Case 1:04-cv-00461-BAF

Document 36

Filed 04/28/2006

Page 1 of 3

IN THE UNITED STATES COURT OF FEDERAL CLAIMS CADDELL CONSTRUCTION CO., INC., ) ) Plaintiff, ) ) v. ) ) UNITED STATES OF AMERICA, ) ) Defendant. )

No. 04-461C (Judge Futey)

JOINT STATUS REPORT Based upon a modification to the anticipated completion of work by defendant's experts, and the Court's availability for a two-week trial in early 2007, the parties have conferred and propose the following pretrial schedule. 1. Defendant's experts will conclude their work and issue

reports by July 14, 2006. 2. Plaintiff shall have an opportunity to depose

defendant's experts until September 1, 2006. 3. Plaintiff shall have the opportunity to submit rebuttal

expert reports by October 15, 2006, after which the rebuttal experts will be deposed by defendant prior to December 1, 2006. 4. Plaintiff shall file its Appendix A pretrial materials Plaintiff shall submit its trial exhibits

by December 1, 2006.

to defendant by the same date. 5. Defendant shall file its Appendix A pretrial materials Defendant shall submit its trial exhibits

by January 15, 2007.

to defendant by the same date.

K:\My Documents\Caddell\status report re trial schedule.wpd

Case 1:04-cv-00461-BAF

Document 36

Filed 04/28/2006

Page 2 of 3

6.

The Court will schedule a pretrial conference at its

convenience any time after January 15, 2007. 7. The Court will schedule a trial in Jackson, Mississippi,

during the first half of March 2007, with an estimated duration of two weeks. 8. The parties request that the Court accept the use of

electronic exhibits at trial. If the Court is unable to conduct the trial in the first half of March 2007, the parties may wish to propose a revised pretrial schedule based upon the actual trial date. Respectfully submitted, PETER D. KEISLER Assistant Attorney General DAVID M. COHEN Director s/Bryant G. Snee BRYANT G. SNEE Assistant Director s/Brian S. Smith BRIAN S. SMITH Attorney Commercial Litigation Branch Civil Division Department of Justice Washington, D.C. 20530 Telephone: (202) 616-0391 Fax: (202) 353-7988 Attorneys for Defendant s/David W. Mockbee MOCKBEE HALL & DRAKE, P.A. Lamar Life Building, 10th Floor
K:\My Documents\Caddell\status report re trial schedule.wpd

2

Case 1:04-cv-00461-BAF

Document 36

Filed 04/28/2006

Page 3 of 3

317 East Capitol Street Jackson, Mississippi 39201 601/353-0035 Telephone 601/353-0045 Facsimile Attorney for Plaintiff April 28, 2006

K:\My Documents\Caddell\status report re trial schedule.wpd