Free Proposed Findings of Uncontroverted Fact - District Court of Federal Claims - federal


File Size: 51.8 kB
Pages: 12
Date: November 10, 2006
File Format: PDF
State: federal
Category: District
Author: unknown
Word Count: 2,242 Words, 14,795 Characters
Page Size: Letter (8 1/2" x 11")
URL

https://www.findforms.com/pdf_files/cofc/21047/16.pdf

Download Proposed Findings of Uncontroverted Fact - District Court of Federal Claims ( 51.8 kB)


Preview Proposed Findings of Uncontroverted Fact - District Court of Federal Claims
Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 1 of 12

IN THE UNITED STATES COURT OF FEDERAL CLAIMS PCL CONSTRUCTION SERVICES, INC., Plaintiff, v. THE UNITED STATES, Defendant. ) ) ) ) ) ) ) ) )

No. 06-144C (Judge Horn)

DEFENDANT'S PROPOSED FINDINGS OF UNCONTROVERTED FACT IN SUPPORT OF ITS MOTION FOR SUMMARY JUDGMENT Defendant, the United States, respectfully submits the following proposed findings of uncontroverted fact in support of our motion for summary judgment. Our proposed facts are

supported by five documents, which are already before the Court; 1) PCL's first amended complaint it its breach of contract case ("breach complaint"), 2) the transcript from the breach trial, 3) PCL's post trial brief from the breach trial, 4) the Court's trial decision following the breach trial, 5) PCL's complaint in this case ("delay complaint").1 1. In the mid-1990s, plaintiff PCL Construction Services,

Inc., ("PCL") partially performed a construction contract for the United States Bureau of Reclamation ("Reclamation") whereby PCL constructed the Hoover Dam visitor center and parking structure. PCL Construction Services, Inc. v. United States, 47 Fed. Cl.

Although the documents relied upon in our motion are already before the Court, we propose to submit a "joint appendix" with PCL to collect all documents relied upon by both parties in our briefs. -1-

1

Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 2 of 12

745, 753-82 (2000)(hereinafter "PCL"). 2. Near the conclusion of the project, PCL refused to PCL's

perform further and was duly terminated for default.

challenge to the default termination was rejected by this Court, and PCL did not appeal that aspect of the Court's decision. at 811. 3. After its partial performance, PCL claimed that it PCL

believed that Reclamation imposed excessive contract changes upon PCL (PCL First Amended Complaint in case no. 95-666C ("breach complaint") ¶¶ 144, 154-155; PCL Complaint in case no. 06-144C ("delay complaint") ¶¶ 71), that the contract plans and specifications were "defective" (breach complaint ¶¶ 8, 117, 121, 122, 124, 132-136, 139-140, 143, 147-148, 212, 218, 288; delay complaint ¶¶ 43-44, 46, 48, 52) which disrupted and delayed PCL's contract performance (breach complaint ¶¶ 132-134, 290, 292-296; delay complaint ¶¶ 51-52, 57-58, 68), and that Reclamation otherwise "maladministered" PCL's contract. Breach complaint ¶¶

149-164, 170, 173, 288-296; delay complaint ¶¶ 48-58, 67-68, 71, 79-80. 4. PCL depicted the alleged "perturbation" it experienced

with RFI's, "CRXs" (instances where PCL believed it was entitled to extra compensation for contract changes), and other contemporaneous written correspondence but, notably, did not provide a single complete contractually-required time-impact

-2-

Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 3 of 12

evaluation for any of its alleged construction difficulties. at 745, 759, 761-764, 766, 768, 771, 773-774, 779, 812; breach

PCL

complaint ¶¶ 144, 150-153; delay complaint ¶¶ 46, 58, 60-68, 7280. 5. Some of the individual aspects of the project of which

PCL complained were delays to the excavation of the back slope at the rear of the parking structure ("back slope")(breach complaint ¶ 128; delay complaint ¶¶ 33-37), problems and delays constructing the ring beam in the visitor center ("ring beam")(breach complaint ¶ 128; delay complaint ¶¶ 33-37), and extra costs and delays caused by the installation of a drag tie in the foundation of the parking structure ("drag tie") (breach complaint ¶ 128), among others (delay complaint ¶¶ 33-37). 6. PCL also periodically presented change order proposals

in an attempt to negotiate payments for its individual CRXs. Delay complaint ¶¶ 72-29. 7. In 1994, with construction progressing towards

substantial completion, PCL presented (but did not certify) a request for equitable adjustment ("REA") that sought approximately $23 million, based upon the entirety of PCL's construction delays and cost-overruns through July of 1993 ­ virtually all of which were blamed upon Reclamation. PCL at 803;

breach complaint ¶¶ 166-171; delay complaint ¶¶ 14, 86-90. 8. PCL's REA purported to analyze the delays and

disruptions caused by Reclamation and assigned most, but not all, -3-

Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 4 of 12

of the responsibility for PCL's delayed performance and cost overruns to Reclamation. 9. PCL at 780, 803.

PCL's perturbations at the back slope, ring beam, drag

tie, and as a result of PCL's CRXs were featured prominently in PCL's REA. 10. Delay complaint ¶ 88.

Reclamation found no Government liability under PCL's

REA based, in part, upon PCL's failure to provide valid contractually-required time-impact evaluations for its claimed delays and disruptions, but Reclamation indicated a willingness to consider further analysis by PCL in which Reclamation even volunteered to participate. 11. PCL at 780; delay complaint ¶ 89.

Instead of certifying or further refining its REA,

however, PCL chose to abandon the REA and instead submitted a certified claim based upon the exact same transactional facts as its REA (including the back slope, ring beam, drag tie, and contract changes). Breach complaint ¶¶ 128, 166-169; delay

complaint ¶¶ 33-37, 86-90. 12. Without any indication that PCL wished to "split" its

REA into two or more claims and to move forward with one claim while reserving another, PCL's certified claim simply characterized the same transactional factual events depicted in its REA as a "breach of contract," "fraud in the inducement," "hindrance", "cardinal change," and/or "defective specifications." Breach complaint.

-4-

Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 5 of 12

13.

When Reclamation denied PCL's certified claim, PCL

appealed the denial to this Court by filing the breach complaint that mirrored both the REA and certified claim. The breach

complaint was based upon the same transactional facts as both and specifically relied, again, upon perturbations at the back slope, ring beam, and drag tie, as well as unresolved CRXs and all of the same transactional facts set forth in the REA and certified claim. 14. Breach complaint ¶¶ 5-6, 128, 165-169. Again, PCL's breach complaint contained no indication

whatsoever that PCL wished, or expressly reserved the right, to split its multiple legal theories away from other separate, unlitigated, claims based upon the same transactional facts. PCL's

breach complaint simply repackaged the same transactional facts (delays and cost overruns allegedly caused by Reclamation's contract and maladministration thereof) into a series of legal theories based upon breach of contract, misrepresentation, superior knowledge, breach of implied warranty, cardinal change, and hindrance of performance.2 15. Breach complaint.

PCL's breach complaint did not assert that PCL's delays

and disruptions entitled PCL to relief under the changes clause

PCL presented the same legal theories in its complaint as in its certified claim except it added counts for "illegally funded contract," and "illegal contract based upon violation of FAR Part 16". Breach complaint p 10. -5-

2

Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 6 of 12

(or any other clause) of the contract. for Relief. 16.

Breach complaint, Prayer

Although for ease of reference, PCL, the Court, and

Government counsel periodically referred to PCL's case as a "breach of contract" or "total breach" claim, PCL actually litigated no fewer than six distinct legal theories ­ none of which are identical to each other. 17. Breach complaint.

PCL's "fraud in the inducement" theory suggested that

the original contract solicitation was so "severely defective" that PCL was duped into signing the contract. ¶¶ 210-233. 18. PCL's "cardinal change" theory, on the other hand, was Breach complaint

based entirely upon events that occurred during performance -that contract changes and the need for numerous RFIs and CRXs constituted a fundamental change to the nature and the scope of the contract. 19. Breach complaint ¶¶ 298-303.

The only identical aspect of PCL's different legal

theories was a demand for total cost damages of $31,040,071. Breach complaint, Prayer for Relief. 20. The "total" or "global" nature of PCL's breach claims

more accurately describes the amount of damages sought by PCL, and the method of its calculation, rather than a single "global" construction event or time period covered by PCL's breach claim and complaint. PCL at 800.

-6-

Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 7 of 12

21.

The litigation of PCL's case was lengthy and expensive.

PCL at 782. 22. It included a summary judgment proceeding whereby PCL's

"illegal funding" claims were eliminated (PCL Construction Services. Inc. v. United States, 41 Fed. C1. 242 (1998); delay complaint ¶ 19), two rounds of discovery which included depositions of approximately 40 fact witnesses (some deposed twice), analysis of PCL's case by six expert witnesses (four of whom were retained by PCL), separate claims by PCL challenging its termination for default and seeking return of liquidated damages and funds retained by Reclamation, a trial that occupied 51 days in Court over a period of 17 months (Tr. 12780), an unsuccessful multi-episode attempt to mediate a resolution to the case (which included yet another analysis of the project by an expert witness for PCL) (PCL at 782), and a Government counterclaim for defective components of the theater turntable feature of the visitor center that was defectively designed and constructed by PCL. 23. Although litigation of PCL's case provided PCL with the

opportunity for a full and complete adjudication of the transactional factual events depicted in PCL's REA, certified claim, and breach complaint, PCL never attempted to (retroactively) split or expressly reserve any additional claims arising out of the same transactional facts.

-7-

Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 8 of 12

24.

PCL and its experts rejected the suggestion that a

traditional contract-based delay/disruption/changes claim was more appropriate than PCL's many "breach" theories when they testified that a traditional schedule/delay analysis of the project was "impossible." See, e.g., Bennett Tr. 61-62, 698-700;

Eudy Tr. 6351; Fenster Tr. 6477-78; Mizell Tr. 6540, 6719-6721; Kellogg Tr. 7900, 7903-4, 7943-7945, 8062, 8176; Schwartzkopf Tr. 12008. 25. PCL's president testified that PCL's own summary level Bennett Tr. 710; PCL at

schedule delay analysis was "wrong." 802. 26.

Throughout the litigation, the Government urged PCL to

abandon its breach theories in favor of a contract-based claim.3 See, e.g., Tr. 64-65 (opening statements). 27. PCL expressly refused to do so, even when cautioned by

the Court as follows: The Court: Are you saying that your client is absolutely adamant that they will not present a certified claim at this point? Yes, Your Honor. So be it. I think that's foolish, but so be it.

Mr. Fenster: The Court:

Urging PCL to drop its breach claim in favor of a contract-based claim is very different from consenting or acquiescing to PCL splitting its claims into separately-litigated cases. -8-

3

Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 9 of 12

Tr. 13042 28. The trial-level litigation of the perturbations to the

project concluded with this Court's 67-page decision that rejected all of the claims presented in PCL's breach complaint that arose from the transactional facts upon which PCL's REA and certified claim were based. 29. PCL at 812.

PCL's appeal of this Court's trial decision was

rejected, after full briefing and argument, in an unpublished decision of the United States Court of Appeals for the Federal Circuit. 30. Delay complaint ¶ 23. At no time during PCL's partial performance of the

contract, the presentation of PCL's REA, the submission of PCL's certified claim, or the trial and appellate litigation of PCL's case, did PCL seek, or expressly attempt to reserve the right, to split its certified claim into separately submitted or litigated claims arising out of the same transactional facts. 31. In 2005, after retaining new counsel, PCL submitted two

new certified claims to Reclamation that arise out of the same transactional facts (the alleged perturbation of PCL's partial contract performance) that were fully and finally resolved upon the merits in PCL's prior litigation ­ including the back slope, ring beam, drag tie and unresolved CRXs. 8. 32. After denial of PCL's new delay/disruption/CRX claims Delay complaint ¶¶ 6,

by Reclamation upon the basis of res judicata, (delay complaint -9-

Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 10 of 12

¶¶ 7, 9) PCL filed the its delay complaint that seeks to relitigate the same transactional facts ­ that were fully and finally resolved upon the merits in PCL's prior litigation. Delay complaint. 33. PCL's delay complaint asserts five grounds for recovery

that rely upon the same transactional facts as PCL's breach complaint. They are: A type I differing site condition claim, a

type II differing site condition claim, a changes clause claim, a "constructive changes" claim, and a suspension of work claim. Delay complaint ¶¶ 119-176. 34. PCL's delay complaint contains a section entitled

"preservation of claims" that relies only upon contract modifications and correspondence from the construction period that predate PCL's breach complaint. 35. Delay complaint ¶¶ 81-85.

Pages 220-222 of PCL's post-breach-trial brief (arguing

that the release/reservation language in bilateral contract modifications did not bar PCL's breach claim) is almost word-forword with paragraphs 81-85 of PCL's delay complaint. Respectfully submitted, PETER D. KIESLER Assistant Attorney General DAVID M. COHEN Director s/Deborah A. Bynum DEBORAH A. BYNUM Assistant Director s/Brian S. Smith -10-

Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 11 of 12

BRIAN S. SMITH Attorney Commercial Litigation Branch Civil Division Department of Justice Attn: Classification Unit 8th Floor, 1100 L St. NW Washington, D.C. 20530 Tele: (202) 616-0391 Attorneys for Defendant November 10, 2006

-11-

Case 1:06-cv-00144-MBH

Document 16

Filed 11/10/2006

Page 12 of 12

CERTIFICATE OF FILING I certify that on November 10, 2006, the foregoing brief was filed electronically. I understand that notice of this filing

will be sent to all parties by operation of the Court's electronic filing system. the Court's system. s/Brian S. Smith Parties may access this filing through

-12-