Free Cross Motion [Dispositive] - District Court of Federal Claims - federal


File Size: 245.6 kB
Pages: 54
Date: January 31, 2008
File Format: PDF
State: federal
Category: District
Author: unknown
Word Count: 9,496 Words, 65,618 Characters
Page Size: Letter (8 1/2" x 11")
URL

https://www.findforms.com/pdf_files/cofc/21006/30-1.pdf

Download Cross Motion [Dispositive] - District Court of Federal Claims ( 245.6 kB)


Preview Cross Motion [Dispositive] - District Court of Federal Claims
Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 1 of 54

No. 06-101C (Judge Allegra) IN THE UNITED STATES COURT OF FEDERAL CLAIMS

JAY CASHMAN, INC., Plaintiff, v. THE UNITED STATES, Defendant.

DEFENDANT'S OPPOSITION TO PLAINTIFF'S MOTION FOR SUMMARY JUDGMENT AND CROSS-MOTION FOR SUMMARY JUDGMENT

JEFFREY S. BUCHOLTZ Acting Assistant Attorney General JEANNE E. DAVIDSON Director DONALD E. KINNER Assistant Director OF COUNSEL: Donald M. Harris Counsel U.S. Army Engineer District New York TARA KILFOYLE Trial Attorney Commercial Litigation Branch Civil Division 1100 L St., N.W. Attn: Classification Unit 8th Floor Washington, D.C. 20530 Tele: (202) 305-1709 Fax: (202) 307-0972

January 31, 2008

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 2 of 54

TABLE OF CONTENTS STATEMENT OF THE ISSUES.................................................................................................... 1 STATEMENT OF THE CASE....................................................................................................... 2 A. B. Introduction................................................................................................. 2 The Nature Of The Work To Be Performed Under The KVK 8 Contract....................................................................................................... 2 Multibeam Surveys For The KVK Phase II And KVK 8 Contracts. .......... 4 The Specifications for KVK 8. ................................................................... 8 The Award And Performance of KVK 8. ................................................... 9

C. D. E.

STATEMENT OF FACTS. .......................................................................................................... 12 ARGUMENT................................................................................................................................ 12 I. II. Standard for Summary Judgment.......................................................................... 12 The Corps Properly Required Cashman To Meet the Contract Objective, And Cashman Is Not Entitled To Additional Compensation For Doing So......... 14 Failure to Comply With Corps Engineering Manual Requiring Information To Be Included In Dredging Contract Specification Cannot Form The Basis For Cashman's Contract Disputes Act Claim . ........................................... 16 Cashman's Failure To Inquire Regarding A Patent Ambiguity Does Not Render The Corps Liable To Cashman................................................................. 19 A. B. Legal Standards......................................................................................... 20 Cashman Did Not Inquire Regarding A Patent Ambiguity In The Specifications............................................................................................ 21

III.

IV.

V.

Cashman Did Not Reasonably Interpret The Contract To Provide That The Corps Would Produce Final Acceptance Surveys Using The Average Depth..................................................................................................................... 23 A. Legal Standards......................................................................................... 23

-i-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 3 of 54

B.

Cashman's Interpretation That The Corps Would Produce Final Acceptance Surveys Using the Average Depth Was Unreasonable ......... 24 Evidence In the Record Does Not Support The Argument That Cashman Assumed That Final Acceptance Surveys Would Be Produced Using The Average Depth Based Upon The Nature of Dredging Equipment, And Such An Assumption Would Be Unreasonable ............................................................................................ 26 It Was Unreasonable For Cashman To Assume That Multibeam Surveys Would Change The Method That The Corps Used To Accept New Work Dredging of Hard Bottom Material............................ 28 It Was Inherently Unreasonable For Cashman To Assume That The Corps Would Only Require Each Three Foot By Three Foot Cell To Be Dredged to An Average Depth of 47 Feet . ............................ 29 Information Or Opinions Acquired After Award Are Irrelevant To Whether Cashman's Interpretation Was Reasonable At The Time That Cashman Submit Its Bid . ................................................................. 31

C.

D

E.

F.

VI.

The Corps Did Not Breach The Duty To Cooperate With Cashman.................... 32 A. B. Legal Standards......................................................................................... 33 The Corps Did Not "Hide" The Product That It Would Use To Produce Acceptance Surveys From Cashman .......................................... 34 The Corps Did Not "Hide" Representatives of the Survey Section From Cashman. ......................................................................................... 38 Cashman Failed To Make The Required Contract Sumbittals Regarding Its Proposed Method For Submitting Pre-Final Acceptance Surveys . ................................................................................ 40 Mr. Galli's Testimony Indicates That Cashman Unreasonably Delayed In Seeking Formal Direction ...................................................... 40 Engineering Manuals In Effect At The Time of Contract Award Did Not Prohibit Use Of The Minimum Depth Method To Produce Acceptance Surveys. ................................................................... 41 The Corps Was Not Imposing "A More Stringent Tolerance To Determine Whether A Minimum Depth Survey Had Passed," Or Utilizing A "New Acceptance Criteria. .................................................... 44 -ii-

C.

D.

E.

F.

G.

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 4 of 54

CONCLUSION............................................................................................................................. 45

-iii-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 5 of 54

TABLE OF AUTHORITIES CASES Alliant Techsystems, Inc. v. United States, 74 Fed. Cl. 566 (2007). .................................................................................................... 20 Am-Pro Protective Agency, Inc. v. United States, 281 F.3d 1234 (Fed. Cir. 2002)........................................................................................ 34 Anderson v. Liberty Lobby, Inc., 477 U.S. 242 (1986)......................................................................................................... 12 Avtel Servs. v. United States, 70 Fed. Cl. 173 (2005). .................................................................................................... 34 Blake Constr. Co. v. United States, 987 F.2d 743 (Fed. Cir. 1993).......................................................................................... 14 Bromley Contracting Co. v. United States, 15 Cl. Ct. 100 (1988). ....................................................................................................... 13 C&L Constr. Co. v. United States, 6 Cl. Ct. 791 (1984). ........................................................................................................ 19 Celotex Corp v. United States, 477 U.S. 317 (1986)......................................................................................................... 12 Centex Corp. v. United States, 395 F.3d 1283 (Fed. Cir. 2005).................................................................................. 34, 42 Conner Bros. Constr. Co. v. United States, 65 Fed. Cl. 657 (2005). .................................................................................................... 14 Engineered Demolition, Inc. v. United States, 70 Fed. Cl. 580 (2006). .................................................................................................... 21 Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed. Cir. 1985).............................................................................. 21 Freightliner Corp. v. Caldera, 225 F.3d 1361 (Fed. Cir. 2000)........................................................................................ 19

-iv-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 6 of 54

Fruin-Colnon Corp. v. United States, 912 F.2d 1426 (Fed. Cir. 1990)............................................................................ 24, 26, 31 Fry Communications, Inc. v. United States, 22 Cl. Ct. 497 (1991). ...................................................................................................... 31 Galen Med. Assocs. v. United States, 369 F.3d 1324 (Fed. Cir. 2004)........................................................................................ 34 Granite Mgmt. Corp. v. United States, 74 Fed. Cl. 155 (2006). .................................................................................................... 34 HPI/GSA-3C, LLC v. Perry, 364 F.3d 1327 (Fed. Cir. 2004).................................................................................. 23, 24 Interwest Constr. v. Brown, 29 F.3d 611 (Fed. Cir. 1994)................................................................................ 15, 20, 23 Lockheed Martin IR Imaging Syst., Inc. v. West, 108 F.3d 319 (Fed. Cir. 1997).......................................................................................... 20 M.G. Constr., Inc. v. United States, 67 Fed. Cl. 176 (2005). .................................................................................................... 21 Maintenance Engineers, Inc. v. United States, 21 Cl. Ct. 553 (1990). .......................................................................................... 24, 26, 31 Manson Constr. Co. v. United States, 79 Fed. Cl. 16 (2007). ...................................................................................................... 17 Mega Constr. Co. v. United States, 29 Fed. Cl. 396 (2003). .................................................................................................... 22 Metric Constructors v. Nat'l Aeronautics & Space Admin, 169 F.3d 747 (Fed. Cir. 1999).......................................................................................... 20 NVT Techs., Inc. v. United States, 370 F.3d 1153 (Fed. Cir. 2004)........................................................................................ 13 Natural Res. Def. Council v. United States Army Corps of Eng'rs, 399 F. Supp. 2d 386 (S.D.N.Y. 2005)................................................................................ 2 North Star Alaska Hous. Corp. v. United States, 76 Fed. Cl. 158 (2007). .................................................................................................... 34 -v-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 7 of 54

O'Connor v. United States, 308 F.3d 1233 (Fed. Cir. 2002)........................................................................................ 13 PDR , Inc. v. United States, 78 Fed. Cl. 201 (2007). .................................................................................................... 13 P.R. Burke Corp. v. United States, 277 F.3d 1346 (Fed. Cir. 2002).................................................................................. 15, 20 Precision Pine & Timber v. United States, 50 Fed. Cl. 35 (2001). ...................................................................................................... 33 Redland Genstar, Inc. v. United States, 39 Fed. Cl. 220 (1997). .................................................................................................... 19 Reynolds Assocs. v. United States, 31 Fed. Cl. 335 (1994). .................................................................................................... 18 S. Cal. Edison v. United States, 58 Fed. Cl. 313 (2003). .................................................................................................... 34 Short Bros., PLC v. United States, 65 Fed. Cl. 695 (2005). .................................................................................................... 34 St. Christopher Assocs., L.P. v. United States, 75 Fed. Cl. 1 (2006). ........................................................................................................ 18 St. Christopher Assocs., L.P. v. United States, Fed. Cir. No. 2007-5069 at 10-14, 2008 U.S. App. LEXIS 324 (Jan. 9, 2008)............... 18 Stuyvesant Dredging Co. v. United States, 834 F.2d 1576 (Fed. Cir. 1987)........................................................................................ 15 Sweats Fashions, Inc. v. Pannill Knitting Co., 833 F.2d 1560 (Fed. Cir. 1987)........................................................................................ 13 Sys. Fuels, Inc. v. United States, 66 Fed. Cl. 722 (2005). .................................................................................................... 34 Tecom, Inc. v. United States, 66 Fed. Cl. 736 (2005). .................................................................................................... 34 Torncello v. United States, 681 F.2d 756 (Ct. Cl. 1982). ............................................................................................ 34 -vi-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 8 of 54

Travelers Cas. & Sur. Co. of Am. v. United States, 75 Fed. Cl. 696 (2007). .................................................................................................... 13 Travelers Cas. & Sur. of Am. v. United States, 74 Fed. Cl. 75 (2006). ................................................................................................ 20, 22 Triax Pac., Inc. v. West, 130 F.3d 1469, 1474 (Fed. Cir. 1997).............................................................................. 21 Turner Constr. Co. v. United States, 367 F.3d 1319 (Fed. Cir. 2004)........................................................................................ 23 United States v. Turner Constr. Co., 819 F.2d 283 (Fed. Cir. 1987).......................................................................................... 23 Walter Dawgie Ski Corp. v. United States, 30 Fed. Cl. 115 (1993). .................................................................................................... 33 White v. Edsall Constr. Co., 296 F.3d 1081 (Fed. Cir. 2002)........................................................................................ 32

-vii-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 9 of 54

IN THE UNITED STATES COURT OF FEDERAL CLAIMS

JAY CASHMAN, INC., Plaintiff, v. THE UNITED STATES, Defendant.

) ) ) ) ) ) ) ) )

No. 06-101C (Judge Allegra)

DEFENDANT'S OPPOSITION TO PLAINTIFF'S MOTION FOR SUMMARY JUDGMENT AND CROSS-MOTION FOR SUMMARY JUDGMENT Pursuant to Rule 56 of the Rules of the United States Court of Federal Claims ("RCFC"), defendant, the United States, respectfully requests that the Court grant summary judgment in favor of defendant and deny plaintiff, Jay Cashman, Inc.'s ("Cashman's") motion for summary judgment. In support of our motion, we rely upon the Complaint, pleadings and appendix filed by Cashman, defendant's Answer, Proposed Findings of Uncontroverted Fact and responses to Cashman's Proposed Findings of Uncontroverted Fact, and the following brief and appendix. STATEMENT OF THE ISSUES 1. Whether the United States Army Corps of Engineers (the "Corps") required Cashman to

perform work beyond the requirements of contract DACW51-03-C-0014 (the "KVK 8 contract"), in requiring Cashman to dredge the contractually defined area to a depth of 47 feet. 2. Whether the Corps' failure to comply with a provision in a Corps engineering manual

stating that certain information "shall" be included in dredging contract specifications provides Cashman with a cause of action against the United States, where the engineering manual was not part of or incorporated into Cashman's contract. -1-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 10 of 54

3.

Whether the KVK 8 contract was patently ambiguous regarding the multibeam survey

product that the Corps would use to determine that Cashman had achieved the contractually required depth, and whether Cashman failed to make inquiry regarding the ambiguity prior to submitting its bid. 4. In the alternative, whether Cashman's interpretation regarding the multibeam survey

product that the Corps would use to determine that Cashman had achieved the contractually required depth was reasonable. 5. Whether Cashman has established that the Corps breached its duty to cooperate. STATEMENT OF THE CASE A. Introduction This case arises out of the KVK 8 contract, which was awarded to Cashman by the New York District of the Corps in May 2003. Defendant's Proposed Findings of Uncontroverted Fact ("DPFUF") ¶ 30; Defendant's Appendix ("Def. App.") 14; 39. The contract required Cashman to dredge the contract area to a depth of 47 feet, and stated that the Corps would use acoustic multibeam surveys to determine whether Cashman had achieved the required depth. DPFUF ¶¶ 31, 44; Def. App. 14; 71; 74; 130. A dispute arose regarding the multibeam acceptance survey product that the Corps used to determine that the contractually required depth had been achieved. B. The Nature Of The Work To Be Performed Under The KVK 8 Contract The Port of New York and New Jersey (the "port") is the third largest port in the nation, and the largest port on the East Coast. See Natural Res. Def. Council v. United States Army Corps of Eng'rs, 399 F. Supp. 2d 386, 391 (S.D.N.Y. 2005); DPFUF ¶ 1; Plaintiff's Appendix ("Pl. App." 4). Billions of dollars worth of cargo pass through the port on an annual basis. See -2-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 11 of 54

id. Beginning in 1986, Congress authorized the Corps to undertake a number of projects to deepen the navigational channels in the New York and New Jersey Harbor to meet industry demand for larger and deeper-bottomed cargo vessels to use the channels. DPFUF ¶ 2; Pl. App. 3-4; Def. App. 1-2. As part of this effort, the New York District of the Corps embarked upon the Kill Van Kull and Newark Bay Navigation Improvement Project (the "KVK project") to deepen the Kill Van Kull and Newark Bay Channels (the "channels"), which form the main artery linking the Ports of Elizabeth and Newark Bay. DPFUF ¶ 3; Pl. App. 4; Def. App. 1-2.. Phase I of the KVK project ("KVK Phase I"), which was substantially completed in 1995, involved a series of contracts to lower the depth of the channels to 42 feet1 below mean low water.2 DPFUF ¶ 4; Def. App. 77; 127; 153. The Corps included a two foot safety factor beyond the authorized depth of the channel for navigational purposes, because the KVK project involved rock and hard material, raising concerns that a vessel could hit the bottom of the channel and be seriously damaged. DPFUF ¶ 8; Def. App. 4; 77. Phase II of the KVK project ("KVK Phase II"), which was completed between 1999 and 2004, involved a series of contracts to lower the depth of the channels to 47 feet below mean low water. DPFUF ¶ 5; Def. App. 3-4; 77. There are future plans to lower the depth of the channels to 52 feet below mean low water, but the channels are currently authorized for use by vessels as 45-foot channels.3 DPFUF ¶ 6; Def. App. 5-6; 65; 79-80.

1

The authorized depth of the channels for navigational purposes was 40 feet. In simplistic terms, "mean low water" refers to an average low tide.

2

If the authorized depth of the channel for navigational purposes is 45 feet, a ship with a draft of more than 45 feet should not use the channel. Def. App. 78; 152. -3-

3

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 12 of 54

KVK Phase II involved "new work" dredging, meaning deepening projects that involve dredging below the published elevation of the channels at the time that the projects began. DPFUF ¶ 9; Def. App. 7; Pl. App. 8. KVK Phase II also involved the dredging of "hard bottom" materials, such as rock or compacted gravel, till, or heavy clays. DPFUF ¶ 9; Pl. App. 8, Def. App. 4; 77-78. KVK Phase II was divided into eight separate contracts for eight defined areas of the project. DPFUF ¶ 10; Def. App. 8-9; Pl. App. 3. These eight contracts were awarded to five different dredging prime contractors, and were awarded and completed on a rolling basis between 1999 and 2004.4 Id. The KVK 8 contract, which was awarded to Cashman on May 23, 2003, was the final contract of KVK Phase II to be awarded and completed. DPFUF ¶ 26; Pl. App. 1-3, Def. App. 13; 40-43. C. Multibeam Surveys For The KVK Phase II And KVK 8 Contracts

Hydrographic multibeam surveys ("multibeam surveys") involve an acoustic survey system that indirectly measures the depth of a channel. DPFUF ¶ 11. A sonar system transmits a fan of acoustic signals into the water to create a sounding. Id.; Def. App. 235 (Declaration of William McDonald ¶ 6); Def. App. 49-51. When the signals hit the seabed, or an object under water, energy is created that returns to the multibeam system. DPFUF ¶ 11; Def. App. 49-51; Def. App. 235 (Declaration of William McDonald ¶ 6). The multibeam system records the time

In Cashman's motion, Cashman asserts that prior to the KVK 8 contract, the previous KVK Phase II contracts had been awarded to three different dredging contractors. See Memorandum of Points and Authorities In Support of Plaintiff's Motion For Summary Judgment ("Pl. Memo.") at 3. This is incorrect. Prior to the KVK 8 contract, the previous KVK Phase II contracts had been awarded to four different dredging prime contractors. See DPFUF ¶ 10; Def. App. 9. -4-

4

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 13 of 54

that it takes for the acoustic signals to travel to the seafloor (or underwater object) and back to the system. Id. This information can be used to calculate the depth to the seafloor or underwater object. Id. After data is recorded by the multibeam sonar system, it is edited and processed by computer programs to filter out extraneous data ("noise"). DPFUF ¶ 12; Def. App. 52; 235 (Declaration of William McDonald ¶ 7). There are a number of survey products that can be produced based upon the edited data.5 DPFUF ¶ 13; Def. App. 52; 235 (Declaration of William McDonald ¶ 7). Surveys can be produced using the average depth, which averages the survey data points in a three foot by three foot "bin" or "cell" of a designated area of the contract. DPFUF ¶ 14; Def. App. 120-21; 235 (Declaration of William McDonald ¶ 7). Surveys can also be produced using the minimum depth or "shoalest" depth, which represents whether the shallowest data points in a three foot by three foot cell are above the contractually required depth. DPFUF ¶ 15; Def. App. 52; 120-21; 235 (Declaration of William McDonald ¶ 7). In a survey produced using the minimum depth, if at least three data points within a three foot by three foot cell are confirmed to be high spots above the contractually required depth, the cell is not at the contractually required depth. DPFUF ¶ 15; Def. App. 58-58; Def. App. 235 (Declaration of

Cashman refers to the various survey products as "data processing methods." See Memorandum of Points and Authorities In Support of Plaintiff's Motion For Partial Summary Judgment ("Pl. Memo") at 5. The Corps considers the process of filtering or editing extraneous "noise" spikes, or inaccurate data points, out of multibeam survey data to be "data processing." See EM 1110-2-1003 ¶ 11-12(a), January 1, 2002, Def. App. 129. Average depth or minimum depth surveys are survey products produced from multibeam survey data after the data processing occurs, and are outputs, rather than processes. See EM 1110-2-1003 ¶ 11-12(b), January 1, 2002, Def. App. 129. The process of generating the survey outputs is known as "binning or gridding routines." Id. This explanation is provided solely to assist the Court in understanding why the parties have used slightly different terminology, and should not affect the outcome of this case. -5-

5

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 14 of 54

William McDonald ¶ 7). Both contractors and the Corps used multibeam surveys for a number of purposes on the KVK Phase II contracts. DPFUF ¶¶ 36-37; Pl. App. 22, Def. App. 68; 168-69; 242 (Declaration of Salvatore DiDato ¶ 8). Only "after-dredge surveys," or surveys undertaken after a contractor has commenced dredging operations, are at issue in the present litigation. The KVK 8 contract required Cashman to perform monthly progress payment surveys, to determine the quantity of material dredged for progress payment purposes. DPFUF ¶ 37; Def. App. 168-69. When Cashman believed that it had reached the contractually required depth, it was required to perform a pre-final acceptance survey to advise the Corps that it believed that the area was ready for final acceptance. DPFUF ¶ 37; Pl. App. 22. The Corps would then perform a final acceptance survey to determine that the work had been dredged to the contractually required depth. Id. The Corps also performed final payment surveys to determine the final quantity of material removed for payment purposes.6 DPFUF ¶ 37; Def. App. 168-69. For all of the KVK Phase II contracts, payment surveys were produced using the average depth, because it provided a more equitable volume calculation for payment purposes. DPFUF ¶ 42; Def. App. 123; 167. Acceptance surveys were produced using the minimum depth, because it ensured that the contractor had achieved the contractually required depth, and there were no high spots or "shoals" that could potentially cause damages to vessels. Id. There were three primary types of materials to be dredged under the KVK 8 Contract -

In some instances, the Corps' survey data taken from a final acceptance survey could also be used to produce a final payment survey. However, this could only occur if an area was accepted on the first attempt. DPFUF ¶ 38; Def. App. 237 (Declaration of William McDonald ¶ 11). -6-

6

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 15 of 54

softer materials, such as silt, that could not be placed in the Historic Area Remediation Site ("HARS") after removal, and hard materials such as glacial till, clay and rock material, that could be placed in the HARS after removal, and rock.7 DPFUF ¶ 39; Def. App. 70; 162-63. For the material unsuitable for placement in the HARS, the contractor was to perform monthly progress payment surveys. DPFUF ¶ 40; Def. App. 168-69. In addition, the Corps conducted final payment surveys to determine the final quantity of material removed after dredging of the material unsuitable for the HARS in a contractually defined area was complete. DPFUF ¶ 40; Def. App. 69. However, the contractor was not required to perform pre-final acceptance surveys for the material unsuitable for placement in the HARS, and the Corps did not perform acceptance surveys for this material, because all of this material was located above the contractually required depth of 47 feet. DPFUF ¶ 40; Def. App. 71; 242 (Declaration of Salvatore J. DiDato ¶ 10). Therefore, the contractor could never achieve the contractually required depth by removing the material. The contractor was simply required to dredge this material with an environmental "bucket" until there was no more material to dredge. DPFUF ¶ 40; Def. App. 72-73. For the material that was suitable for placement in the HARS and rock, the contractor also performed monthly progress payment surveys. DPFUF ¶ 41; Def. App. 68-69. In addition, the contractor was required to perform a pre-final acceptance survey to advise the Corps that the contractor believed that the area was ready for final acceptance. DPFUF ¶ 41; Def. App. 130. The Corps would then perform a final acceptance survey to determine whether the work had been

Though not especially relevant to the pending motions, for informational purposes, the HARS is an area where "cleaner" sediments dredged from the harbor are used to "cap" older materials that have the potential to cause environmentally adverse effects. Def. App. 163. If rock met certain criteria, it would be placed in a reef. Def. App. 162. -7-

7

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 16 of 54

dredged to the contractually required depth. Id. After the work had been accepted, the Corps would either perform or produce another survey to determine the final volume that had been dredged for payment purposes.8 DPFUF ¶ 41; Def. App. 68-69. D. The Specifications for KVK 8

The specifications for KVK 8 provided that the awardee would be required to dredge the contractually defined area to a depth of 47 feet below mean low water. DPFUF ¶ 31; Def. App. 14; 71; 74. The specifications further provided that: If during the dredging or upon completion of the post-dredging surveys and soundings, materials are found above the required depth of 47 feet, below MLW [mean low water], these materials shall be removed immediately at the Contractor's expense. DPFUF ¶ 33; Def. App. 71. However, because of inaccuracies in the dredging process, the specifications provided that the awardee would be compensated at the contract price for "allowable overdepth," defined as material removed up to 1.5 feet beyond the contractually required depth of 47 feet. DPFUF ¶ 34; Def. App. 74. Any material removed more than 1.5 feet beyond the contractually required depth was the responsibility of the contractor, and would not be paid for by the Corps. DPFUF ¶ 33; Def. App. 71. Paragraph 1.15 of the Section 0800 of the specifications for KVK 8, entitled "Final Examination and Acceptance," provided in relevant part: As soon as practicable after the completion of an entire acceptance area a final examination of the work will be conducted by the Contracting Officer at the cost and expense of the Government by acoustic sweep survey system. Should any
8

As previously discussed, in some cases, the same multibeam survey dataset that is used to produce the final acceptance survey can also be used to produce the final payment survey. However, this only occurs when an area is accepted the first time that it is submitted for a final acceptance survey. DPFUF ¶ 38. -8-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 17 of 54

shoals or lumps or other lack of contract depth be disclosed by this examination the Contractor will be required to remove same. The Contractor or his authorized representative will be notified when soundings or sweepings are to be made and will be permitted to accompany the survey party. **** The Contractor shall perform pre-final hydrographic sweep surveys of an entire acceptance area to verify the area is satisfactorily completed prior to final examination by the Government. The pre-final surveys shall be performed using a multitrack or multibeam survey system to insure 100% coverage of the entire acceptance area. The proposed method for performing these surveys and all equipment and programs shall be submitted for approval. The Contractor's hydrographic surveys shall meet or·exceed the survey standards listed in EC 1130-2-210 HYDROGRAPHIC SURVEYING, 1 October 1998 for Class I surveys. DPFUF ¶ 44; Def. App. 130. However, the specifications did not state how the Corps would produce the final surveys that it would use to determine acceptance. The "EC 1130-2-210" referenced in Paragraph 1.15 of the solicitation is an engineering circular issued by the Corps. Paragraph A-2 of Appendix A of EC 1130-2-210, entitled "Revised Survey Classifications," provides in relevant part: Hard Bottom Material and/or New Work. This category of dredge measurement, payment, and acceptance surveys includes dredging of newly authorized projects containing hard bottom material, such as rock or compacted material, or maintenance projects containing hard bottom material. . . . Mechanical or acoustic sweep methods must be employed to insure 100% bottom coverage in order to detect small objects remaining above the required dredging prism. The most precise positioning and depth measurement standards and techniques must be employed for this class of project. In actuality, only a small number of Corps projects fall under this category - for example, projects like Kill Van Kull, NJ and St. Mary's River, MI. DPFUF ¶ 45; Def. App. 7. E. The Award And Performance of KVK 8

Prior to KVK 8, Cashman had not been awarded any of the KVK Phase II contracts.

-9-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 18 of 54

DPFUF ¶ 28. However, Cashman had submitted bids for several of the contracts, and had been the apparent low bidder for KVK contract for Area 5, but had requested and was granted permission to withdraw its bid due to a bid error. DPFUF ¶ 28; Def. App. 15-38. On March 23, 2003, Cashman submitted a bid for the KVK 8 contract. DPFUF ¶ 26; Pl. App. 1-3. Prior to submitting its bid, Cashman did not make inquiry regarding the method that the Corps would use to produce acceptance surveys, although Cashman knew that there were different ways to produce multibeam surveys. DPFUF ¶ 26; Def. App. 10-12. Bruce Wood, Cashman's Vice President and the Project Director for the KVK 8 contract, testified that at the time that he prepared Cashman's bid for the KVK 8 contract, he assumed that the Corps would process multibeam acceptance surveys using the average method "[b]ased upon the plans and specs . . . ." DPFUF ¶ 27; Def. App. 155.. However, Alex Dick, Cashman's Dredging Project Manager, James Galli, Cashman's Project Manager, Dan Gaudet, one of Cashman's surveyors, and Paul Poirier, Cashman's Quality Control Manager, all testified that they had no opinion regarding the method that the Corps would use to produce acceptance surveys data at the time they began work on the contract. DPFUF ¶¶ 58-61; Def. App. 172-80. Either at the time of bid or as work progressed, Cashman's employees decided that the Corps would produce final acceptance surveys using the average depth. DPFUF ¶ 64. Therefore, Cashman produced its pre-final acceptance surveys using the average depth. DPFUF ¶ 64. However, Cashman produced surveys for its own internal use using the minimum depth, because Cashman found it useful in determining how deep to set the digging system on the dredge, and to compare the difference between the average and minimum depth survey products. DPFUF ¶ 65; Def. App. 89-91. -10-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 19 of 54

The KVK 8 contract was divided into a number of sub-areas for acceptance purposes. Answer ¶ 6. As work progressed, on numerous occasions, the Corps' final acceptance surveys showed high spots above the contractually required depth in sub-areas that Cashman's pre-final acceptance surveys indicated had been dredged to grade. DPFUF ¶ 75; Def. App. 132-48. As Cashman continued to be unable to achieve the contractually required depth based upon the Corp's acceptance surveys, Cashman began an internal investigation as to why this was occurring. DPFUF ¶ 78; Def. App. 95-96. As a result of this investigation, Cashman determined that surveys produced using the minimum depth would be more likely to show high spots above the contractually required depth than surveys produced using the average depth method. Id. Mr. Galli testified that he verbally asked Ronald Conetta, the Administrative Contracting Officer, how the Corps was producing its acceptance surveys. DPFUF ¶ 83; Def. App. 92; 192. Mr. Conetta had no experience with dredging prior to the KVK Phase II contracts, no knowledge of which survey products were available for use and in use by the Corps' Survey Section to produce final acceptance surveys, and did not even know that there were multiple ways to produce surveys from multibeam survey data. DPFUF ¶ 84; Def. App. 107-113; 189-92. Mr. Galli testified that Mr. Conetta stated that he did not know, but advised Mr. Galli to write a letter seeking formal direction on the issue "many times." DPFUF ¶ 85; Def. App. 92. On August 31, 2004, Mr. Galli finally wrote a letter seeking direction. DPFUF ¶ 86; Def. App. 114.. The letter stated that Mr. Galli had been verbally informed on August 31, 2004 that the Corps produced acceptance surveys using the minimum depth, and requested confirmation of the acceptance standard that the Corps was using. Id. The Corps responded by letter on October 1, 2004, stating that the Corps produced acceptance surveys using the minimum -11-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 20 of 54

depth. DPFUF ¶ 87; Pl. App. 51-53. Until receiving the letter, Cashman continued to produce pre-final acceptance surveys using the average depth. DPFUF ¶ 88; Def. App. 197-200. After the October 1, 2004 letter, Cashman began to produce its pre-final acceptance surveys using the minimum depth. DPFUF ¶ 89; Def. App. 97-98. However, the Corps' acceptance surveys continued to find shoals on many areas of the project that Cashman believed had been dredged to the contractually required depth. DPFUF ¶ 89; Def. App. 143-48; 195-96. Cashman completed work on KVK 8 in November 2004. DPFUF ¶ 91; Def. App. 9; Pl. App. 3. On July 22, 2005, Cashman submitted a certified claim under the Contract Disputes Act, requesting $6,538,769 in damages, consisting of $4,430,561 in damages for "Extra Effort to Remove HARS material," and $2,108,208 in damages for "Days Spent Removing Shoaling." DPFUF ¶ 92; Def. App. 213. The Contracting Officer issued a final decision denying Cashman's claim on October 26, 2005. DPFUF ¶ 93; Def. App. 216-23. Cashman filed this action on February 10, 2006. See Compl. STATEMENT OF FACTS For our statement of facts, we respectfully refer the Court to the accompanying Defendant's Proposed Findings of Uncontroverted Facts, and Defendant's Responses to Plaintiff's Proposed Findings of Uncontrovered Facts. ARGUMENT I. Standard for Summary Judgment Summary judgment is proper if no genuine question of material fact exists. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255 (1986); Celotex Corp v. United States, 477 U.S. 317, 322 (1986). A fact qualifies as "material" if it would affect the outcome of the case. Anderson, 477 -12-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 21 of 54

U.S. at 248. The burden of showing the absence of a genuine question of material fact rests with the movant, and the Court must view all evidence in the light most favorable to the non-movant, resolving all doubts in that party's favor. O'Connor v. United States, 308 F.3d 1233 (Fed. Cir. 2002). After the moving party has met its burden, the non-movant "must proffer countering evidence sufficient to create a genuine issue of factual dispute." Sweats Fashions, Inc. v. Pannill Knitting Co., 833 F.2d 1560, 1562 (Fed. Cir. 1987). The non-movant's burden is to set forth specific facts that generate issues for trial. This burden "is not met by reliance on its pleadings alone, or by conclusory allegations and generalizations." Bromley Contracting Co. v. United States, 15 Cl. Ct. 100, 105 (1988). The non-movant must present sufficient evidence of a dispute as to "material fact such that the trier of fact could reasonably find in favor of the non-movant." Id. at 105. Contract interpretation is a question of law that is particularly well suited for summary judgment. PDR , Inc. v. United States, 78 Fed. Cl. 201, 204 (2007); Travelers Cas. & Sur. Co. of Am. v. United States, 75 Fed. Cl. 696, 703 (2007). Whether a contract provision is ambiguous is a question of law, and whether an ambiguity is patent or latent is likewise a question of law. NVT Techs., Inc. v. United States, 370 F.3d 1153, 1156 (Fed. Cir. 2004). However, the interpretation of "language, conduct and parties' intent . . . may sometimes involve questions of material fact and not present a pure question of law." PDR, Inc., 78 Fed. Cl. at 204 (citing Beta Systems, Inc. v. United States, 838 F.2d 1179, 1183 (Fed. Cir. 1988)).

-13-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 22 of 54

II.

The Corps Properly Required Cashman To Meet the Contract Objective, And Cashman Is Not Entitled To Additional Compensation For Doing So Cashman argues that because the Corps used a minimum depth survey product for its

final acceptance surveys, there was a "change to the contract entitling Cashman to an equitable adjustment." Pl. Memo. at 21. Cashman's numerous arguments regarding the survey product that the Corps would use for final acceptance surveys ignores the fact that the Corps did nothing but require Cashman to meet the contract objective of dredging the contractually defined area to a depth of 47 feet below mean low water. See Pl. Memo at 7-8; 11-12; 15; 19. Essentially, Cashman is arguing that it is entitled to additional compensation for meeting the contract objective, and that the Corps should not have required Cashman to do so. Paragraph 5.1.1. of Section 2900 of the KVK 8 contract provided that "the required dredging depth as shown on the drawings is 47 feet below [mean low water]." Def. App. 74. The contract also provided that: If during the dredging or upon completion of the post-dredging surveys and soundings, materials are found above the required dredging depth of 47 ft below [mean low water], these materials shall be removed immediately at the contractor's expense. Def. App. 71. The provisions addressing the required depth were not design specifications, setting forth in precise detail the materials to be employed and the manner in which the work is to be performed. See Blake Constr. Co. v. United States, 987 F.2d 743, 745 (Fed. Cir. 1993); Conner Bros. Constr. Co. v. United States, 65 Fed. Cl. 657, 685 (2005). For example, the specifications did not require Cashman to use a particular type of dredging equipment to achieve the contractually required depth. See Def. App. 73; 76. Similarly, the contract did not direct Cashman how to set the digging system on the dredge to achieve the contractually required depth -14-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 23 of 54

- the decision was Cashman's. Def. App. 157-58. Instead, the specification was a performance specification, setting forth an objective or standard to be achieved, and expecting Cashman to exercise its ingenuity in achieving that objective or standard of performance. See P.R. Burke Corp. v. United States, 277 F.3d 1346, 1357 (Fed. Cir. 2002); see also Stuyvesant Dredging Co. v. United States, 834 F.2d 1576, 1582 (Fed. Cir. 1987) ("Technical provision 4-1 did not instruct Stuyvesant how it should perform the dredging of the channel. It merely stated the result to be achieved, namely, that the channel was to be dredged to its acceptable prism."). Where, as here, the contract states the performance requirements, the contractor is obligated to meet them. See Interwest Constr. v. Brown, 29 F.3d 611, 615 (Fed. Cir. 1994). Cashman argues that the Corps should have used average depth survey products to accept Cashman's work. Pl. Memo. at 6, 15-16. However, if the Corps had used average depth survey products, it would necessarily not have required Cashman to dredge the entire contract area to the contractually required depth of 47 feet. By Cashman's own description, the average depth survey product is produced by taking data points within a three foot by three foot bin, "averag[ing] all of the data points within a bin, and if the average is minus forty-seven feet or deeper, the bin is determined to be dredged to the required grade." Pl. Memo. at 5. However, the fact that the average depth of the bin is 47 feet means that there would be points higher than 47 feet, and therefore, not dredged to the contractually required depth. Def. App. 52; ("The average depth over the series can overly smooth the data . . . ."); 164. According to Cashman, therefore, it should have been permitted to achieve less than what the contract required. Prior to award, Cashman did not contend that the requirement to dredge to a depth of 47 -15-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 24 of 54

feet was impossible. Def. App. 156. Nor can Cashman do so now, as it ultimately completed the contract and achieved the required depth. Although Cashman could not dredge to a neat line of 47 feet, the contract provided that Cashman would receive compensation for materials removed up to one and one-half feet below the contractually required depth, to ensure that it would meet the requirement to dredge to a depth of at least 47 feet. Def. App. 74. In fact, when Cashman prepared its bid, Cashman assumed that it would need to perfom dredging even beyond the paid overdepth to meet the required depth of 47 feet. Def. App. 161. Despite this, Cashman now contends that it was a change to Cashman's contract to require Cashman to meet the contract objective. Cashman's pre-bid expectation conformed with the contract's clearly specified provision that the Corps would direct Cashman return to sub-areas with high spots shallower than 47 feet at Cashman's expense, and achieve the contractually required depth. Def. App. 71. Cashman contends that the Corps should be required to compensate Cashman for the cost of removing high spots above the contract depth. Pl. Memo. at 23. However, according to the plain language of the KVK 8 contract, Cashman is not entitled to additional compensation for this work. III. Failure to Comply With Corps Engineering Manual Requiring Information To Be Included In Dredging Contract Specification Cannot Form The Basis For Cashman's Contract Disputes Act Claim Cashman contends that it is entitled to recover damages because the contract did not specify the survey product for the Corps' final acceptance surveys, as required by "the Corps mandatory internal guidance for the preparation of dredging specifications." Pl. Memo. at 12. Cashman has identified "the legal effect of the Defendant's failure to place information in the contract specifications that it was required to insert by mandatory internal guidance . . . ." as a -16-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 25 of 54

relevant legal issue to be determined by the Court. See Pl. Memo. at 9. However, any failure by the Corps to comply with its own "internal guidance" cannot form the basis for Cashman's Contract Disputes Act claim. Cashman notes that paragraph 11-4(g) of the Corps' Engineering and Design Manual ("EM") 1110-2-1003 (1 January 2002) applicable at the time of Cashman's contract, provided that: Measurement and payment provisions in dredging contract specifications shall clearly stipulate the type of survey system, acoustic frequency, navigation guidance system and software, data acquisition parameters (horizontal and vertical control, density, etc.), data processing and binning techniques, and mathematical volume computational method/software that will be employed by the government. Plaintiff's Appendix ("Pl. App.") 21. Cashman then argues that the specifications for the KVK 8 contract did not clearly state the binning techniques that the Corps would use to produce acceptance surveys, and therefore, the Corps violated its internal policy, and is liable to Cashman. See Pl. Memo at 10-14. Strangely, at the same time, Cashman argues that EM 11102-1003 was "not part of the contract and it was not disclosed to [Cashman] prior to award of the contract."9 Pl. Memo. at 4. First, "internal guidance" of the Corps that is "not part of the contract" does not confer legal rights upon Cashman. See Manson Constr. Co. v. United States, 79 Fed. Cl. 16, 19 (2007).

Although Cashman continuously refers to EM 1110-2-1003 as the Corps' "internal guidance," it was a publicly available document, and was referenced in EC 1130-2-210, which the KVK 8 contract stated set forth standards that the contractor should "meet or exceed" for its hydrographic surveys, as a manual containing "[p]rocedural guidance and accuracy standards for performing hydrographic surveys." See Pl. Memo at 4; Pl. Memo at 6 fn. 2; Pl. Memo at 9; Plaintiff's Proposed Finding of Uncontrovered Fact No. 62, see Def. App. Def. App. 128; 130; see also http://web.archive.org/web/19980529092937/www.usace.army.mil/inet/usace-docs /eng-manuals/em1110-2-1003/toc.htm. -17-

9

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 26 of 54

A Corps manual requiring certain information to be included in dredging contract specifications that was not part of or incorporated into Cashman's contract imposes no legal obligation upon the Corps that Cashman can rely upon in its pursuit of damages in its claim under the contract. See St. Christopher Assocs., L.P. v. United States, Fed. Cir. No. 2007-5069 at 10-14, 2008 U.S. App. LEXIS 324 at *19-20 (Jan. 9, 2008); St. Christopher Assocs., L.P. v. United States, 75 Fed. Cl. 1, 10-11 (2006); Reynolds Assocs. v. United States, 31 Fed. Cl. 335, 339 (1994). Second, although EM 1110-2-1003 indicated that the information identified in paragraph 11-4(g) "shall" be included in dredging contract specifications, there is no evidence that the Corps intended to promulgate EM 1110-2-1003 into a regulation providing a cause of action for contractors.10 If the Corps had intended to do so, it would have codified EM 1110-2-1003 in the Code of Federal Regulations. In fact, the stated purpose of EM 1110-2-1003 is to "provide technical guidance for performing hydrographic surveys," not to provide contractors with legal rights. Def. App. 169. Third, there is no indication that paragraph 11-4(g) was included in EM 1110-2-1003 to protect Cashman, or for Cashman's benefit. Indeed, if EM 1110-2-1003 were "internal guidance" for the Corps that was "not disclosed to [Cashman] prior to award of the contract," it would indicate that the provision was included to protect the Corps against claims by contractors, not to protect the legal rights of contractors. See Pl. Memo. at 4. "It is clearly established that when rules and regulations are promulgated for the benefit of the government and no one else,

Cashman presents several statements about concerns or beliefs allegedly possessed by the Office of the Chief of Engineers had. See Pl. Memo. at 10-11. Cashman has not cited evidence in support of those statements, or included evidence in the appendix to support those statements. -18-

10

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 27 of 54

the other party to a contract cannot complain if such regulations are not complied with." C&L Constr. Co. v. United States, 6 Cl. Ct. 791 (1984), aff'd, C&L Constr. Co. v. United States, 790 F.2d 93 (1986) (table). Therefore, even if EM 1110-2-1003 could be given the effect of a regulation, which it cannot, Cashman could not bring suit against the Government based upon a failure to comply with paragraph 11-4 of EM 1110-2-1003. See Freightliner Corp. v. Caldera, 225 F.3d 1361, 1365 (Fed. Cir. 2000) ("In order for a private contractor to bring suit against the Government for violation of a regulation, that regulation must exist for the benefit of the private contractor."). Furthermore, Cashman incorrectly contends that in Redland Genstar, Inc. v. United States, 39 Fed. Cl. 220, 234 (1997), this Court has made a determination regarding the "duty of the Corps to follow the requirements in its engineer manuals." See Pl. Memo. at 13. Redland Genstar was a pre-award bid protest, where the relevant inquiry was whether the Corps' decision to depart from engineering guidance relating to the requirements of a solicitation in a manner that potentially violated the Competition in Contracting Act lacked a rational basis. See 39 Fed. Cl. at 234. The Court never held that there was an independent cause of action arising from the Corps' lack of compliance with its engineering manuals. Here as well, there is not, and Cashman's arguments are inapposite to the issues to be determined in this litigation. IV. Cashman's Failure To Inquire Regarding A Patent Ambiguity Does Not Render The Corps Liable To Cashman In fact, Cashman's own arguments regarding the Corps' failure to specify the survey product that it would use for final acceptance surveys demonstrates that the Corps is not liable to Cashman. On numerous occasions throughout Cashman's brief, Cashman argues that

-19-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 28 of 54

information regarding the survey product that the Corps would use for final acceptance surveys was essential in determining Cashman's "daily dredging regimen" and how deep Cashman would dredge the contractually defined areas. Pl. Memo. at 8, 19; see also Pl. Memo. at 4, 12-13, 19, 22. Cashman also argues that the Corps did not identify the criteria that it would use to accept Cashman's work. See Pl. Memo. at 22. However, if the solicitation failed to include essential information that Cashman needed to determine how it would perform the work necessary to achieve the contractually defined objective, or what standard the Corps would employ to accept the work, this is by definition a patent ambiguity, giving rise to a duty of inquiry by Cashman prior to submitting its bid. A. Legal Standards

If a contract term does not have a plain meaning, it is ambiguous, and the Court must then determine whether the ambiguity is patent or latent. Alliant Techsystems, Inc. v. United States, 74 Fed. Cl. 566, 577 (2007). A patent ambiguity encompasses "an obvious omission, inconsistency, or discrepancy of significance." Interwest Constr. v. Brown, 29 F.3d 611, 617 (Fed. Cir. 1994); Travelers Cas. & Sur. of Am. v. United States, 74 Fed. Cl. 75, 88 (2006). The relevant question is whether the ambiguity would have been apparent to a reasonable contractor. See Lockheed Martin IR Imaging Syst., Inc. v. West, 108 F.3d 319, 322 (Fed. Cir. 1997). With a patent ambiguity, if the non-drafting party fails to make an appropriate inquiry, the ambiguous provision will be construed against the non-drafting party. P.R. Burke Corp. v. United States, 277 F.3d 1346, 1355 (Fed. Cir. 2002); Metric Constructors v. Nat'l Aeronautics & Space Admin, 169 F.3d 747, 751 (Fed. Cir. 1999). The existence of a patent ambiguity in a Government contract raises a duty of inquiry, regardless of the reasonableness of a contractor's -20-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 29 of 54

interpretation. Triax Pac., Inc. V. West, 130 F.3d 1469, 1474 (Fed. Cir. 1997), Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed. Cir. 1985). This duty of inquiry prevents contractors from taking advantage of ambiguities in contracts by adopting narrow interpretations in their bids, and then, after the award is made, seeking equitable adjustments to perform the additional work that the Government actually wanted. Triax Pac, Inc., 130 F.3d at 1475. The duty to inquire starts at the pre-award phase, at a time when the parties are able to take prophylactic action. M.G. Constr., Inc. v. United States, 67 Fed. Cl. 176, 186-87 (2005); see also Engineered Demolition, Inc. v. United States, 70 Fed. Cl. 580, 591 n. 15 (2006). Even if the contractor raised discrepancies with the contracting officer after commencing performance of the contract, that would be too late. M.G. Constr., Inc., 67 Fed. Cl. at 186-87 B. Cashman Did Not Inquire Regarding A Patent Ambiguity In The Specifications

The specifications for the KVK 8 contract did not explicitly state the survey product that the Corps would use for its final acceptance surveys. Paragraph 1.15 of Section 800 of the KVK 8 contract provided: As soon as practicable after the completion of an entire acceptance area, a final examination of the work will be conducted by the Contracting Officer, at the Court and expense of the Government by acoustic sweep survey system. Should any shoals, lumps, or other lack of contract depth be disclosed by this examination, the Contractor will be required to remove same. Def. App. 130. Cashman notes that the specifications "did not state that the Corps planned to process its survey data in any particular manner." Pl. Memo. at 12. Cashman also contends that it needed this information to determine what its daily dredging regimen for the project would be, how deep it would dredge, and because it established the Corps' standard for determining -21-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 30 of 54

whether Cashman had met the contract objective. See Pl. Memo. at 8, 19; see also Pl. Memo. at 7-8, 23. The omission of information necessary to either determine how Cashman would perform the work under the contract, or the standard for determining that the contract objective had been met, would be an obvious omission of significance, that would be neither hidden nor subtle to a contractor preparing a bid for the contract. See Travelers Cas. & Sur., 74 Fed. Cl. at 93-94; Mega Constr. Co. v. United States, 29 Fed. Cl. 396, 457 (2003). According to Cashman's own brief, if Cashman had known that the Corps would use a minimum depth survey product for its acceptance surveys, Cashman would have "dredg[ed] deeper . . . in order to account for the less forgiving results of a minimum depth acceptance survey." Pl. Memo. at 8. Cashman was aware that there were multiple survey products that could be produced from multibeam survey data prior to submitting its bid for the KVK 8 contract. Def. App. 10-12; Pl. App. 33. Furthermore, EC 1130-2-210, which set forth the standards that the solicitation required the awardee to meet or exceed in its own hydrographic surveys, provided that "procedural guidance and accuracy standards for performing multibeam surveys are contained in EM 1110-2-1003." Def. App. 128. EM 1110-2-1003 discussed multiple survey products that could be produced from multibeam survey data. Def. App. 52. Although Cashman knew that different survey products existed, and although Cashman asserts that it needed to know the survey product that the Corps would use for final acceptance surveys both to determine how it would perform the work under the solicitation, and the standard for acceptance of the work, Cashman did not make inquiry regarding the survey product that the Corps would use for final acceptance surveys prior to submitting its bid for the KVK 8 contract. -22-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 31 of 54

Def. App. 10-12; Pl. App. 33. As Mr. Hawkins, the Corps' Project Manager for the Harbor Deepening Project testified, it was unclear " . . . how the contractor bid the job if he had no clear understanding of how he was going to do it." Def. App. 246. Cashman cannot simultaneously argue that information on the survey product for final acceptance surveys was essential to its performance, and simultaneously argue that it did not notice that the information was not included in the specifications. See Pl. Memo. at 4. Because Cashman did not seek clarification of the contract requirements, it cannot now secure an equitable adjustment arising from the alleged ambiguity. See Interwest Constr. v. Brown, 29 F.3d at 615-16. V. Cashman Did Not Reasonably Interpret The Contract To Provide That The Corps Would Produce Final Acceptance Surveys Using The Average Depth However, even if the Court were to determine that the specifications were latently ambiguous in failing to specify the survey product that Cashman would use for final acceptance surveys, Cashman's interpretation that the Corps would produce final acceptance surveys using the average depth was unreasonable, precluding Cashman from recovery. A. Legal Standards

Where an ambiguity is not sufficiently glaring to trigger the patent ambiguity exception, it is deemed latent and the general rule of contra proferentem applies. HPI/GSA-3C, LLC v. Perry, 364 F.3d 1327, 1334 (Fed. Cir. 2004). The rule of contra proferentem requires that ambiguous or unclear terms that are subject to more than one reasonable interpretation be construed against the party who drafted the document. United States v. Turner Constr. Co., 819 F.2d 283, 286 (Fed. Cir. 1987). However, before a court may enforce the general rule of contra proferentem against the drafter of a latent ambiguity, the contractor's interpretation of that ambiguity must be

-23-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 32 of 54

reasonable. HPI/GSA-3C, LLC, 364 F.3d at 1334; see also Turner Constr. Co. v. United States, 367 F.3d 1319, 1321 (Fed. Cir. 2004). In addition, the contractor must have actually construed the specifications in accordance with one of the meanings to which the language was susceptible. HPI/GSA-3C, LLC, 364 F.3d at 1334 (citing W. Contracting Corp. v. United States, 144 Ct. Cl. 318, 326 (1958)). Where a contractor seeks recovery based on his interpretation of an ambiguous contract, he must show that he relied on this interpretation in submitting his bid. Fruin-Colnon Corp. v. United States, 912 F.2d 1426, 1430 (Fed. Cir. 1990). Such reliance must be shown at the time that the contractor entered into the contract. See Maintenance Engineers, Inc. v. United States, 21 Cl. Ct. 553, 562 (1990). B. Cashman's Interpretation That The Corps Would Produce Final Acceptance Surveys Using the Average Depth Was Unreasonable

As previously discussed, Paragraph 1.15 of Section 0800 of the KVK 8 contract provided that "[t]he Contractor's hydrographic surveys shall meet or exceed the survey standards listed in EC 1130-2-210, HYDROGRAPHIC SURVEYING, 1 October 1998 for Class I surveys." Def. App. 130. Based upon EC 1130-2-210, Cashman could not reasonably have believed that the Corps would produce final acceptance surveys using the average depth, or that it would be advisable for Cashman to produce its pre-final acceptance surveys using the average depth. Appendix A of EC 1130-2-210, Paragraph A-2(a)(1), provided: Hard Bottom Material and/or New Work. This category of dredge measurement, payment, and acceptance surveys includes dredging of newly authorized projects containing hard bottom material, such as rock or compacted material, or maintenance projects containing hard bottom material. All newly authorized projects are not necessarily in this category. This category may also include projects where low under-keel clearances are anticipated over potentially -24-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 33 of 54

hazardous bottom conditions. Mechanical or acoustic sweep methods must be employed to insure 100% bottom coverage in order to detect small objects remaining above the required dredging prism. The most precise positioning and depth measurement standards and techniques must be employed for this class of project. In actuality, only a small number of Corps projects fall under this category - for example, projects like Kill Van Kull, NJ and St. Mary's River, MI. Def. App. 7, see also Def. App. 168 The KVK 8 project contained hard bottom material, and was new work dredging. See Pl. Memo. at 2; See Pl. App. 8, Def. App. 4; 77-78. In fact, the Kill Van Kull projects were specifically identified as a type of Corps project that would be governed by Paragraph A-2(a)(1). Def. App. 7 EC 1130-2-210, Paragraph A-2(a)(1) provides that for hard bottom or new work dredging, such as the KVK projects, the most precise positioning and depth measurement standards must be employed. Def. App. 7. Average depth survey products are certainly not the "most precise positioning and depth measurement" standard, because they "average[] all of the data points within a bin, and if the average is minus forty-seven feet or deeper, the bin is determined to be dredged to the required grade." See Pl. Memo. at 5. This would "smooth out" or hide objects above the contractually required depth, making it difficult to detect them. Def. App. 52; 164. Paragraph A-2(a)(1) also provides that, "[m]echanical or acoustic sweep methods must be employed to insure 100% bottom coverage in order to detect small objects remaining above the required dredging prism." Def. App. 7. As Cashman itself notes in its proposed findings of fact, "[t]he average method is less likely to result in a requirement to re-dredge because the average of all the data points in a bin may be below grade, even though not all of the points in the bin are

-25-

Case 1:06-cv-00101-FMA

Document 30

Filed 01/31/2008

Page 34 of 54

below grade." Plaintiff's Proposed Finding of Uncontroverted Fact ("PFOUF") No. 39. Therefore, the average method of processing multibeam acceptance surveys is less likely to "detect small objects remaining above the required dredging prism." Def. App. 7. For these reasons, any assumption that the Corps would produce final acceptance surveys using the average depth was unreasonable. C. Evidence In the Record Does Not Support The Argument That Cashman Assumed That Final Acceptance Surveys Would Be Produced Using The Average Depth Based Upon The Nature of Dredging Equipment, And Such An Assumption Would Be Unreasonable

In Cashman's memorandum in support of its motion for summary judgment, Cashman's counsel presents an elaborate explanation of why, in light of the nature of dredging equipment, it was reasonable for Cashman to assume that the Corps would produce acceptance surveys using the average depth. See Pl. Memo. at 15-16. As defendant understands Cashman's argument, Cashman contends that because the bucket of a backhoe dredge is larger than a three foot by three foot cell for multibeam surveying, Cashman assumed that the depth wo