 674 (2004)). Therefore, far from concluding, as the Yankees suggest, that this Court has already found that the Yankees have established causation simply because the Court decided to allow the Yankees to submit evidence regarding their reracking costs, this Court specifically stated that, to establish their damages, the Yankees must submit evidence that their costs "are reasonably certain and caused by" the breach. Id. at *2 (emphasis added).

- 21 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 22 of 53

2.

In Evaluating Pre-Breach Mitigation Claims, The Court Must Recognize That, Prior To An Actual Breach, The Yankees Had No Obligation To Mitigate Their Damages

In prior briefing, we have discussed in detail the reasons that plaintiffs are not entitled to recover pre-breach damages in a partial breach of contract case. Nevertheless, the Court permitted the Yankees to present evidence regarding pre-breach damages. Accordingly, to the extent that the Court considers whether pre-breach damages were "caused" by DOE's later breach, it must place the mitigation concept into proper context. In their post-trial briefs, the Yankees argue that all of their pre-1998 activities were undertaken in an effort to mitigate the effects of DOE's impending breach. YA Br. 8. Yet, as we explained in our initial post-trial brief, the duty to mitigate does not arise until there has been an actual breach of contract. Def. Br. 6970 (discussing Reliance Cooperative Corp. v. Treat, 195 F.2d 977 (8th Cir. 1952)). Accordingly, to establish that DOE's 1998 breach somehow "caused" the Yankees to incur costs prior to 1998, the Yankees must establish that they were reasonably compelled to incur those costs because of the breach. However, as we explained in our initial post-trial brief, the pre-breach reracking claims that Connecticut Yankee and Maine Yankee have presented are unrelated to DOE's delay. Def. Br. 69-70 & n.21. To determine whether an attempt at mitigation was appropriate in cases involving post-breach activities, courts consider whether a reasonable person, in light of the known facts and circumstances, would have taken steps to avoid certain damages. Koby v. United States, 54 Fed. Cl. 493, 497 (2002). Nevertheless, plaintiffs must mitigate any potential damages "at the least cost to the defendant." LaSalle Talman Bank, F.S.B. v. United States, 45 Fed. Cl. 64, 111 (1999) (quoting Northern Helex Co. v. United States, 207 Ct. Cl. 862, 524 F.2d - 22 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 23 of 53

707, 713 (1975)), rev'd on other grounds, 317 F.3d 1363 (Fed. Cir. 2003). This principle applies the general rule that, following a breach, "a party cannot recover damages for loss that he could have avoided by reasonable efforts." Robinson v. United States, 305 F.3d 1330, 1333 (Fed. Cir. 2002) (quoting Restatement (Second) of Contracts § 350, cmt. b) (emphasis in original). The least-cost principle "precludes rewarding a plaintiff for undertaking a form of mitigation that is considerably more costly than other available means of mitigation." LaSalle, 45 Fed. Cl. at 111. "It is a mistake to think that by merely placing the `mitigation' label on any expense incurred an injured party is entitled to recover it. Plaintiff cannot escape the burden of proving that the losses sought to be avoided were caused, or would have been caused, by defendant's breaches." Affiliated Foods, Inc. v. Puerto Rico Marine Mgmt., 645 F. Supp. 838, 840 (D.P.R. 1986). As we discussed in our post-trial brief, the decisions by Maine Yankee and Connecticut Yankee to shut down their reactors prematurely in the late 1990s rendered their reracking efforts ­ and the considerable costs associated with those efforts ­ unnecessary. Def. Br. 69-70; see Response to CYPFOF ¶ 109-128; Response to MYPFOF ¶ 103-128. The evidence adduced at trial established that Connecticut Yankee and Maine Yankee should have waited to rerack their pools until they needed the space, given that, had they done so, they would never have reracked. See Order, Yankee Atomic, 2004 WL 1535688 at *6 (June 28, 2004). 3. The Yankees' Arguments That Their ISFSI Construction Costs Are Related To An Effort To Mitigate Are Unfounded

For the reasons explained above, the Yankees' ISFSI construction claims, much of which pre-date 1998, fail because they are not tied to DOE's delay. Instead, the costs were incurred as a result of independent decisions to build ISFSIs regardless of DOE's delay. This Court has

- 23 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 24 of 53

recognized that the Yankees cannot recover the cost of building their ISFSIs to the degree that those efforts were more expensive than the wet storage alternative: [I]f one accepts the plaintiff's position as to the contract requirement for spent fuel removal, the cost of storage after the assumed removal comprises breach damages. It is assumed that storage costs contract damages would be premised on the extant wet storage facilities in the absence of mitigation activity. Presumably, plaintiff's case is premised on shifting to dry storage as a mitigation activity. If, however, dry storage will cost more than continuing the wet storage which existed when the contract was breached, a question is raised as to the government's liability for this additional cost. . . . Yankee Atomic Electric Company v. United States, No. 98-126, slip op. at 2-3 (Fed. Cl. Dec. 24, 2003). Further, this Court has addressed the relationship between causation and mitigation: Moreover, as the submissions note, factors other than the pure need for spent fuel storage during the breach period are apparently present in a decision to shift to dry storage, so that any dry storage cost in excess of that for continued wet storage, if any, may be attributed to factors other than the government's breach of contract. Id. at 2. As we have demonstrated numerous times, the Yankees did not build their ISFSIs because of the breach - they chose to build their ISFSIs for reasons that were unrelated to the breach. While the Yankees have argued that their ISFSIs were constructed in an attempt to mitigate damages, it is abundantly clear that the capital investment made by the Yankees in their ISFSIs cannot be justified by their savings in O&M costs. Specifically, in their proposed findings of fact, Yankee Atomic claims to have incurred annual costs totaling $9.1 million to operate its wet pool (YA PFOF ¶ 142), but also seeks $67.14 million for the cost of operating its ISFSI from June 2003 to 2010 (translating into annual operating costs of $10.3 million). YA PFOF ¶ 141. After 2010, that annual cost of ISFSI O&M

- 24 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 25 of 53

allegedly declines to $6.5 million.9 Maine Yankee has claimed $4.67 million per year to operate its wet pool (MY PFOF ¶ 159), but also seeks annual ISFSI operating costs of $9.8 million (MY PFOF ¶ 158), declining to $6.85 million after 2010. MY PFOF ¶ 177. Finally, Connecticut Yankee has claimed $10.7 million per year to operate its wet pool (CY PFOF ¶ 157) while seeking ISFSI operating costs of $93.58 (an annual operating cost of $15.6 million) (CY PFOF ¶ 156), declining to $10.2 million after 2010. CY PFOF ¶ 173. Based upon the difference between the O&M costs for continuing wet pool versus those for ISFSI operations, none of the three Yankees shows a material reduction between the wet pool and ISFSI O&M costs until 2011. Beginning in 2011, the difference between the annual O&M costs for wet storage versus dry storage at Yankee Atomic is $2.6 million per year and at Connecticut Yankee is $.5 million. Dividing the ISFSI capital costs by the annual O&M savings after 2010 reveals that it would take 30 years before Yankee Atomic's O&M cost savings would exceed its capital costs and over 145 years for Connecticut Yankee.10 There is no break-even point for Maine Yankee because Maine Yankee's alleged ISFSI O&M costs always exceed the annual costs of wet pool O&M. Furthermore, those computations are based upon nominal dollars. Since the relative cost of money spent many years from now is, upon a present-value basis, much less than the money spent in the past and the short-term, the O&M savings are even

All three of the Yankees have reserved the right to seek compensation above their current post-2010 ISFSI O&M estimates in future litigation. Yankee Atomic alleges its ISFSI capital costs were $76.99 million. YA PFOF ¶ 140. $76.99 million divided by $2.6 million/year = 29.61 years. Connecticut Yankee's alleged ISFSI capital costs were $72.16 million. CY PFOF 154. $72.16 million divided by $.5 million/year = 144.32 years. - 25 10

9

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 26 of 53

less when compared upon an actual basis.11 Moreover, this extended recovery period is required even if one did not wholly accept the Yankees' alleged O&M numbers. 12 Thus, any analysis of the Yankees' damages demonstrates that the construction of their ISFSIs did not successfully mitigate their damages. If the Court were to require the Government to pay the Yankees' ISFSI construction costs, there would be no savings unless the Government fails to accept all of the Yankees' SNF by 2040, or beyond. III. THE DAMAGES THAT THE YANKEES SEEK WERE NOT FORESEEABLE AT THE TIME OF CONTRACTING A. The Court Must Resolve Foreseeability By Reference To The Actual Terms Of The Standard Contract Itself

In addition to proving causation, the Yankees must also prove that the damages they seek were foreseeable at the time of contracting. "Damages are not recoverable for loss that the party in breach did not have reason to foresee as a probable result of the breach when the contract was made." Restatement (Second) of Contracts § 351(1) (1981). In this Court, the Yankees must establish not only that their claimed damages were "foreseeable to the party in breach at the time of contract formation," but that "both the magnitude and type of damages were foreseeable" as

The extent of the impact that a present-value analysis would have upon this computation varies depending upon the particular discount rate assumed, but the number of years required to break-even can only increase. Applying the analyses of Mssrs. Johnson and Abbot, beginning in 2011, the difference between the annual O&M costs for wet storage versus dry storage at Yankee Atomic is $2.4 million per year, at Maine Yankee it is $2.2 million, and at Connecticut Yankee it is $2.7 million. Tr. 6522:6-11, 6382:2-12, 6607:16-6608:4 (Johnson); Johnson Demonstrative 62a. Applying those annual savings to the Yankees' alleged ISFSI capital costs, means that Yankee Atomic would break even in 32 years ($76.99/2.4), Maine Yankee would break even in 38 years ($83.72/2.2), and Connecticut Yankee would break even in 27 years ($72.16/2.7). YA PFOF ¶ 140, MY PFOF ¶ 157, CY PFOF ¶ 154. - 26 12

11

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 27 of 53

well. Landmark Land Co. v. United States, 256 F.3d 1365, 1378 (Fed. Cir. 2001); see Northern Helex Co. v, United States, 207 Ct. Cl. 862, 524 F.2d 707, 714-15 (1975); Bank United of Texas FSB v. United States, 50 Fed. Cl. 645, 654 (2001), rev'd on other grounds, 2003 WL 22177282 (Fed. Cir. Sept. 22, 2003). The "mere circumstance that some loss was foreseeable, or even that some loss of the same general kind was foreseeable, will not suffice if the loss that actually occurred was not foreseeable." Restatement (Second) of Contracts § 351(1) cmt. a (1981). The Yankees have failed to meet their burden of establishing foreseeability here. In determining whether the damages that Yankee Atomic seeks were foreseeable, the Court must begin from the premise that "the boundaries of contract liability are determined by the contract itself; the scope of the risks assumed by the defendant delineate the scope of [its] liability," and, therefore, its "liability originates in contract and is thus bounded by contract." 3 D. Dobbs, Law of Remedies § 12.4(5) (2d ed. 1993); see Hi-Shear Tech. Corp. v. United States, 356 F.3d 1372, 1378 (Fed. Cir. 2004) (logical starting point for damages is understanding of breaching party's obligations under contract). As a result, to identify the type of damages that were "foreseeable" here, this Court must look to the language of the Standard Contract and to the scope of DOE's obligations under that contract. Since the Standard Contract was an industry-wide contract (see DPFOF ¶ 21), DOE could not begin SNF acceptance from all utilities on January 31, 1998. Instead, as previously discussed, the Standard Contract sets forth a mechanism for defining an acceptance queue, which DOE was required to implement in performing its contractual obligations, based upon the age of each contract holder's SNF. See DPFOF ¶¶ 53, 89 (discussing "oldest fuel first" acceptance queue ("OFF")). While the contract allows DOE to accept fuel outside of the OFF queue (see - 27 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 28 of 53

DX 6, 7, 8 at Art. VI.B.3 (priority), Art. V.D. (emergency), Article V.E. (exchanges)), the OFF queue is the contractual basis upon which the order of SNF acceptance is determined. DPFOF ¶¶ 53, 89. Accordingly, it is the application of the OFF acceptance queue that dictates the scope of DOE's obligations and liabilities and the foreseeability of the Yankees' alleged damages. To the extent that the Yankees argue that they should recover damages based upon a right to priority acceptance for shutdown reactors that could be obtained (a) only through DOE's exercise of discretion, (b) upon a right to exchange SNF acceptance allocations that DOE had the unilateral contractual right to deny, or (c) upon an acceptance scenario that requires the abandonment of SNF acceptance based upon an OFF acceptance allocation, the Yankees have not established how, under the terms of the Standard Contract, DOE could have foreseen that the Yankees would have such expansive rights, in conflict with the terms of the Standard Contract. It simply was not foreseeable at the time the Standard Contract was executed that OFF acceptance obligations could be converted into priority acceptance requirements that substantially expedite the Yankees' fuel shipments to DOE and, therefore, substantially increase DOE's liabilities without an express grant of priority by DOE. B. There Is No Contract Requirement Eliminating Additional At-Reactor Storage Costs After January 31, 1998

The Yankees' foreseeability argument hinges upon this Court's adoption of a contractual requirement that DOE accept SNF in a manner that would prevent contracting utilities "from having to incur additional costs of on-site storage of SNF after January 31, 1998." See YA Br. 4. The Yankees argue that, because they each constructed a dry storage facility, and because the Standard Contract's "goal" was to prevent such construction, foreseeability and resultant damage

- 28 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 29 of 53

have been proven. The Yankees' argument fails, however, because, as previously discussed in our initial post-trial brief and above, there is no provision in the Standard Contract that requires DOE to accept SNF in a manner that prevents contracting utilities from incurring additional costs associated with on-site SNF storage after January 31, 1998. See DPFOF ¶ 19. Accordingly, the Yankees cannot establish that, under the terms of the Standard Contract, it was foreseeable at the time of contract award that DOE would be obligated to satisfy such a requirement. Further, as previously discussed, the Yankees have mischaracterized DOE's past program goals, eliminating the "in the aggregate" limitation upon DOE's hope to eliminate the need for additional out-of-pool at-reactor storage. See DX 23. If the Court considers DOE's actual program goal, rather than the Yankees' modification of it for litigation purposes, the Yankees' foreseeability argument disintegrates when the performance requirements needed to achieve that past program goal are examined in 1983 ­ at the time of contracting ­ and, in 1999, when the Yankees' expert reports were prepared. As recently as 1991 ­ eight years after the alleged program goal was articulated ­ a rate of only 900 MTUs per year would have, in the aggregate, achieved the program goal. DX 23 (Yankees' expert witness, Dr. Bartlett, approving 1991 ACR and finding that rate of acceptance contained therein would achieve the program goal). As a result, at the time of contract formation, a relatively small rate of acceptance could have achieved the stated program goal (even if the alleged "goal" included shutdown reactors, as the Yankees contend here). However, by 1998, 12 utilities had shutdown prematurely (Tr. 948:25-949:4 (Graves)), including eight reactors that shutdown in the mid- to late 1990s that possessed 2,500 to 2,600 MTUs of SNF in their wet pools. DPFOF ¶ 196.e. Assuming that the program goal advanced by the Yankees dictated DOE's performance obligations, meeting that goal in 1998 - 29 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 30 of 53

would require massive SNF acceptance in 1998. DPFOF ¶¶ 125, 126, & 128; DX 218. Taken even further, if 30 reactors shutdown prematurely this year, the "program goal" advanced by the Yankees would require far higher rates than proposed by the Yankees in this litigation. The imposition of alleged "goals" as contract requirements converts fixed performance obligations into ever-changing performance requirements. The Yankees have not established how the number of shutdown reactors or the scope of the need for SNF acceptance to preclude any additional at-reactor storage in 1998 was foreseeable in 1983. C. The Magnitude Of The Yankees' Claims Evidences The Lack Of Foreseeability

As set forth above, the Yankees must establish that "both the magnitude and type of damages were foreseeable." See Landmark Land, 256 F.3d at 1378; see Northern Helex, 524 F.2d at 714-15; 5 A. Corbin, Corbin on Contracts § 1012, at 88 (1964) (to have been foreseeable, "the injury that occurs must be one of such a kind and amount as a prudent man would have realized to be a probable result of his breach."). Where there is an "extreme disproportion between the loss and the price charged by the party whose liability for that loss is in question, . . . [t]he fact that the price is relatively small suggests that it was not intended to cover the risk of such liability." Restatement (Second) of Contracts § 351(1) (1981). Consistent with that proposition, this Court has rejected lost profits claims upon the grounds that, although foreseeable as a general matter, "the magnitude of damages which the lost-profit models purport to show was not reasonably foreseeable." Bank United of Texas FSB v. United States, 50 Fed. Cl. at 654.

- 30 -

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 31 of 53

Here, the magnitude of the Yankees' alleged damages in relation to the contract prices that they paid (or that they still must pay) for all of DOE's program costs, including the licensing and construction of Yucca Mountain, the cross-country transportation of Yankee Atomic's SNF, the permanent emplacement of that SNF in Yucca Mountain, and at least 10,000 years of storage and monitoring, demonstrate that the damages sought in these cases were not foreseeable. For example, Yankee Atomic has paid a total of $22 million to DOE. Yet, in this litigation, Yankee Atomic seeks an award of damages through 2010 of nearly $185,000,000 ­ more than eight times the monies that it has paid to DOE under the Standard Contract ­ for the construction of dry storage, transportation of SNF less than one mile to the ISFSI, and storage costs through 2010. YAPFOF ¶¶ 4, 136. Yankee Atomic further seeks a finding that it is entitled to recover at least $6.5 million in damages every year beyond 2010 that it stores SNF on-site (YAPFOF ¶ 158) ­ an amount that adds an additional $22 million to damages, in nominal dollars, ever 3.5 years. In addition to the seemingly unchecked liability, DOE remains obligated to perform under the Standard Contract ­ DOE still must license and construct Yucca Mountain, still must transport Yankee Atomic's SNF from Massachusetts to Nevada, still must emplace that SNF in Yucca Mountain, and still must store and monitor that SNF for at least 10,000 years. YAPFOF ¶ 164.13

Connecticut Yankee has paid $41 million (CYPFOF ¶ 1) and owes another $48.7 million in principal. DPFOF ¶ 319. In this litigation, Connecticut Yankee seeks damages totaling $198 million (CYPFOF ¶ 150), in addition to damages after 2010 accruing at an annual rate of $10.2 million (CYPFOF ¶ 173) and DOE performance of its contractual obligations. Maine Yankee has paid $65 million (MYPFOF ¶ 1) and owes another $50.4 million in principal. In this litigation, Maine Yankee seeks damages totaling $159.7 million (MYPFOF ¶ 152, in addition to damages after 2010 accruing at an annual rate of $6.85 million (MYPFOF ¶ 177) and DOE performance of its contractual obligations. - 31 -

13

Case 1:98-cv-00126-JFM

Document 899-4

Filed 01/13/2005

Page 32 of 53

The magnitude of the Yankees' claims in relation to the amounts that they have paid to DOE belies any contention that their damages were foreseeable. This Court should find that the Yankees' damages were not foreseeable at the time of contracting ­ both in type and in magnitude ­ because the Yankees' damages are predicated upon the imposition of extra-contractual obligations and because the exorbitant amount of the Yankees' claims could not have been foreseen at the time of contracting.14 IV. THE YANKEES HAVE FAILED TO ESTABLISH THEIR ALLEGED DAMAGES WITH REASONABLE CERTAINTY

As previously discussed, the Yankees conclude that "causation follows from any reasonable [acceptance] schedule" and argue that they have established causation regardless of whether this Court finds that DOE would have completed acceptance of the Yankees' SNF in "1999, or 2003 or 2007." See YA Br. 27. Focusing upon causation, the Yankees completely ignore the requirement that their damages be established with reasonable certainty and that they have the burden of proof upon this issue. If this Court does not accept the fuel-out dates that Mr. Graves proposes, the Yankees' entire damages claim fails based upon the Yankees' failure to prove their damages with reasonable certainty.

A separate foreseeability question is raised by the Yankees' decisions to shutdown prematurely. In 1983, Yankee Atomic was licensed to operate until July 2000 (DPFOF ¶ 273), Connecticut Yankee was licensed until 2007 (DPFOF ¶ 280), and Maine Yankee was licensed until October 2008. DPFOF ¶ 277. Even under the Yankees' damages theories, as of 1983, DOE would hav