Case 1:06-cv-00418-NBF
Document 35
Filed 04/02/2008
Page 1 of 2
In the United States Court of Federal Claims
No. 06-418C (Filed: April 2, 2008)
* * * * * * * * * * * * * * * * * * HOH RIVER TIMBER COMPANY, * * Plaintiff, * * v. * * THE UNITED STATES, * * Defendant. * * * * * * * * * * * * * * * * * * *
ORDER ON MOTION The court is in receipt of the parties' joint status report, filed March 28, 2008, indicating that they have reached a tentative settlement. The parties are currently negotiating the final terms of the agreement and, therefore, request an additional 30 days to finalize the settlement agreement. The parties' request for additional time is GRANTED. The above-captioned case remains STAYED. The parties shall file a joint status report by Wednesday, April 30, 2008. IT IS SO ORDERED.
s/Nancy B. Firestone NANCY B. FIRESTONE Judge
Case 1:06-cv-00418-NBF
Document 35
Filed 04/02/2008
Page 2 of 2