Case 1:04-cv-00461-BAF
Document 56
Filed 12/12/2006
Page 1 of 3
IN THE UNITED STATES COURT OF FEDERAL CLAIMS CADDELL CONSTRUCTION CO., INC., Plaintiff, v. UNITED STATES OF AMERICA, Defendant. ) ) ) ) ) ) ) ) ) )
No. 04-461C (Judge Bohdan A. Futey)
PLAINTIFF'S SUPPLEMENTAL EXHIBIT LIST Plaintiff, Caddell Construction Co., Inc. ("Caddell"), supplements its Exhibit List filed November 22, 2006 based upon issues raised for the first time by Defendant, United States of America, in its Memorandum of Contentions of Fact and Law: Ex # P-194 P-195 P-196 P-197 P-198 P-199 P-200 P-201 P-202 P-203 Date 4/10/96 5/8/96 5/14/96 5/15/96 6/22/96 7/2/96 7/25/96 8/28/96 9/4/96 9/25/96 Description VA/Caddell Job Meeting No. 1 minutes VA/Caddell Job Meeting No. 5 minutes VA letter to JMGR re: A/E response to RFI No. 146 VA/Caddell Job Meeting No. 6 minutes VA/Caddell Job Meeting No. 7 minutes VA letter to JMGR re: A/E response to RFI No. 200 Caddell letter to VA re: precast questions VA/Caddell Job Meeting No. 20 minutes VA/Caddell Job Meeting No. 21 minutes VA/Caddell Job Meeting No. 24 minutes with attached request for information standard overdue option report VA/Caddell Job Meeting No. 27 minutes
P-204
10/16/96
HallL\exh\4460.035 Plf Exhibit List-revised 112006.wpd
Case 1:04-cv-00461-BAF
Document 56
Filed 12/12/2006
Page 2 of 3
Ex # P-205
Date 10/24/96
Description VA letter to Caddell re: RFI No. 309 with attached 10/23/96 VA handwritten memo re: same VA letter to JMGR re: structural steel shop drawing review VA/Caddell Job Meeting No. 33 minutes with attached overdue option reports VA letter to Caddell re: clarification for stair no. 7 roof with attached sketches VA letter to JMGR re: RFI No. 508 with attached RFI No. 508 VA letter to JMGR re: bracing tops of CMU partitions VA letter to JMGR re: plumbing conflicts VA letter to JMGR re: precast supports VA price negotiation memorandum re: change to increase electrical service Amendment of Solicitation/Modification of Contract No. FSA-271 re: precast erection problems
P-206 P-207 P-208
11/15/96 12/4/96 1/13/97
P-209 P-210 P-211 P-212 P-213 P-214
5/13/97 7/8/97 9/4/97 11/19/97 4/12/99 7/13/00
Respectfully submitted, CADDELL CONSTRUCTION CO., INC., PLAINTIFF By: /s/ David W. Mockbee David W. Mockbee MOCKBEE HALL & DRAKE, P.A. Lamar Life Building, Ste 1000 317 E. Capitol Street Jackson, MS 39201 (601) 353-0035 - Telephone (601) 353-0045 - Facsimile
HallL\exh\4460.035 Plf Exhibit List-revised 112006.wpd
2
Case 1:04-cv-00461-BAF
Document 56
Filed 12/12/2006
Page 3 of 3
CERTIFICATE OF SERVICE I, David W. Mockbee, do hereby certify that I have this day caused to be filed via the Official Electronic Document Filing System of the United States Court of Federal Claims ("CM/ECF") a true and correct copy of the above and foregoing Plaintiff's Exhibit List. Copies of this document will be transmitted via Additional
the Court's CM/ECF System to all counsel of record.
copies may be obtained through the Court's CM/ECF System. Dated: December 12, 2006. /s/ David W. Mockbee David W. Mockbee
HallL\exh\4460.035 Plf Exhibit List-revised 112006.wpd
3