Free Proposed Findings of Uncontroverted Fact - District Court of Federal Claims - federal


File Size: 14.8 kB
Pages: 3
Date: October 27, 2005
File Format: PDF
State: federal
Category: District
Author: unknown
Word Count: 681 Words, 4,363 Characters
Page Size: Letter (8 1/2" x 11")
URL

https://www.findforms.com/pdf_files/cofc/20226/9.pdf

Download Proposed Findings of Uncontroverted Fact - District Court of Federal Claims ( 14.8 kB)


Preview Proposed Findings of Uncontroverted Fact - District Court of Federal Claims
Case 1:05-cv-00751-NBF

Document 9

Filed 10/27/2005

Page 1 of 3

IN THE UNITED STATES COURT OF FEDERAL CLAIMS CINCINNATI INSURANCE COMPANY, Plaintiff, v. THE UNITED STATES, Defendant. ) ) ) ) ) ) ) ) )

No. 05-751C (Judge Firestone)

DEFENDANT'S PROPOSED FINDINGS OF UNCONTROVERTED FACT Pursuant to RCFC 56(h)(1), defendant respectfully submits the following proposed findings of uncontroverted fact in support of Defendant's Motion For Summary Judgment: 1. In 2003, the United States Army Corps of Engineers ("Corps") entered into a

construction contract with Lasker, Inc. ("Lasker"). Compl. ¶ 3. The total initial contract price was $1,811,000.00. Ex. 1. 2. CIC, as surety, provided payment and performance bonds for the project in the penal

sums of $1,811,000.00. Compl. ¶ 4. 3. On June 17, 2004, Lasker submitted pay application number 10, seeking $146,247.40.

Ex. 1. At the time that Lasker submitted application number 10, it had already received $1,636,923.60, leaving a balance of contract funds of $183,684.40. Pay application number 10 was not a request for final payment. Ex. 1. 4. On June 23, 2004, the Corps advised CIC that the Corps contemplated paying Lasker

only $67,000, while retaining $116,000 for closeout, punchlist, and incomplete work. Ex. 2. 5. On June 25, 2004, CIC sent a letter to the Corps, addressed to the contracting officer's

representative, advising that CIC had received claims from Lasker's subcontractors. CIC purported to "withdraw" its "previous consents" to make payment to Lasker. Ex. 3.

Case 1:05-cv-00751-NBF

Document 9

Filed 10/27/2005

Page 2 of 3

6.

As of June 18, 2004, the contract was 98 percent complete; however, there were

outstanding deficiencies and incomplete work that needed to be addressed. Exs.4 and 6. 7. On June 26, 2004, the contracting officer's representative advised Lasker that its pay

application number 10 was "not a proper invoice." The reasons stated for rejecting the application were the existence of deficiencies and/or incomplete work as reflected on a final punch list, the fact that the remaining contract balance was insufficient to protect the Government's interest for payments due to subcontractors and suppliers, the fact that subcontractors and suppliers had not been paid from previous payments, and, accordingly, Lasker's certification, pursuant to FAR 52.232-5, was inconsistent with its nonpayment of subcontractors and suppliers. Ex. 4. 8. 9. 10. On or about July 27, 2004, Lasker submitted a revised pay application number 10. Ex. 5. On August 3, 2004, payment was made to Lasker in the amount of $106,447.50. Ex. 7. On August 4, 2004, Lasker sent a letter to the Corps demanding that all further payments

be forwarded directly to CIC. Ex. 8. 11. On August 30, 2004, CIC sent a letter to the Corps advising that it had learned of the

recent payment to Lasker and demanding that Corps reimburse CIC for costs and expenses related to the "premature release of contract funds." Ex. 9. 12. The contracting officer responded on September 10, 2004, advising CIC that, in

accordance with FAR 28.106-7(a), he was precluded from withholding payment to Lasker. The letter further advised that the Corps had received an "Assignment of Claims" on August 12, 2004, but that payment to Lasker had already been made. Ex. 10. 13. On February 11, 2005, CIC filed a certified claim for damages resulting from the Corps'

payment of $106,477.50 to Lasker. Ex. 11.

Case 1:05-cv-00751-NBF

Document 9

Filed 10/27/2005

Page 3 of 3

14.

On May 17, 2005, the contracting officer denied CIC's allegation that a wrongful

payment had been made. Ex. 12. 15. To the extent that CIC made payments to subcontractors of Lasker, such payments were

made pursuant to its obligations under its payment bond with Lasker. 16. At no time did CIC finance completion of the project or execute a takeover agreement

with the Government to complete construction performance. Respectfully submitted, PETER D. KEISLER Assistant Attorney General DAVID M. COHEN Director s/ James M. Kinsella JAMES M. KINSELLA Deputy Director s/ Doris S. Finnerman DORIS S. FINNERMAN Trial Attorney Commercial Litigation Branch Department of Justice 1100 L Street, N.W. Attn: Classification Unit 8th Floor Washington, D.C. 20530 Tele: (202) 307-0300 Fax: (202) 305-7643 Attorneys for Defendant October 27, 2005