Free Joint Status Report - District Court of Federal Claims - federal


File Size: 16.8 kB
Pages: 4
Date: July 7, 2006
File Format: PDF
State: federal
Category: District
Author: unknown
Word Count: 816 Words, 5,346 Characters
Page Size: Letter (8 1/2" x 11")
URL

https://www.findforms.com/pdf_files/cofc/20226/23.pdf

Download Joint Status Report - District Court of Federal Claims ( 16.8 kB)


Preview Joint Status Report - District Court of Federal Claims
Case 1:05-cv-00751-NBF

Document 23

Filed 07/07/2006

Page 1 of 4

IN THE UNITED STATES COURT OF FEDERAL CLAIMS CINCINNATI INSURANCE COMPANY, Plaintiff, v. THE UNITED STATES, Defendant. ) ) ) ) ) ) ) ) )

No. 05-751C Judge Firestone

JOINT STATUS REPORT Pursuant to the Court's order dated June 2, 2006, the parties submit this joint status report regarding future proceedings to resolve this litigation. The Plaintiff's Position: In reviewing the Government's argument that FAR 28.106-7 prohibited the contracting officer during contract performance from withholding progress payments because subcontractors or suppliers have not been paid, the Court's decision questioned this provision's application to the instant facts. The Court's denial of the Government's Motion for Summary Judgment was based upon there being an issue of material fact as to whether contract performance was still ongoing as of August 4, 2004, the date of the Corps' payment to Lasker. While this FAR provision may address instances when subcontractors are not getting paid, this FAR provision has no application when Lasker had violated its contract with the Corps, the Prompt Payment Act, and the False Claims Act. Additionally, this Court has previously ruled that this FAR provision is inapplicable to payments being made following substantial completion of the project (Appeal of Indiana Lumberman's Mutual Insurance Co., 15 Cl. Ct. 62 (1988)), and the Government has previously admitted that the subject project was substantially complete some 45 days before the August 4, 2004 payment was made.

Case 1:05-cv-00751-NBF

Document 23

Filed 07/07/2006

Page 2 of 4

The Government also does not have the ability or discretion to ignore, waive or modify terms of the contract which provide security for the bonded project without considering the surety's interests or which would materially increase the surety's risk. By making payment to Lasker while knowing of Lasker's various violations and breaches, the Government wrongfully released payment and is liable to the Plaintiff for the resulting damages. The Plaintiff submits that the parties proceed forward with the discovery process and then have this matter set for trial. The Defendant's Postition: The Court's decision found that the issue of contract completion at the time that notification and payment were made is "in dispute and is material to the case." In order to resolve this factual dispute, the Government proposes that the parties could file stipulated facts regarding the status of contract performance, from which the Court may then determine whether performance was complete. The Government submits, however, that it is entitled to judgment regardless of the state of completion of the contract. FAR § 28.106-7(a) provides that, "[d]uring contract performance, agencies shall not withhold payments due contractors or assignees because subcontractors or suppliers have not been paid." (Emphasis added.) This Court acknowledged the Government's right to continue making progress payments during contract performance, stating, "`during performance of a contract, the Government's role is substantially different from that of a mere stakeholder of the final contract payment. During performance of a contract, the Government has a vital interest in the contract's completion and, as such, its contracting officer is vested with broad discretion in administering the contract for the purpose of promoting performance.' Therefore, `the decision

2

Case 1:05-cv-00751-NBF

Document 23

Filed 07/07/2006

Page 3 of 4

of a Government contracting officer that a progress payment to a financially strapped contractor should not be withheld will be accorded deference by this court . . . .'" Cincinnati Ins. Co. v. United States, 2006 WL 1645031, *4 (Fed. Cl. 2006) (citations omitted). Thus, if the Court determines that contract work was ongoing, the Government's decision to make progress payments should be accorded deference, and the Court should enter judgment for the defendant. Alternatively, FAR § 28.106-7(b) provides that, after completion of the contract work, "the contracting officer shall withhold final payment. However, the surety must agree to hold the Government harmless from any liability resulting from withholding the final payment." In this case, the plaintiff did not agree to hold the Government harmless. Accordingly, it has not satisfied a condition precedent for requiring the Government to withhold final payment. Thus, even if the Court determines that the contract work was "complete," which it was not , the Court should enter judgment for the defendant. Respectfully submitted, PETER D. KEISLER Assistant Attorney General DAVID M. COHEN Director s/ Donald E. Kinner DONALD E. KINNER Deputy Director

3

Case 1:05-cv-00751-NBF

Document 23

Filed 07/07/2006

Page 4 of 4

s/ G. Bruce Stigger G. BRUCE STIGGER Alber Crafton, PSC Hurstbourne Place, Suite 1300 9300 Shelbyville Road Louisville, KY 40222 Tel: (502) 815-5000 Fax: (502) 815-5005 Attorney for Plaintiff

s/ Doris S. Finnerman DORIS S. FINNERMAN Attorney Commercial Litigation Branch Civil Division Department of Justice Attn: Classification Unit 8th Floor 1100 L Street, N.W. Washington, D.C. 20530 Department of Justice Tel: (202) 307-0300 Fax: (202) 305-7643 Attorneys for Defendant

July 7, 2006

4