Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 1 of 30
IN THE UNTED STATES DISTRICT COURT FOR THE DISTRICT OF DELAWARE
DONALD M. DUR
CONTRACTING , INC. Plaintifvs.
CITY OF NEWAR , et aI. Defendants
and
CITY OF NEWARK Third-Party
Plaintifvs.
DONALD M. DUR CONTRACTING , INC. FEDERAL INSURCE COMPANY AND URS CORPORATION Third-Party Defendants
Case No. 04- 0
163- GMS
APPENDIX TO PLAITIFF' S MOTION FOR RELIEF FROM INTENTIONAL DESTRUCTION OF DOCUMENTATION GENERATED BY THE RESIDENT PROJECT REPRESENTATIVE
Powell, Trachtman , Logan , Carrie &
Lombardo , P.
Paul A. Logan Delaware Supreme Cour il #3339
David T. Bolger Pennylvana Bar No. 4 7327
Admitted
Pro Hac Vice
475 Allendale Road , Suite 200 Kig of Prussia , PA 19406 Telephone: 610- 354- 9700 Telefacsimle: 610- 354- 9760
Attorneys for Plaitiff
KOP:346392v1 3514-
............. ......
Case 1:04-cv-00163-GMS Document 200 Filed 08/22/2006
............... .
...... ... ........
Page 2 of 30
TABLE OF CONTENTS
Document
Pa!!e
Complaint................................................................................................ ...
Answer, Counterclaim and Thd
Par Complaint of Defendants City of Newark................. A-
Selected Portions of Joseph R. Kula s deposition June 13 2006... .... ..... ......
Thrd- Pary Complaint of Defendant City of Newark dated
URS Corporation s Answer and Counterclaim to Third Par
"""""""""" A-
Complaint....................... .
I03
l 09
Selected Portions of Glenn R. Bowen
s deposition April 13
, 2006.......... ......................
Request for Production of Documents (Set I) Directed to the City of Newark
KOP:346393vl 3514-
..
'I't tl'$v.
:'J'J) c
'A1 cover s
Ll V
lL LUV EK
J-Y
upplement the filin serVice o pleadings or other I?aprs required taw, except as provided by local rules of court. TIus form approved by the Judicial Conference of the Umted States In September 1974 , of the Clerk of Court for the purpose of initiating the civil docket sheet. (SEE INSTRUCTIONS ON TIE REVERSE OF THE FORM.IS requITed for the
Case the infolmtion 1:04-cv-00163-GMS neither replace n eet and ted herein
HJ:Kr Document 200 Filed 08/22/2006
g -,
*.
':
'$
a 4 -3 a 30 6 3 Page of 1
I. (a) PLAITIFFS DONAL M. DURKIN CONTRACTING, INC.
1310 Industrial Boulevard, Suite 200
DEFENDANTS CITY OF NEWARK, HAOLD F. GODWn
JOHN H. FARRELL, IV , JERRY CLIFTON, KAL G. KABACHER, DAVID J. ATHEY, J. OSBORNE, JR., CHRISTINA REWA, URS CORPORATION
Southampton, PA 18966
(b) County of Residence
FR
of First Liste Plaintiff BUCK
(EXCEPT IN U. S.
(c) Attorney
Paul A. Logan, .
s (Finn Name, Address
Powell Trachtman Logan CarrIe & Lombardo
Kin of Prussia PA 19406 610
n. BASIS
475 A1lendale Road,
OF JUSDICTION
Esquire
, and Telephone Number)
Suite. 200,
PLAIN CASES)
County ofResidenc
NOTE: IN
LA
(I U. S. PLAINF CASES ONLY) CONDEMNATION CASES, USE THE LOCATION OF THE
of First Lited NE CASTLE
LAN INOLVED.
Attorneys (If Known)
Qf"
354-970
(place an "X" in One Box Only)
m. CITNSHI OF PRICIPAL P ARTIES(place an "X" in O
'l.l .
S. Governmet Plaintiff
o3
(For Diversity Cases Only) and o
D I
Incorporated or Prncipal
Federl Question
(U. S. Governnt Not a Par)
Citizen of This State DI
o 2 U. S. Goverment
Defendat
Diversity (Indicate CitiZenship of Pares in Item
Citin of Another
State
020
D 3
DEF\J
x fO
Plaiti
dat)
DEF
of Business In Ths State
and
XI 4
Incororte
Principal Plac
5 D
of Business In Another State
Foreign Nation
o 6
v. NATU OF
CONTRACT
SUIT.
(Place an "X"
in One Box Onlv)
TORTS
FORFITUR/PENAL TY
BANKRUPTCY
422 Appel 28 USC 158
InurCe 120 Mare
11 0
130 Miler Act
OTHER STATUTES
0 400 Sta Reapportonmnt 0 410 Antitrt
0 0 0 0 430 Bank and 450 Rates/etc. 460 Deporttion 470 Racketer Infuenced and
PERSONAL INJURY
3 IO Ailaue
PERSONAL INJURY
362
PersnallIur
Prouct Uabilty
610 Agrcultue
620 Other Food & Drug 625 Drug Related Seizure
140 Negotile
Instnnt
315 Airlae Product
Moo Malpractice
365 Persona Injur
Libility
320 Assault, Libel & Slander
330 Federal Employers
423 Withdrwal
28 USC 157
of Propert 21 USC
630 Liquor Laws
ISO Recvery of Overpaymnt
CornceCC
Bang
& EnorcementofJudgmnt
-. t 51
152 Recve ofD"fuulted
Stuent Loans
MOOca Act
0 368 Asbestos Personal
Injur Product
640 R.R. & Truk
650 Airline Regs.
660 Occupational
PROPERTY RIGHT
820 Copyrhts
830 Patent
Liilty
340 Marie
345 Mare Product Liability 350 Motor Vehicle 355 Motor Vehicle Product Liability
360 Oter Persona Injur
Libilty
PERSONAL PROPERTY
0 370
Other Fraud
Corrt Orgtions
0 810 Selective Servce 0 850 Secwities/Comrditiesl
0 875
(EcI. Vetera)
153 Recvery of Overpaymnt
of Veteran s Benefils
o 160 Stocolders ' Suils
at 190 Other Contrct
rf 195 Contrct Produc Libility
371 Tru
in Ledig
Safety/Health 690 Other
840 Trademark
380 Othr Persona)
LABOR
710 Fair Labor Stadards
SOCIA SECURTY
861 HI (1395ft 862 Black (923) 863 DIWCfIW (405(g)) 864 SSID Title XVI 865 RS (405(g))
Cumer Cballenge
12 USC 3410
Ecnomic Stabiliztion Act Envionmtal Mattrs Energ Alocation Act Freeom
Inonntion Act
Exchae
Propert Damage
0 385 Propert Damge
Prduc Libility
REAL PROPERTY
CIV RIGHTS
& Ejectmt
441 Voti 442 Employmnt
443 Honsing!
Act 720 LaborlMgml Relations
Lu
PRIONER PETITIONS
510 Motions to Vacate
210 Lad Condenmtion
220 Forelosur
730 LaborlMgmlReport
& Disclosur Act
740 Railway Labor Act
790 Oter Labor Litition
0 0 0 0 0
891 892 893 894 895
AgcuIl Acls
230 Rent Lee
Sentence
Habea Corpus:
FEDERA TAX SUI
0 870 Taxes (U. S.
0 900Appeal of
Fee Determation
240 Tort to Lad
245 Tort Product Uability 290 All Other Rea Propert
Accrmdations
0 44 Welfae
440 Other Civi Righls
530 Generl
535 Death Penalty
or Defendat)
0 871
Plai
0 950
Under Eqna Access to
Instice
540 Manda & Other 550 555 Prison Condition
Constituonality of
Civiltts
791 Empl Ret Inc. Secwity Act
lRThdPar
26 USC 7609
State Statutes 0 890 Other Statutory Actions
V. ORIGIN
(pLACE AN "X" IN ONE BOX ONLY)
Trasferr from
Appeal to
Orginal 0 2 Removed from
Proceeding State
. 'I CAUSE OF ACTION
(Cite the
Do not CIte Jundictional
Court Appellate Court Reopened fi
ITom
ivi
tu uner which yo
0 3 Remaded
04
another distrct
Distrct
Reinstated or
0 5
(specify)
o 6 Multidistrct
Litigation
7 Judg MagIstrte
from
Judgment
and wrte brief statement of canse.
statutes uness diversIty.
ch of contract, civil rights.
\Tiolatioi1. "" 42
lJSC 1983. 28 USC 1332
DEMAND $
vu. REQUESTED IN
COMPLAIT:
U-ID. RELATED CASE(S)
o CHECK IF THIS IS A CLASS ACTION
UNDER F. RC.P. 23
over 100, 000
CHECK YES only if demaded in complaint:
JUY DEMAD:
IF AN NONE
(See instructions):
DOCKET
Yes oNo
NUMER
)ATE
3/16/04
AMOUN
APPLYING IF
?OR OFFICE USE ONLY
REEIT
JUGE
MAG. JUGE
=----
--/
.. --. ? ";
:: :: (.. ..
, ,; ("
1.
Case 1:04-cv-00163-GMS 0:---
Document 200
Filed 08/22/2006
Page 4 of 30
IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF DELAWAR
DONALD M. DUR
CONTCTING
INe.
1310 Industral Boulevard, Suite 200 Southampton, P A 18966
VS.
CI ACTION NO. .. 0
4-01
6 3
.;,4' .
CIT OF
NEWAR
. c: Of' (f:;
220 Elkon Road P. O. Box 390
Newark, DE 19715- 0390
C1 ogr:
0",
-a ;-'2
c.
-f(p fG
HAOLD F. GODWJ
Mayor, City of Newark, Delaware
\i A
JOHN H. FARLL, IV
Council Member, City of Newark, Delaware
JERRY CLIFTON Council Member, City of Newark, Delaware
KA G. KABACHER
Council Member, City of Newark, Delaware
DAVI J. ATHY
Council Member, City of Newark, Delaware
J. OSBORN, JR Council Member, City of Newark, Delaware
CHRTINA REWA
Council Member, City of Newark, Delaware
and
UR CORPORATION
1200 Philadelphia Pike Wilmgton, DE 19809
COMPLAINT
KOP:269634v33514-
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006 -=.--"" 1
Page 5 of 30
Parties
Plaintiff Donald M. Durkin Contracting, Inc. ("Durki") is a Pennsylvana
corporation, with itspricipal
offce located
at 1310 Industrial Boulevard , Suite 200
Southampton, Pennylvana 18966.
Defendat City of Newark ("City) is a political subdivision of the State of
Delaware , with its offces located at 220 Elkon Road , P. O. Box 390 , Newark, Delaware 197150390.
Defendat Harold F. Godwi is an adult individual who , at all times relevant
hereto , served and contiues to serve as the Mayor of the City of Newark, Delaware.
Defendat John H.
Farell,
IV is an adult individual who , at all times relevant
hereto , served and contiues to serve on the City Council representing Distrct 1 ofthe City of
Newark, Delaware. .
Defendat Jerr Clifon is an adult individual who , at all ties relevant hereto
served and
contiues to serve on the City Council representing Distrct 2 of the City of Newark
Delaware.
Defendat Karl F. Kalbacher is an adult individual who , at all times relevant
hereto , served and contiues to serve on the City Council representing Distrct 3 ofthe City of
Newark, Delaware.
Defendant David J. Athey is an adult individual who , at all ties relevant hereto
served and continues to serve on the City Council representig Distrct 4 ofthe City of Newark
Delaware.
Defendant Fran
J. Osborne ,
Jr. is an adult individual who , at all times relevant
KOP:269634v3 3514-
._-t r
=-_._
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 6 of 30
hereto, served and contiues to serve as Deputy Mayor and as a member of City Council
representing Distrct 5 of the City of Newark, Delaware.
Defendant Chrstina Rewa is an adult individual who , at all times relevant hereto
served and continues to serve on the City Council representing District 6 of the City of Newark
Delaware.
10.
The Defendats identified and named in paragraphs 3 though 9 , inclusive, shall
be hereafer referred to as "City Council"
11.
Defendat UR Corporation ("URS") is a business corporation incorporated
offce located
under the laws of Delaware, with a pricipal
at 1200 Philadelphia Pike
Wilmgton, Delaware
19809.
Jurisdiction and Venue
12.
Jursdiction is predicated upon 28 U.
arsing under the Constitution,
CA.
g 1331 and 1343 ,
in that ths is a
civil. action
laws , and treaties of the United States. Jursdiction is
and pendent jursdiction.
also predicated upon the doctre of ancilar
13.
Jursdiction is fuher predicated upon 28 U.
and
CA.
1332 , there being complete
diversity between all plaitiff
all defendants , and the matter in controversy, exclusive of
interest and cost, is in excess of $1 00 000.
14.
Venue in ths Distrct
is proper
pursuant to 28 U.S.
A.
1391(a) and (b).
KOP:269634v3 3514-04
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 7 of 30
Facts
Events Prior to Biddin and Contracting
15.
At some time prior to Januar, 2002 , the City retained the serVces of UR for the
puroses of analyzg the feasibility of, and thereafter preparig professionally engineered design
and constrction
documents for, the constrction of a water supply reservoir. ("Project"
16.
pumped
The Project was intended to provide for the constrction of an "off-stream
318 millon
storage reservoir" with the capacity of approxiately
17.
gallons of water.
The reservoir was to be situted on propert owned by the City, with a work area
in excess of 60 acres , adjacent to inter alia Old Paper Mil Road Newark, Delaware.
18.
At all ties relevant hereto , including the design phase for the Project, the City
and URikDew that the Project and the water supply reservoir was located imedately adjacent
to a densely populated residential area.
19.
Because ofthe location ofthe water supply reservoir, at all times relevant hereto
iving adjacent to the
the City,and UR were acutely aware that (1) the safety ofthe residents
reservoir and the public in general , and (2) the long-term integrty of the water supply reservoir
were imperative considerations , especially since a failure ofthe water supply reservoir could
imperl the life and safety ofthe persons and propert working on the Project , and risk the safety
of the residents in the suroundin area, including multiple occupied residences , with potentially
catastrophic consequences in term ofloss of life and
20.
propert.
The City and UR were also fully aware that for the safety and protection of those
working in and around the reservoir durg constrction of the Project , the design for the reservoir and for the overall Project had to address site safety at all times durng the constrction
KOP:269634v3 3514-04
=--Case 1:04-cv-00163-GMS Document 200 Filed 08/22/2006 Page 8 of 30
:.
phase of the Project.
21.
At all ties
durg the design phase for the Project and prior to constrction,
the
City and UR also knew , and specifically understood , that the Project was subject to competitive
bidding by contractors pursuant to the public bidding laws in the state of Delaware, and that all
relevant inormation known by the City and UR respectig the Project needed to be disclosed
and either provided , or at least made available , to the bidders prior to submitting the bids.
22.
At all ties
durg the design phase for the Project and prior to constrction,
the
City and UR knew that the bidders would utilize and rely upon the pre-bid inormation
disclosed by the City as the basis for, among other thgs , selectig the partcular mean and
methods of constrction
to be employed anticipating the conditions to be encountered and
accounted for durg constrction, the initial fillng of the reservoir and the maintenance of the
reservoir durg the period of contractor responsibility, all of which was taken into account and
factored into the pricing of the Project work.
23.
At all times durg the design phase for the Project and prior to constrction,
the
the
City and UR were aware that soil staility,
inormaton was among
sequence and maner
of constrction and safety
the essential information necessary for bidders to fuly evaluate the scope
and complexity ofthe Project work.
24.
At all times durng the design phase for the Project and prior to constrction, the
City and URS also knew that all bidders , and ultimately the contractor who was awarded the
contract for the Project, would rely on the adequacy ofthe
plans ,
drawings and specifications
and also would reasonably presume that URS had completed all testing, analysis and evaluations
to determe the constrctabilty and adequacy of the design.
KOP:269634v3 3514-
\t
Case 1:04-cv-00163-GMS
25.
Document 200
Cc_Filed 08/22/2006
Page 9 of 30
At all times durng the design phase for the Project and prior to constrction,
the
City and URS knew that bidders were not obligated to conduct any independent investigation
into the adequay of the bid documents or the constrctaility
of the
Project design but would in
fact rely upon the City and UR to provide a design which was complete in all material respects
and could be
constrcted utilizing ordiar and customar constrction technques and mean
and methods of constrction.
26.
At all ties prior to the lettg
ofthe
Project for competitive biddig, the City and
UR specifically knew that they had the affative legal obligation to disclose all relevant
inormation to all prospective bidders , and that non-disclosure of any material inormation would
be a constrctive or actual fraud on the bidders.
27.
At all ties
durg the design phase for the Project. and prior to constrction,
the
City and UR expressly and impliedly w31anted the adequacy of the design for the Proj ect, the
completeness ofthe bid and contract documents , and that the City and UR had disclosed all
known relevant inormation respecting the Project.
28.
Durki avers, upon information and belief, that prior to the solicitation of bids for
the Project, UR prepared an intial design for the water supply reservoir and presented it to the
City for review and consideration.
29.
Durkin avers , upon inormation and belief, that contrar to UR' professional
duties and in lieu of completig its own testing and analysis ,
analysis provided by a vendor of a proprieta
30.
UR relied upon inormation and an
as "Fabriform
product marketed
Durkin avers , upon inormation and belief, that URS' initial design incorporated a
design for the interior side slopes of the water supply reservoir that was intended to provide for
KOP:269634v3 3514-04
-Case 1:04-cv-00163-GMS Document 200
=-- - .
Filed 08/22/2006
Page 10 of 30
interior slope stability at all times durg
intially filled,
constrction, while the water
supply reservoir was
when water
and durg the servce lie
of the reservoir
, includig such ties
level
in the reservoir was being drawn down for maintenance or to address emergencies.
31.
Durki avers , upon information and belief, that UR' intial design included total
slope protection; however, in an effort to ostenibly " save costs-and at the behest of the
City-URS agreed to change their design.
32.
Specifically, the intial
design prepared by URS included fist placing an
impervous liner over the bottom and interior side slopes of the reservoir, over which was to be
placed a proprieta
product
known as ' 'Fabriorm , which would cover the impervious lier
, from the ri ,
system along the entire interior side slopes of the reservoir, i.
or the top ofthe
interiorslope , to the basin floor of the reservoir.
33.
The changed design ("modied design ) that was included in the bid do cuments
eliated the "Fabriorm" for the lower porton ofthe interior side slopes , specificaly from
elevation 169 down to the bottom of the reservoir, and instead called for the placement of
screened soil materials ITom the excavation of the basin (which soils were referred to as "cover
soil" in the Contract) over the impervous liner system from elevation 169 down to the basin
floor. In the bid and
Contract documents ,
UR identified the area between the basin floor and
elevation 169 as "Zone IV , and the cover soil for that area as "Zone IV material"
34.
URS' change from the
intial design to the
modified design was ostensibly for the
of
purose of savig the City approximately one millon dollar in the cost
reservOIr.
35.
constrctig the
The modified design was incorporated into the bid and Contract documents for
KOP:269634v3 3514-
,I
Case 1:04-cv-00163-GMS 7:-
Document 200
Filed 08/22/2006
Page 11 of 30
the Project, without disclosure to any bidder of the initial design, or disclosing the fact that the
modified design had not been evaluated by the City or URS for constructability, safety, operation
or long term stability of the reservoir.
36.
Durki avers , upon inormation and belief, that although UR signficantly
of
changed its intial design URS failed to consider and professionally address the consequences
the modified design prior to incorporatig
37.
the changes into
the Project documents.
Durkin avers , upon inormation and belief, that before incorporatig tl1 modified
design into the Project doc1Jents , (1) UR did not verfy that the modified design was even
constrctable utiliing ordiary
constrction mean and methods ,
(2) UR did not verify that the
modified design was safe for the contractors attemptig to build the Project, and (3) URS did not
verify that if completed as designed by UR , the reserVoir would be safe and fuction properly.
38.
Although the plan , drawigs and specifications for the Project were ostensibly
. prepared by UR , and UR affied its professional engieering seal
upon the Project plans and
drawigs, Durki avers , upon inormation and belief, that signficant portons of the
purorted
engieerig" for the plans , drawigs and specifications for the Project were not prepared or
evaluated by UR , but intead were plan , drawigs and specifications prepared by others.
39.
Durki avers , upon inormation and belief, that the drawigs for the Project
incorporated a non-site specific "design" ostensibly prepared by vendors of the Fabriform
proprietar systems ,
which design was not fully evaluated was not based on actual site
conditions , and was not verified by URS as appropriate for incorporation into the Project
requirements before the Project was let for bidding.
40.
Durkin avers , upon inormation aid belief, that prior to completing the " fial
KOP:269634v3 3514-
'"
, t.
Case 1:04-cv-00163-GMS 1F-Document 200
-:-----
Filed 08/22/2006
Page 12 of 30
design"
and prior to solicitig bids
, UR had failed to perform all essential engieerig required
of design professional , includig the slope stability analysis ofthe modified design and all other
critical studies and testig, all of which were necessar for UR to determe the constrctability
of the modified design and the safety of the Project durg constrction , and for proper
maitenance of the reservoir on a long term basis.
41.
Durki avers , upon inormatiQn and belief, that prior to soliciting bids , UR did
documents or anywhere
know, but did not disclose in the biddig
modified design had inerent flaws ,
accessible to bidders , that the
includig the followig:
materials were especially vuerale to severe erosion
that the Zone
durng constrction;
. that the modified design provided that the Zone N- materials were to form
a shelf area, known as a 1Jench", from the floor ofthe reservoir to elevation 169 , upon
. which the ' abriorm" slope cover was anchored but that the bench and Zone
materials would fail under conditions that were liely
filig of the
to occur
durg constrction, the
reservoir or durng the serice life of the reservoir; and
that when the reservoir was drwn down to a water elevation below 169
(i. e. the highest point of Zone N) and wave and/or wind conditiQns existed, or if the
water was drawn down below the elevation of 169 at a rate greater than five million
gallons per day, the Zone IV materials would fail and the bench and the Fabriorm
would be compromised.
42.
anchor
Because UR had failed to perfonn all necessar calculations and pre-bid
evaluations , the severity of defects may not have been fully known but UR proceeded with the
KOP:269634v3 3514-04
=--
Case 1:04-cv-00163-GMS
Document 200
'0._- j Filed 08/22/2006
Page 13 of 30
procurement on behalf of the City without regard to the known defects and without disclosure to
any bidder.
Bid SolicitationIre-Contract Activities
43.
In or about Janua, 2002 , the City advertised for bidding the public works project
it referred to as the " Water Supply Reservoir, City of Newark, Delaware, Contrt 02- 02"
utiizing UR' modified design.
44.
Prior to the solicitation of bids ,
UR and the City both knew, or in the exercise of
professional diligence UR should have known that the materials that would be utilized to
constrct the reservoir were highy erodible and untable under conditions that UR and the City
knew or should have known would be encountered durg
constrction and
after the reseroir
was placed in servce.
45.
Specifically, but without limtation, prior to the solicitation of bids ,
UR and the
City bothJmew that when the level of water within the reservoir would periodically be an
elevationJower than 169 ,
tht the "bench"
that the "Zone IV" materials would be subject to severe erosion and
was "anchored"
upon which the Fabriorm
would fail, creatig a risk of
cattrophic failures of the slopes and possible compromise of the integrty of the entie
reservoIr.
46.
Durkin avers , upon information and belief, that before soliciting any bids , URS
and the City knew of the conditions that would affect the Project, but despite their obligations to
disclose all material inormation, failed to advise all bidders , including Durki, of these material
conditions.
47.
Durki avers , upon information and belief, that prior to soliciting bids for the
KOP:269634v33514-4
A-II
(.
--!
Case 1:04-cv-00163-GMS Document 200 Filed 08/22/2006 Page 14 of 30
Project, the City and UR lmew that no reasonable pre-bid or pre-contract investigation by any
. bidder would discover the inonnation lmown but concealed by UR and the City, includig,
without litation,
the fact that URS had failed to adequately prepare design and constrction
engineerig
documents and had not completed all necessar
48.
evaluations.
The City and UR waranted , either expressly or implicitly, that the bidding
documents were complete and accurate, that the City and/or URS had disclosed alllmown
relevant inonnation, and that the biddig
documents
fully and accurately described the scope of
work such that a competent contractor could formulate a bid price and complete the work in
conformance therewith.
49.
Specifically, the bid documents were represented by the City and URS to describe
(Section 3. 2) and that the scope ofthe work to be perfonned by
reasonably
a fuctionally complete Projecf'
the contractor was " any work, materals or equipment that may
Contract, Documents... " (Section 3.
50.
be inerred ITom the
The City opened all bids and thereafter reviewed with Durki the apparent low
bidder, the basis upon which Durki had prepared its proposal.
51.
Notwthstadig the review of Durki' s bid and post bid-openig discussions , at
no time prior to awarding the Contract to Durki did either the City or UR disclose to Durki
any factul or engieerig inonnation
respectig relevant site conditions , the constrctabilty of
the Project, or that UR had not properly completed the necessar engieerig for the Project
even though the foregoing facts were critical to Durki' s bidding and method of prosecuting the
Project, and that the foregoing facts were not known by or available to Durki.
Contract Award:
Durkin
Performance
and
CitylU'
Responses
KOP:269634v33514-04
( .
--
---
Case 1:04-cv-00163-GMS
;:i
Document 200
Filed 08/22/2006
Page 15 of 30
52.
On April 24 , 2002 , Durkin and the City entered into a wrtten contract for the
Notice to
constrction ofthe Project (" Contrct" ).
proceed with the constrction work was
hereto as
issued by the City on May 24. 2002. Relevant portions of the Contract are atthed
Exhbit "
53.
Federal Inurance Company ("Federal") was , at all times relevant hereto , the
payment and performance bond surety for Durkin in connection with the Project.
54.
The City appointed URS as the constrction
inspector
for the Project
notwthstadig the fact that UR was the designer of the Project, and that one of the essential
fuctions of the constrction inpector is to report and evaluate any alleged defects in the Project
design for which UR
would ultiately be responsible
55.
UR'
positions as both designer of the Project and constrction
inpector was an
inerent confict of interest, which should have disqualified UR as the field inspector on behalf
of the City.
56.
Afer mobilizing to the site and commencing
constrction
of the Proj ect
, Durkin
was subjected to materially different requiements than those specified in the Contract, and was
fuher directed to perform additional and extra work.
57.
Specifically, after
begig work on the Project, Durki was diected by the City
including, as examples only:
and UR
to employ technques and perform additional and extra work to address omissions and
documents ,
deficiencies in the Contrct
the Project design failed to properly anticipate the characteristics of the soils; as a
result, Durkin was diected to haul in water to add to the on-site materials in order
to achieve the specified moistue content set fort
in the Contract
documents;
KOP:269634v33514-04
=:-
l ,
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 16 of 30
UR field personnel charged with followig the Contract specifications failed to
follow the requiements for acceptace testing; as a result, Durki was forced to
retain the servces of a soil engieer to ensure that the requied testing for
compliance with the Contract specifications was performed in a timely and proper
maner so as to permt the work to proceed on schedule;
UR'
design failed to properly estiate
the quatity of excavated
materials; as a
result , Durki was diected to haul the excess material to the exterior embanent
of the reservoir which fronts Old Paper Mill Road , and was
fuer requied to
Fil.
handle and compact the excess materials as if it were "Landscape
Durki was also diected to perform additional work in
screenig the fill material
to remove rocks and stones ,
notwthstadig the fact that the Contract permtted
an alternative method of treating the fill, namely rakg.
58.
As of October, 2003 , Durkl had accrued and presented claims for the extra work
in an amount in excess of $650 000 due to the design defects and improper Contract
admstration by UR.
59.
Durki complied with all ofUR' directives , the Contracfrequiements and all
other conditions precedent to presentig claims for extra compensation to the City.
Siope Stabilty. Safety and Project Constructabilty Issues
60.
As ofthe early fall of2003 , Durki had substatially underten the specified
in the Contract in anticipation ofthe star of the constrction of the
prepartory work described
Zone IV" materials , including the screenig of the Zone IV material , the placement of the
geotextile and impervous liner on the substatial
areas ofthe slopes
and the floor of the
KOP:269634v3 3514-
.,
-"
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 17 of 30
reservolf.
61.
In the locations designated by the Contract , Durki had placed geotextile materials
and liner and prepared to place the Zone IV materials on the slopes
begig at the " shallow
end of the reservoir, i. , where the difference in the elevation from the floor of the reservoir to
the elevation of the Zone IV bench was the smallest.
62.
As designed by UR, the Zone IV materials were to be placed ftom the toe of the
. slope to elevation 169 , whereat a ' 'bench'' ftom the Zone IV materials was constrcted , and
where the Fabrionn materials were be anchored. From that point, the Fabrionn materials
would be placed on the slope up to the top of the reservoir, at which point a "wetland" mitigation
strctue was to be constrcted.
63.
As designed byURS , large rocks , known as "rip-rap , were to be placed on the
Fabrionn at and near the top ofthe slope adjacent to the wetland mitigation strctue.
64.
Durki had retaned the servces of a geotechncal consultant , GeoSyntec
Consultats , Inc. ( " GeoSyntec ), for puroses of maintaig quality control durg the
placement of the Zone IV materials , instaation of the Fabrionn, placement of the rip-rap and
constrction of the "wetland" mitigation strctue at the top of the slope of the reservoir
65.
Nowhere in the Contract specifications was Durki directed to employ any special
technques for placement of the Zone IV materials , the Fabrionn
rip-rap.
or extraordiar constrction
material , the wetland strctue or the
66.
Durki began
the placement of the Zone IV materials at the end of the reservoir
where the least amount of Zone IV materials would be placed , and completed a section ofthe
Zone IV work prior to any rai.
KOP:269634v3 3514-4
, .
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006 =.-i
Page 18 of 30
67.
Al materials placed by Durki
met
the Contract specifications for gradation and
the cover
density, and Durki
68.
fuher protected the Zone IV materials from rain by sealig
soil.
In September, 2003 , there was a sustained rain event.
69.
Notwthstading (l). Durki' s instalation of the Zone IV materials in complete
accordance with the Contrct design (2) Durki' s implementation of erosion mitigation utilizing
ordiar mean and methods; (3) Durki' s constrction ofthe slopes to the grades and lies
prescribed in the Contrt
plan; and (4) Durki' s proper placement and compaction of the Zone
een placed by Durki were severely damaged by
IV materials , the Zone IV materials that had
the
rai.
70.
Specifically, due to defects in UR' desi
water on the impervous slope liner at
elevations ' greater than 169 was chaneled down to and
undermed the Zone IV bench , causing
severe daage to the work, which included displacement and sloughg of entie sections of the
Zone IV materials down the slope to the floor of the reservoir.
71.
The ordinar mean and methods of erosIon mitigation employed by Durki
could
not overcome the defects in URS' design.
72.
Not only did the Zone IV materials fail , but because the eighteen (18" ) inches of
lier
Zone IV materals placed on the flQor of the reservoir were placed on top of the impervous
the moistue was trapped in the materials.
73.
The trapped moistue in the materials located on the floor of the reservoir resulted
in the bearg capacity of those materials being signficantly dished, thereby precluding
constrction equipment from
gaing access to the affected areas without severe ruttig
and
liely damagig the underlying liner.
KOP:269634v3 3514-04
A-
.'
Case 1:04-cv-00163-GMS Document 200 Filed 08/22/2006 Page 19 of 30
74.
As a result of the severe damage to and failure of the Zone IV materials , Durki
requested that GeoSyntec evaluate the conditions and advise Durki of the likely cause(s) of the problems and any potential consequences.
75.
GeoSyntec advised Durki that there was a potential serious defect in URS' s
of the Project,
design that affected the constrctability
and also that there were other, potentially
more serious defects , that called into question the integrty of the entire design and raised
life/safety issues.
76.
The Contract Specifications (Section 3.3. 2) requied Durki to advise the City and
UR of any discovered design problem and defects.
77.
Durkin imediately
advised
the City and UR of the potential defects in the
Projectdesign, and requested that the City and UR
78.
imedately address the issues.
to
Contemporaneous with the notice to the City and UR , Durki requested UR
provide its design analysis of inter alia slope stability, so that Durki' s geotechncal consultant could
fier review the modified design.
79.
At a meetig among the City, Durki, URS on September 26 2003 , Durki'
consultats advised the
meeting attendees of the discovered design defects; specifically, Dur'
consultats advised,
inter alia that in the event of a rapid or other draw- down of the reservoir
the design for the Zone IV materials had a factor of safety of less that one.
80. 81.
A factor of safety of less than one indicates that failure would occur.
In a memorandum from URS to the City dated October 14 2003 , that was not
addressed or sent by URS to Durki URS wrote inter alia:
'we concur that if a very conservative approach is tae to the evaluate cover soil stability using the innite slope method of analysis and assuming no soil cohesion, intantaeous
KOP:269634v3 3514-
,'
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 20 of 30
drawdoWl , and no drainage ofthe
calculated. "
cover soils ,
a factor of safety of approximately one is
82.
The conditions described in URS' memorandum would occur if the reservoir
were drawn down in an emergency.
83.
As
a "high hazard" earhen da URS knew that the factors of safety for its design
for such strctues.
were well below the minium standards of safety acceptale
84.
In the October 14 2003; memorandum UR aclmowledged that it had changed its
origial design to the
modified design in order to save approxiately
$1. 0 rillon.
85.
UR fuer aclmowledged in its October 14
2003 , memorandum that "the
erosion (of the Zone IV materials) that has been observed to date has occured with the lie
above. El. 169 exposed (no riprap or Fabriform in place). Ths relatvely smooth surace results
in very high erosive velocities.
86.
As
par of the October
14,
2003 , memorandum
UR aclmowledged that the
(US) do propose a slight
concern that were raised by Durki were valid and stated that ' We
change in the Fabriorm detail to mitigate the maintenance impacts , and proposed to the City
varous alternatives designed to address some of the defects in the modified design.
87.
Begig in late October, 2003 , UR advised Durkin that the modified design
Durki to provide pricing for alternates to the as-designed
requied changes , and requested
system.
88.
URS fuer stated even though they agreed that the modified design had to be
abandoned and corrective measures implemented, neverteless , if the prices quoted by Durkin for
the alternatives were not acceptable , that UR would direct Durki to proceed with the modified
KOP:269634v33514-
A-
, ,
.. '"
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 21 of 30
design set forth in the Contract, even though URS knew that the modified design could not be
constrcted.
89.
Durki avers , upon inormation and belief, that UR attempted to conceal its own
responsibility for the
design errors and fiancial
errors by attempting to convice the City that the
alternatives were to "mitigate potential maitenance issues " so as to obta
fuds from the City to
pay Durkin the costs to remedy the defects in UR' modified design.
90.
Only after October, 2003 , did the City and UR
the
adit to Durki for
the fist tie
that the City had contigent plan to drai
reservoir for maintenance , emergencies or due to
severe drought conditions , and that the conditions durg the draig
maitenance or durg
intallation of rip-rap.
of the reservoir for
emergency draw- down
would likely underme the Fabrionn and
FUTHER INSTIGATION OF DESIGN DEFICIENCIES
91.
As requested Durki provided prices to UR
for the varous alteratives to the
modified design.
92.
Afer submittg proposals for alternative design for reviewig and
consideration, Durki was advised that the City and UR would not implement any of the
alternatives to the design notwithstadig
the seriousness of the issues and life/safety concerns
because Durki' s prices were allegedly too high.
93.
Durki alternatively offered to work on a "tie
and material" basis ,
with control
of the operations being vested in URS and the City, but this proposal was also rejected.
94.
At all times durg these discussions and exchanges of pricing for the alternative
schemes proposed by UR,
Durki continued with the available work on the Project, had
KOP:269634v33514-
=--Case 1:04-cv-00163-GMS Document 200 Filed 08/22/2006 Page 22 of 30
materials delivered to the Project site, and awaited diection
from the City and
UR on how it
was to proceed.
95.
Durg this same period of time Durki continued to request that the City and
UR provide their design calculations and other essential design inormation so that Durki'
consltants could complete a
fuer evaluation of the design issues that affected both life/safety
concern as well as constrctaility.
. 96.
In the late fall and/or early witer, 2003 , Durki leared for the fit
tie that the
reason that tJ;e requested design inormation was not provided was that UR had failed to
. complete these essential calculations and analyses prior to biddig, and
was
only then
begig
to evaluate the life/safety, slope stabilty
97.
and other issues
afectig constrctability. .
attempt to force
Shortly thereafter, in an improper and ilegal
Durki to proceed
with a mown deficient plan the City, with the advice ofUR , wrote to Federal and claied that
Durkin.was in some fashion failing to perform the Contract work.
98.
The letter to Durki'
s surety
was
wrtten in bad faith in that inter alia Durki
had never abandoned the site and was stil prosecutig available work and havig materials
delivered to the site , and that pursuant to Section 3.3. 2
ofthe Contract specifications
, Durki was
contractully obligated to rase the design deficiency issues with the City andUR.
99.
The letter to Durkin s surety was wrtten in bad faith in that inter alia
lmew at the time of the City' s notice to Federal that there were indeed design deficiencies , and
that if Durkin had proceeded, additional costs and expenses would be incured for no good
purose.
100.
The letter to Durki' s surety was in bad faith in that inter alia the City and
KOP:269634v3 3514-
.-
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 23 of 30
knew that section 3.
2.
0ftheContIact specifications provided that "the Contractor shall not
an
proceed with the Work affected thereby" (i. e. a design defect or error J ' 'util supplement to the Contract Documents. has been
101.
issued (in wrtig)....
abatement or
In December, 2003 , the City and UR met with Federal and Durkin in a
supposedy "off the record" meetig.
102.
At the behest of the City to seek the advise of consultats
other than
those
retaned by Durki
Federl engaged the servces of a nationally-recognzed geotechncal
Greg Richardso
engieerig consultat ,
Ph.I). , P. , to review the design and advise whether
there were defects in the modified design.
103.
Unkown to Federl and Durki prior to Federal retag Dr. Richardso
had contacted Dr. Richardson for puroses of solicitig advice respectig the adequacy ofUR'
modified design.
104.
In conversations between UR and Dr. Richardso
UR admtted to the design
deficiencies and that UR had modied its intial design at the behest of the City in order to save
approximately $1. 0 millon.
105.
In completig his analysis and evaluation of the modified design Dr. Richardson
laboratory then being utilied by
also contacted the testig
UR to belatedly complete the slope
stabilty analysis and other
computations. The results of these discussions were reported in the
wrtten report prepared by Dr. Richardson, which fuer confed the deficiencies in the
modified design.
106.
Richardson completed his analysis and generated an intial wrtten report dated
Januar 13 , 2004.
KOP:269634v3 3514-04
,'
=-_
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 24 of 30
107.
In the Janua 13 2004 report , Richardson confed the defects in the design the
exitence of signficant life/safety issues , that the as-designed system was not "constrctable" and
advised that proceedg with the modified design would imperil workers and that potential
catatrophic failures could occur if the constrction
108.
work proceeded.
A copy of Dr. Richardson s Januar 13 , 2004 report was provided to the City and
20 , 2004.
UR by Federal under a cover letter dated Janua
109.
At no tie did
the City or UR seek an independent evaluation of either UR'
modified design or Dr. Richardson s report.
110.
On Janua 30 2004, URS prepared a wrtten response to the Januar
13
2004
report of Dr. Richardson.
111.
The January 30 2004 report from UR respondig to Dr. Richardson
Janua
2004 report was not forwarded to Durki
or Federal for comment or response prior to
termation of the Contrct by the City.
CITY AND UR' REFUSAL TO PAY FOR WORK AN MATERIALS
112.
Notwthstading its contraCtul obligation to pay Durki for the work performed
and the materials provided on the Project
begig in November, 2003 , in material breach of
Durki.
the Contract, the City began to improperly withold payments from
113.
Notwithstanding its own material breach of the Contract by refuing to pay for
work performed, the City, through UR , diected Durki to continue with the Project work
puruat to the modified design.
114.
At the diection of the City, Durki
contiued to work on the Project
fishig
much work as was available until in or about Janua, 2004 , when, because of weather concerns
KOP:269634v33514-
.'
...
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 25 of 30
and restrctions in the Contract specifcations , work was halted.
115.
As recently as mid-Jarua 2004,. the City approved Durki' s payment estiate
for work completed though Janua 2004.
116.
Durki fuher continued to have materials delivered to the Project for use when
the weather conditions permtted
fuer work.
NOTICE OF DEFAULT
117.
Section 15. 2
of the Contract provides
lited rights for the Owner to termate
rights.
a
contrtor for an alleged default , and fuer imposes express conditions precedent upon the
Owner to protect the contractor s procedural and substative
due process
U8.
Section 15.
1 though section 15. 2.4
of the
Contrct allow for a termation for
default only if the contractor ' 'persistently fails to perform the Work in
acrdace with the
Contract Documents... " or if the contrctor "disregards Laws or Reguations of any public body
havigjurisdictiori" or if the contractor "disregards t4e authority of the Engieer" or if the
contrctor " otherwse
violates in any substantial way any provision of the Contract Documents.
119.
Section 15.2.4 of the Contrt provides , in pertinent par, that
may, after
OWNR
vie CONTRACTOR (and the surety. if any). seven
permittd by
days written notice and to the extnt
Laws and Reeulations.
termiate the services of CONTRACTOR. " (Emphasis added)
120.
The language contained in Section 15.2.4 ofthe
Contract was an express
contractul requirement and procedural condition
precedent to the right of the City to termate
the Contract for cause and avail itself of the rights and remedies set forth in Section 15. 2.4.
121.
The City failed to provide Durki or Federal with the requied seven days wrtten
notice of its intent to termate the Contract for cause.
KOP:269634v3 3514-04
...
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 26 of 30
122.
. a letter
The last dated correspondence ftom the City prior to termating the Contract was
ftom the City Manager to Durki' s surety dated November 21 2003 , in which the City
Manager stated inter alia that " (O)n behalf of the City of Newark, Delaware , I am wrtig
inform you that we are now
considering
declarng (Durki) in default.. This
precautionary
letter has becme necessar followig (Durkir' s)failure to present a response to a mean and
metods for contiuation of the Project in accordace with our contract." The letter concluded
by statig tht "
we are requesting that a conference be held includig the surety representatives
and correct
(Durki), UR and representatives of the City. " (Emphasis added) A tre
letter is atthed hereto as Exhbit "
123.
copy of the
The requested meetig
occUled on December 9
above.
2003 , after which Federal
retained the servces of Dr. Richardson as outlied
124.
At its regularly scheduled meeting in Janua, 2004 , the City Counel did not raise
anyissues respecting any decision to formally declare Durki
to be in default of its obligations
under the Contract, or otherwse cite to the provisions of Section 15. 2.4 of the Contract as the
basis for termation of the Contract
125.
Subsequent to the City Council meetig in Januar 2004 , and up through the date
of termation of the Contract, neither Durki nor Federl received any wrtten notice of default
or any wrtten notice of an intent to termate the Contract pursuant to the provisions of Section
15. 2.4 of the Contract.
126.
It appears the decision by the City and City Council to termnate the Contract was
reached at the City Council meeting conducted on Febru 2 , 2004. The official minutes ofthe
City Council meeting held on Februar
2 , 2004 ,
provide:
KOP:269634v3 3514-04
,.
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 27 of 30
MOTION BY MR. GODWI, SECONDED BY MR. CLIFTON: THT DONALD DUR CONTRACTING, INC. BE TERMATED IMDIATELY FROM FUTHR INOLVEMENT IN THE CONSTRUCTION OF TH NEWAR WATER
RESERVOIR
BASED ON ITS REFUSAL TO PERFORM UNDER ITS CONTRACT
AR;
WITH THE CITY OF NEW
PROMPTLY AN PROPERLY NOTIFY DONALD M. DUR CONTRACTING INC. AN THE SURTY OF DUR, OF TH TERMATION AN DEMA THAT SAI SURTY FULFILL ITS LAWF OBLIGATIONS UNER ITS BOND WI DUR. (Emphasis fushed)
127.
The followig
AN THAT LEGAL COUNSEL FOR THE CIT
day, Febru 3 , 2004 , the City Manager sent a letter to Durki and
mail ,
Federa via facsimle and overght
in which the City "declared a Contractor default and
hereby formaly termates (Durkin)'s
November 21 ,
right to complete the contrt.. "
and fuer stated that the
2004 letter from the City Manager to Federal constituted its seven day advance
wrtten notice of intention to termate the Contract purant to Arcle 15 of the Contract.
128.
On Febru 5 , 2004 , a day after the Contract had been termated by the City, the
Citys attorney sent a letter to counsel for Durki and Federal which included a copy of the
response to Dr. Richardson s Janua 13 , 2004 report.
129.
As of the date the City and City Council termnated the Contract, the City had not
complied with the substantive or procedural due process rights embedded withi the Contract for
termation of the Contract for cause.
130.
At no time had Durkin breached the Contract with the City, or refued "to perform
under its Contract..
131.
Furher, the alleged refusal "to perform under its Contract.. " was specifically
contradicted by the certifications by the City and UR in mid-Januar approving Durki'
request for payment.
132.
The City, City Council and UR failed to afford Durki any substantive or
KOP:269634v33514-
. -
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 28 of 30
procedural due process rights in connection with the decision to termate the Contract for cause.
133.
Durki avers , upon inormation and belief, that the decision by the City and City
Council to termate the Contract was solely an attempt by the City and URS to ilegally foist the
ecnomic impact ofthe deficient modified design on Durki and/or its surety.
134.
The City' s termation of Durki for default has been reported in newspapers and
withi the public
becme "common knowledge"
contractig communty, specifically, and
private owners
without limtation, to other public agencies
and procurement offcials ,
contractors , suppliers, subcontractors and sureties; all of who Durki relies upon for its very
surival as a business.
135. .
In
point of fact, Durki fist leaed of the City' actions
teratig the Contrt
from a- newspaper reporter.
136.
Prior to receivig the City' s notice oftermation,
Durki was awaitin a response
to the fidings and report of Dur' s consultats that confed the design deficiencies in the
modified design, together with appropriate diection
from the
City, all as provided and prescribed
by the Contrct specifications.
137.
At all ties prior to receivig the City' s notice of default, Durki had fully
confonned with and to the requiements of the Contract.
138.
At all ties relevant hereto , the City and City Council acted under the color of
state law.
139.
At all times relevant hereto ,
UR acted as the agent of the City and under the
color of state law.
140.
All conditions precedent to the rights of Durki and the liabilities of the City, City
KOP:269634v3 3514-
-, "
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006
Page 29 of 30
Council and UR have been satisfied or have
141.
Januar 30
occured.
Subsequent to the City' s tennation of the Contract, Dr. Richardson reviewed the
2004 response from URS , visited the site, and examned additional documents
relating to the Project conditions.
142.
AI a result of his fuer investigation and fidings , Dr. Richardson published a
supplemental report to Federal dated March 11 , 2004 , in which he concluded the followig:
That the design associated with utilizing the Zone IV materials ,in the lowennost
porton of the interor embanent slope was not constrctale
as designed
that UR failed to include an essential element of the design namely proper
design measures for protective soil cover durg
the reservoir;
constrction and
durg fillig of
That the design associated with utilizing the Zone IV materials was deficient, in
that the soil layer comprised of the Zone IV materials would inevitably fail from
erosion, which would potentially clog the outlet strctue
and prevenf
the
reservoir from draig;
That UR has approved and overseen the instalation of Zone IV cover soils that
do not meet Project specifications and are higWy erosive with respect to surface
water;
That the UR specifications contaned in the Contrct do not preclude the use of highly erosive silty sand in the Zone IV materials , which should not be used on
exposed slopes;
That URS has not presented design calculations related to (1) the stability of the
KOP:269634v3 3514-04
Case 1:04-cv-00163-GMS
Document 200
Filed 08/22/2006 7---
Page 30 of 30
perieter embanent system durg normal and failed lier
stabilty of the lier and protective soil
conditions ,
(2) the
layer durg draw down of the reservoir
(3) the liner system design and (4) the as- designed and modified underdrain
design and
fuher that the only calculations provided by UR were performed
the
this year, and not at the tie
documents;
design was incorporated into the Contract
That UR has npt presented any field data to substtiate
the
adequay of the
margial liner system and protective layer of soil cover;
That UR has represented that other reservoir facilities in the region use simlar
soil covers , but has not presented successful regional examples with both a servce
history and physical propertes of the soil to allow a techncal evaluation;
That URS has. failed to appreciate the ballast role ofthe protective cover soil in
protecting the geomembrae from floating and thereby exposing the subgrade to
full hydrostatic forces;
That UR has understated the potential for leakage though the mimal single
lier system;
That UR has misrepresented the quality of lier
project specifications ,
constrction
reflected in their
constrction
in that their level of quality control for lier
would not meet mium stadards for muncipal landfill liners , and is an
industr mium, which would lead to a signficant number of liner defects;
UR has not substatiated the stability of the operational cover durg
draw down
conditions and has presented no calculation to support their position, despite
KOP:269634v3 3514-04