Free Proposed Findings of Uncontroverted Fact - District Court of Federal Claims - federal


File Size: 41.9 kB
Pages: 6
Date: November 5, 2007
File Format: PDF
State: federal
Category: District
Author: unknown
Word Count: 1,190 Words, 7,511 Characters
Page Size: Letter (8 1/2" x 11")
URL

https://www.findforms.com/pdf_files/cofc/21048/36-1.pdf

Download Proposed Findings of Uncontroverted Fact - District Court of Federal Claims ( 41.9 kB)


Preview Proposed Findings of Uncontroverted Fact - District Court of Federal Claims
Case 1:06-cv-00146-TCW

Document 36

Filed 11/06/2007

Page 1 of 6

IN THE UNITED STATES COURT OF FEDERAL CLAIMS TETRA TECH EC, INC., Plaintiff, v. THE UNITED STATES, Defendant. ) ) ) ) ) ) ) ) )

No. 06-146C (Judge Wheeler)

DEFENDANT'S PROPOSED FINDINGS OF UNCONTROVERTED FACT Defendant, the United States, pursuant to Rule 56(h)(2) of the Rules of the United States Court of Federal Claims ("RCFC"), respectfully submits these proposed findings of uncontroverted fact in response to to plaintiff's motion for summary judgment. DPFUF No. 1: Contract No. DACA87-00-D-0039 ("Contract") was modified four times, which brought the total contract price to $3,074,731.29. Contracting officer's final decision dated November 30, 2005 (Ex. 1 to PPFUF) at p. 1. DPFUF No. 2: Tetra Tech's certified claim consisted of four parts: (1) $1,119,723.25 for clearance of UXO in excess of 21 UXO-like anomalies per acre; (2) $26,695.24 for increased level of effort by a senior geophysicist; (3) $26,695.24 for increased level of effort to investigate 37mm projectiles in Range 1; and (4) $15,308.88 for costs resulting from extreme weather delays. Contracting officer's final decision (Ex. 1 to PPFUF) at p. 2; certified claim dated September 6, 2005, which is Tab F to the final decision, and portions of which are attached to defendant's proposed findings. DPFUF No. 3: In her final decision, the contracting officer stated that the primary asserted basis of the claim was Tetra Tech's purported belief that the number of anomalies it was actually required to excavate was more than 400 percent above the number it had expected to

Case 1:06-cv-00146-TCW

Document 36

Filed 11/06/2007

Page 2 of 6

excavate when the contract was awarded. Contracting officer's final decision (Ex. 1 to PPFUF) at p. 2 DPFUF No. 4: During the proposal phase, prospective bidders submitted numerous questions that were answered by the Corps. One of the questions was whether the contractor would be expected "to dig all potential UXO items" or only those with certain characteristics. The Corps responded: "All potential UXO items." Contracting officer's final decision (Ex. 1 to PPFUF) at p. 2. DPFUF No. 5: During the proposal phase, a prospective bidder asked whether the Corps would provide an anomaly-per-acre assumption for the project. The Corps answered: "The Contractor should assume 20 UXO/OE items per acre." Contracting officer's final decision (Ex. 1 to PPFUF) at p. 3. DPFUF No. 6: During the proposal phase, a prospective bidder asked if bidders should assume that 20 anomalies per acre would, upon excavation, be identified as UXO/OE1 and require disposal. The Corps answered, "Yes." Contracting officer's final decision (Ex. 1 to PPFUF) at p. 3. DPFUF No. 7: During the proposal phase, a prospective bidder asked: "What estimated number of anomalies per 100 foot square grid, or other unit area, should contractors use to estimate anomaly reacquisition and remediation efforts?" The Corps initially answered: "The Contractor should assume 200 anomalies per acre, and 20 UXO/OE items per acre." The Corps later supplemented this answer with a clarification:

1

"OE" refers to ordnance and explosives. 2

Case 1:06-cv-00146-TCW

Document 36

Filed 11/06/2007

Page 3 of 6

Clarification to bidding based on excavating 200 anomalies per acre: A quantity of 200 anomalies per acre was included in previous correspondence. This suggests that the requirement is for (309 acres x 200 anomalies =) 61,800 excavations. That is not the intent or objective. The requirement is to remove all reasonably detectable UXO and UXO-like items. Based on [the Corps'] knowledge of the site and to provide an even basis for Proposal preparation purposes, the Contractor should assume there exists in the ground (below the surface) approximately 20 UXO or UXOlike items per acre. If the Contractor's false alarm ratio is, say 9:1, then 200 excavations would be required to recover 20 UXO or UXO-like items. The 200 per acre number is simply an illustration of the design process we would use to plan this activity. The Contractor's false alarm ratio may be lower or higher. Each Contractor should base their bid on their own process and cost to recover all detectable UXO or UXO-like objects under the assumption that there will be approximately 20 such items per acre. Contracting officer's final decision (Ex. 1 to PPFUF) at p. 3. DPFUF No. 8: In her final decision, the contracting officer identified several problems with Tetra Tech's performance of the Contract. Those problems included the following: · Tetra Tech's geophysicist apparently chose not to apply all of the applicable criteria (size, mass, and composition) to an anomaly before identifying the anomaly as one that required excavation. As a result, Tetra Tech excavated an excess number of false alarms or false positives. · Although the contract and Tetra Tech's work plan required ongoing comparisons of actual and predicted results, Tetra Tech apparently waited until excavations were complete before it compared predicted results with actual results. · Tetra Tech's decision to dig over 24,000 anomalies (102 anomalies per acre), without incorporating the required feed back process, was a corporate decision. 3

Case 1:06-cv-00146-TCW

Document 36

Filed 11/06/2007

Page 4 of 6

"The fact that this resulted in an extremely large set of anomalies to dig was [Tetra Tech's] risk, not a differing site condition." Contracting officer's final decision (Ex. 1 to PPFUF) at pp. 5-7.. DPFUF No. 9: In her final decision, the contracting officer stated that, in response to Tetra Tech's request for an equitable adjustment, the "[G]overnment, in an effort to reach resolution, decided to allow some compensation . . . ." Contracting officer's final decision (Ex. 1 to PPFUF) at p. 9. DPFUF No. 10: In her final decision contracting officer stated that overall, Tetra Tech was entitled to an equitable adjustment of $341,482.23, broken down as follows: A. Clearance of UXO greater than 21 UXO-like anomalies per acre. Of the $1,119,723.25 claimed, I find that you are entitled to $309,045.23. B. Increased level of effort for senior geophysicist. Of the $26,695.24 claimed, I find that you are entitled to zero dollars. C. Increased level of effort for 37mm in Range 1. Of the $26,695.24 claimed, I find that you are entitled to $19,333.00. D. Lost days associated with extreme weather. Of the $15,308.88 claimed, I find that you are entitled to $13,104.00. Contracting officer's final decision (Ex. 1 to PPFUF) at p. 9.

4

Case 1:06-cv-00146-TCW

Document 36

Filed 11/06/2007

Page 5 of 6

Respectfully submitted, PETER D. KEISLER Assistant Attorney General JEANNE E. DAVIDSON Director STEVEN J. GILLINGHAM Assistant Director s/ Roger A. Hipp ROGER A. HIPP Trial Attorney Commercial Litigation Branch Civil Division U.S. Department of Justice Attn: Classification Unit 8th Floor 1100 L Street, N.W. Washington, D.C. 20530 Tele: (202) 307-0277 Fax: (202) 307-0972 November 5, 2007 Attorneys for Defendant

5

Case 1:06-cv-00146-TCW

Document 36

Filed 11/06/2007

Page 6 of 6

CERTIFICATE OF SERVICE I hereby certify that on this 5th day of November, 2007, a copy of the foregoing "DEFENDANT'S PROPOSED FINDINGS OF UNCONTROVERTED FACT" was filed electronically. I understand that notice of this filing will be sent to all parties of record by operation of the Court's electronic filing system. Parties may access this filing through the Court's system.

s/ Roger A. Hipp