Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 1 of 14
Connecticut Yankee Atomic Power Company v. United States of America Maine Yankee Atomic Power Company V. United States of America Yankee Atomic Power Company v. United States of America
Summary of Opinion
Prepared. by
~iiaff
Mt.
' P.
February 18, 2004
N avigant Consulting, Inc.
000 Midlantic Drive Laurel , New Jersey 08054
001
Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 2 of 14
TABLE OF CONTENTS
Statement of Purpose
II.
Qualifications
III.
IV.
Documents
OUf Understanding
A. Connecticut Yankee
B. Maine Yankee
C. Yankee Atomic
Summary of Opinions
A. Connecticut Yankee
B. Maine Yankee
C. Yankee Atomic
Appendices
1. Curriculum Vitae
2. Documents Considered
3. Documents Not Yet Provided by the Plaintiffs
002
),
))
Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 3 of 14
I. Statement of Purpose
Navigant Consulting, Inc.
NO" was engaged by the Deparbnent of Justice to provide
independent assessment of schedule delays experienced by each of the Plaintiffs
(Connecticut Yankee Atomic Power
Company(II CY" Maine Yankee Atomic Power
YA"
(li
Company
MY"
and Yankee Atomic Power Company
during the design and
construction of the Independent Spent Fuel Storage Installation (" ISFSI" ). In preparing
its analysis, NCI utilized Critical Path Methodology to establish the as-built critical path,
to quantify progress achieved and delay incurred, and to determine the causes of critical
delays.
analysis addresses the time period and delays associated with the
completion of fuel transfer as identified by the Plaintiffs' Stipulations of Facts dated June
30, 1999, July 13, 1999 and March 28, 2003.
II. Qualifications
NCI is a specialized independent consulting firm providing litigation, financial,
restructuring, strategic and operational consulting services to government agencies,
legal counsel and large companies facing the challenges of uncertainty, risk, distress and
significant change. I, Kenneth W. Blair, P. E., am a Principal with NCI and have
developed and reviewed numerous claims for schedule delay and disruption on
construction-related contracts. The opinions expressed in this report are based upon my
education, training, knowledge, experience and expertise in assessing delay, as well as
003
;.
Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 4 of 14
an analysis of the relevant information that has been made available to me and the professional staff working at my direction as of the date of this report. A copy of my
curriculum vitae is included in Appendix 1.
III. Documents
In forming my opinion, I examined contemporaneous project records and publicly
available information as well as reports, pre-trial submissions and transcripts generated
during the course of the discovery process. The documents relied upon in developing
the conclusions herein are contained in the Exhibit List submitted by the Deparbnent of
Justice. Additional information considered in developing the conclusions is included in
Appendix 2. I have also identified and requested information that I understand exists,
but has not yet been provided by the Plaintiffs. Such information is included in
Appendix 3. If this or other additional information becomes available to me, I reserve
the right to revise this report and the opinions stated herein, as necessary.
IV. Our Understanding
A. Connecticut Yankee
1. CY' s
Proposed Stipulation of Fact No. 136 dated July 13
1999 indicates that fuel
transfer to the ISFSI would be completed in February 2003.
004
Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 5 of 14
2. CY's Proposed
Stipulation of Fact No. 206 dated March 28, 2003
indicates that
fuel transfer to the ISFSI would be completed in December 2003.
3. Bechtel
Power Corporation (" Bechtel" ) entered into a firm fixed price contract
with CY on April 3, 1999 to provide deco:mmissioning services, including the
design and construction of the ISFSI. Work commenced shortly thereafter.
4. In accordance with the
contract, Bechtel issued a planned schedule on June 19,
1999 with a data date (or status date) of April 30, 1999. This planned schedule
indicates that fuel transfer to the ISFSI would be completed on February 5, 2003,
consistent with CY's Stipulation of Facts dated July 13, 1999. Bechtel issued
subsequent weekly and/or monthly updates to this schedule periodically
throughout its tenure on the project.
5. The
last project schedule update provided during the time period of the schedule
analysis has a data date of May 6, 2002. This schedule indicates that fuel transfer
to the ISFSI would be completed on December 28, 2003, consistent with CY'
Stipulation of Facts dated March 28, 2003.
6. The planned submittal
date of the Safety Analysis Report
(If
SARIf Storage
Amendment to the Nuclear Regulatory Commission
NRCIf was November 1,
1999.
7. The actual
submittal date of the SAR Storage Amendment to the NRC was May
19, 2000.
005
Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 6 of 14
8. The planned approval date
of the SAR Storage Amendment was December 21,
2000.
9. The
actual approval date of the SAR Storage Amendment was November 28,
2001.
10. The planned date for obtaining a Certificate of Compliance was September 5,
2001.
11. The actual, date for obtaining a Certificate of Compliance was May 29, 2002.
12. CY issued a written directive to Bechtel on December 14, 2000
postponing
construction work for the ISFSI facility and haul road until further notice.
13. CY withdrew its postponement to Bechtel' s mobilization for ISFSI civil work on
February 19, 2002.
14. Bechtel commenced construction efforts at the ISFSI on March 18, 2002.
15. On March 27, 2002, Bechtel submitted a " Proposal for Time Extensions and
Impact Costs - ISFSI" related to CY' s direction to postpone work at the ISFSI
from December 14
2000 through February 19, 2002. Bechtel requested
reimbursement from CY in the amount of $11, 654,884 as well as time extensions
of 383 days to Contract Milestones 21. , 21.26 and 21.27, and a time
461 days to Contract Milestone 21.23.
extension of
16. CY and Bechtel agreed to an " ISFSI Claim Settlement" in the amount of
510 000 for damages claimed by Bechtel and its subcontractors resulting from
006
Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 7 of 14
the delayed start of Bechtel' s work at the ISFSI. This settlement is set forth in
Agreed Change Order 02- 15, effective date September 3, 2002.
17. Shortly after Bechtel' s commencement of construction on March 18, 2002, the
ISFSI civil work was again postponed due to archeological and wetlands issues. .
18. A Letter to Proceed was issued on July 9, 2002 that allowed Bechtel's work at the
ISFSI haul road, pad and monitoring station to proceed.
B. Maine Yankee
(fl
. Stone & Webster Engineering Corporation
SWEC" entered into a firm fixed
price contract with MY effective August 31, 1998 to provide decommissioning
services, including the design and construction of the ISFSI. Work commenced
shortly thereafter.
2. The contract
provided for a schedule to complete fuel transfer and all other items
necessary to eliminate the operation of the spent fuel pool by August 20, 2002.
3.
(If
NAC International
NAC" entered into a firm fixed price subcontract with
SWEC effective November 30, 1998 to provide the engineering, licensing,
fabrication and supply of casks, canisters and ancillary equipment for the spent
fuel storage and transfer system.
4. In accordance with
its contract with MY, SWEC issued a planned schedule on
April 6, 1999 that indicated a
completion of fuel transfer by August 13, 2002.
007
Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 8 of 14
5. MY' s Proposed Stipulation of Fact No. 186 dated June 30,
1999 indicates that fuel
transfer to the ISFSI would be completed in August
2002.
6. On November 18, 1999, MY issued a formal notice of default to SWEC and
demanded that SWEC take immediate action to remedy the deficiencies in its
performance.
7. On May 4, 2000, MY issued a notice to SWEC stating that
it was terminating the
decommissioning contract based upon SWEC's insolvency and because SWEC
had not adequately performed under the contract.
8. Following
SWEC's termination, MY re-negotiated SWEC's subcontract with
NAC and subsequently issued a change order to NAC on January 11, 2001 which
added the fuel transfer to its scope of work.
9. The planned delivery
of the first canister was December 15, 2000.
10. The actual delivery of the first canister occurred on April 3, 2001.
11. The planned start of fuel transfer was April 13, 2001.
12. The actual start of fuel transfer was August 12, 2002.
13. MY terminated NAC's contract effective January 15, 2003.
14. MY' s Proposed Stipulation of Fact No. 186 dated March 28, 2003
indicates that
fuel transfer to the ISFSI would be completed in December 2003.
008
Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 9 of 14
C. Yankee Atomic
1. NAC entered into a Hardware Contract with YA effective May 29, 1996.
2. NACentered into a Fuel Transfer Contract with YA effective November 27, 2000.
3. The planned delivery
of the first canister was April 14, 1998.
4. The
actual delivery of the first canister occurred in the last week of December
2000.
5. The planned
start of fuel transfer was June 21, 2001.
6. The actual
start of fuel transfer was May 30, 2002.
7. The planned completion of
fuel transfer was March 9, 2002.
8. The actual
completion of fuel transfer was June 25, 2003.
V. Summary of Opinions
A. Connecticut Yankee
1. Bechtel' s
planned schedule with a data date of April 30, 1999 has been
represented as the as-planned schedule. The schedule indicates that Bechtel's
plan for the ISFSI was consistent with the milestones outlined in its contract with
CY.
2. Bechtel's schedule update with a data date of May 6, 2002 includes the as-built
and projected schedule information for the ISFSI for the time period consistent
009
Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 10 of 14
with CY' s Stipulation of Facts dated March 28, 2003. The schedule indicates that
the projected completion of fuel transfer is December 28, 2003.
3. The as-built
critical path has been established based, in part, on the information
contained in the May 6, 2002 schedule. The amount of critical delay incurred
between Bechtel's contract award on April 3, 1999 and May 6, 2002 has been
determined.
4. Overall delay
is measured by comparing the actual completion of critical path
activities with the corresponding planned dates for Such activities. There is an
ll-month delay to the planned completion of fuel transfer as of May 6, 2002
as
identified in Bechtel's project schedule. This delay is the result of CY' s direction
to postpone construction work at the ISFSI,
and is not related to the actions or
inactions of the Deparbnent of Energy (" DOE"
5. Agreed Change Order 02- 15
represents settlement of damages claimed by
Bechtel related to CY' s direction to postpone work at the ISFSI from December
14, 2000 through February 19. 2002, and is not related to the actions or inactions
of the DOE.
010
Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 11 of 14
B. Maine Yankee
1. SWEC's schedule of April 6, 1999 has been represented
as the as-planned
schedule. The schedule indicates that SWEC's plan was consistent with the
completion milestone outlined in its contract with MY.
2. MY provided a schedule with a data date of July 17, 2003 that reflected the asbuilt activities completed up until that time and projected the remaining fuel
transfer activities would complete on March 6, 2004, three (3) months later thaI\
the December 2003 projection in MY' s Stipulation of Facts dated March 28, 2003.
3. The as-built
critical path has been established based, in part, on the information
contained in the July 17, 2003 schedule. The amount of critical delay incurred
between SWEC's contract award on August 31 1998 and July 17, 2003 has been
determined.
4. Overall
delay is measured by comparing the actual completion of critical path
activities with the corresponding planned dates for such activities. There is a 16month delay to the planned completion of fuel transfer as identified in MY'
Stipulation of Facts dated March 28, 2003. This delay is the result of SWEC'
performance and ultimate termination as well as NAC's performance and
ultimate termination, and is not related to the actions or inactions of the DOE.
011
Case 1:98-cv-00126-JFM
Document 815-3
Filed 06/01/2004
Page 12 of 14
C. Yankee Atomic
1. Unlike
CY and MY, there was no overall decommissioning contractor that was
responsible for coordinating all of the decommissioning activities including
activities related to the transfer of fuel to the ISFSI. Instead, two separate
contracts were issued to NAC related to the equipment needed for fuel transfer
and the actual transfer of fuel to the ISFSI. The first is known as the Hardware
Contract and the second is the Fuel Transfer Operations Contract, or FTOC. The
contract milestones outlined in these contracts were utilized as the baseline in the
review of activities leading to and actually transferring fuel to the ISFSI.
2. As there
was no comprehensive project schedule, a detailed as-built schedule
was generated utilizing contemporaneous documents including, but not limited
to, correspondence, weekly fabrication logs, monthly project reports,
transmittals, submittals, invoices, amendments to the Contracts, and Certificates
of Compliance.
3. The
critical path of the as-built schedule has been determined as well as the
amount of critical delay incurred between May 29, 1996, the award date of
NAC's Hardware Contract, and June 25, 2003, the completion of fuel transfer.
4. Eleven
months of critical path delay to the completion of fuel transfer is the
result of contractor delays to the fuel transfer preparation activities, and is not
related to the actions or inactions of the DOE.
012
~~'
...
..
: ~ . ' ..;;: :. ~""."'.... "
.. . ,.. .
' .. , '
... . ....,.. ...,. .. ...
..
-_'." -.
.. -
"
:.
. "
""".. :.
.., ,
' . !";" :::':-::.,.~...,.,.,:~:, . .-... ..,. ..... ,..;;:,.~~;'~:,'_",.:. :;,... . ..",'" '":: ,-.:,,'"... '. . ;'. --... , _.. ,. ,:. .~. .,.' . ~.. " ,~~;~ , ' .~:. ; . '.. . .
.. .. ,.. '
'.' '.
Case 1:98-cv-00126-JFM F::"
J:::,
Document 815-3
Filed 06/01/2004
Page 13 of 14
:1.
~::f~
. J:~;~'
t:.
013
;.
Case 1:98-cv-00126-JFM Document 815-3 Filed 06/01/2004 Page 14 of 14
Appendix 1- Curriculum Vitae
Kenneth W. Blair, P.
My qualifications as an expert in scheduling are based upon my work experience in the
engineering, construction, and govermrient contract industries for over thirty years. I
am currently a Principal at Navigant Consulting, Inc. (" NCI" ) where I consult on a wide
variety of matters.
I have Bachelor of Science and Master of Science degrees in civil engineering from
Rutgers University. The degrees were awarded in 1969
and 1971, respectively.
I am a
licensed Professional Engineer in the states of New Jersey, Pennsylvania, and Maryland.
I served as a commissioned officer in the United States Army Reserve Corps of
Engineers from 1969 through 1977.
My career began in 1969 as a Structural Engineer Associate with a structural engineering
consulting firm in New Jersey. In this capacity, I was responsible for the structural
design, specification preparation and field inspection of many types of concrete, steel
and timber structures. I also evaluated existing structures for safety, alternate uses, and
code compliance. My work involved coordination with clients and govemmentaV
regulatory agencies, as well as architects, engineers, contractors and owners.
After leaving the structural engineering consulting firm, I joined the Technical Services
Division of the New Jersey Housing Finance Agency. The Housing Finance Agency was
responsible for design, construction, financing, and management of low-rise, mid-rise,
and high-rise housing throughout the State of New Jersey. I served as Senior Structural
Engineer and, subsequently, as Manager of Engineering and Construction. In the latter
position, I had responsibility for the engineering deparbnent, coordination with
architectural teams and other consultants, geotechnical investigations of sites,
014