Case 1:99-cv-00447-CFL
Document 242
Filed 12/07/2005
Page 1 of 1
IN THE UNITED STATES COURT OF FEDERAL CLAIMS No. 99-447C No. 03-2626C (Filed: December 7, 2005) ) ) Plaintiff, ) ) v. ) ) UNITED STATES, ) ) Defendant. ) ____________________________________) ) ENTERGY NUCLEAR GENERATION ) CO., ) ) Plaintiff, ) ) v. ) ) UNITED STATES, ) ) Defendant. ) ) ORDER The court acknowledges the receipt of the Joint Status Report, filed on December 5, 2005, regarding a plan and schedule for the Boston Edison portion of these cases as consolidated for a limited purpose. A status conference shall be held in these cases to discuss the matters addressed in the Joint Status Report on December 20, 2005, commencing at 2:00 p.m., at the National Courts Building, 717 Madison Place, N.W., Washington, D.C. The courtroom in which the status conference will be held shall be posted in the lobby of the building. It is so ORDERED. s/ Charles F. Lettow Charles F. Lettow Judge BOSTON EDISON COMPANY,