Free Proposed Findings of Uncontroverted Fact - District Court of Federal Claims - federal


File Size: 27.6 kB
Pages: 9
Date: March 15, 2007
File Format: PDF
State: federal
Category: District
Author: unknown
Word Count: 2,003 Words, 12,592 Characters
Page Size: Letter (8 1/2" x 11")
URL

https://www.findforms.com/pdf_files/cofc/21061/16.pdf

Download Proposed Findings of Uncontroverted Fact - District Court of Federal Claims ( 27.6 kB)


Preview Proposed Findings of Uncontroverted Fact - District Court of Federal Claims
Case 1:06-cv-00155-MMS

Document 16

Filed 03/15/2007

Page 1 of 9

IN THE UNITED STATES COURT OF FEDERAL CLAIMS S&M MANAGEMENT INCORPORATED, Plaintiff, v. THE UNITED STATES, Defendant. ) ) ) ) ) ) ) ) )

No. 06-155C (Senior Judge Hodges)

DEFENDANT'S PROPOSED FINDINGS OF UNCONTROVERTED FACT Pursuant to Rule 56(h)(1) of the Rules of the United States Court of Federal Claims ("RCFC"), defendant respectfully submits the following proposed findings of uncontroverted fact in connection with defendant's concurrently filed motion for partial summary judgment. 1. The VA awarded the contract at issue, No. V10N3C-067, to S&M on September 29,

1999. Def. App. 353.1 2. The contract obligated S&M to excavate, remove, and replace more than 2000 feet of

underground steam pipes at a VA facility in Castle Point, New York. Def. App. 99-100. 3. S&M was required pursuant to the contract to dig down to the top of vaults housing the

steam pipes, open the vaults, remove asbestos insulation from the vaults, then remove the steam pipes and their hangers, connections, and other appurtenances. Def. App. 99. 4. The contract then called for the installation of various sizes of steam pipe accompanied

by new hangers, connections, and appurtenances. Id. 5. S&M was also required to install two new manholes, eight new manhole covers, and any

steam vault covers found to be defective or damaged upon removal. Id.

"Def. App. ___" refers to the appendix filed with defendant's Motion for Partial Summary Judgment.

1

Case 1:06-cv-00155-MMS

Document 16

Filed 03/15/2007

Page 2 of 9

6.

The contract required S&M to replace any surface materials removed or damaged during

the project. Id. 7. The VA issued S&M a notice to proceed on November 9, 1999, for a contract amount of

$598,000, which later increased to $678,449.89. Def. App. 355. 8. At the close of construction, VA employees met with S&M to inspect the work

completed. Def. App. 357. This inspection resulted in a list of deficiencies. Def. App. 357-360. The VA forwarded this list to S&M and requested that S&M properly complete the project. Id. S&M disputed the validity of a number of the items on the list and refused to complete the work without change requests. Def. App. 361-63. 9. The VA retained a portion of the contract price because S&M declined to complete the

listed items. Def. App. 491. This retention is reflected in S&M's final application for payment, submitted on November 28, 2001, which sought a progress payment of $3,857.37 on a remaining balance of $75,603.99, plus a $6,000 retainage. Id. The VA disapproved S&M's application, and withheld the remaining contract funds pursuant to the contract's retainage clause, which provides that the "Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds." Def. App. 491, 57. 10. The VA has not provided S&M with a specific list of costs associated with the

uncompleted list items. 11. The first item disputed by S&M, the installation of compensators (which absorb pipe

movement caused by expansion and contraction), involved various manholes and a "Building 1."

2

Case 1:06-cv-00155-MMS

Document 16

Filed 03/15/2007

Page 3 of 9

Def. App. 361, 363, 290, 509-10 (Lancto Declaration ¶¶ 6-10). 12. The contract specifications required S&M to construct a "complete underground steam

and condensate distribution system including all components such as piping, insulation, protective enclosures, valves, manholes, expansion devices, steam traps, corrosion protection and accessories." Def. App. 282. As part of this system, the specifications spell out the parameters for the expansion devices, and expansion compensators in particular. Def. App. 29092. 13. The specifications do not provide specific detail regarding the location or quantity of

expansion joints. The contract drawings, however, do provide such detail for the manholes, and the contract provides that "[a]nything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned on both." Def. App. 76. 14. The contract also provides that "[a]ny work at variance with that specified or shown in

the drawings shall not be performed by the contractor until approved in writing by the contracting officer." Def. App. 86. 15. Drawings D-1 and D-2 show expansion joints present in the manholes. Def. App. 505-

06, 509 (Lancto Declaration ¶¶ 7-8). These expansion joints are represented by either rectangles or trapezoids. Def. App. 505-06, 509 (Lancto Declaration ¶ 7). 16. The drawings provide for expansion joints on all the pipes in manholes 18A, 18B, 18C,

18E, 25, and 25B, but S&M did not install joints on all the pipes. Def. App. 359-60, 509 (Lancto Declaration ¶ 8). 17. The compensator in Building 1 was not shown on a drawing, but a compensator in this

3

Case 1:06-cv-00155-MMS

Document 16

Filed 03/15/2007

Page 4 of 9

location was necessary to complete the pipe system properly. Def. App. 509-10 (Lancto Declaration ¶ 9). 18. The VA has "located no documentation in the files that shows that S&M was given

permission--by the contracting officer or anyone else working for the VA--not to install compensators in manholes 18A, 18B, 18C, 18E, 25, and 25B, or in Building 1." Def. App. 510 (Lancto Declaration ¶ 10). 19. S&M damaged a compensator in Manhole 18C during installation, and the VA requested

that S&M replace the unit. Def. App. 384, 510 (Lancto Declaration ¶ 11). 20. S&M gouged the compensator when grinding pipe in a manhole, compromising the

compensator's structural integrity. Def. App. 510 (Lancto Declaration ¶ 11). 21. The submittal sheet for the compensator notes that the "heavy wall housing adds extra

protection to the joint minimizing external damage." Def. App. 527 (Exhibit H to Lancto Declaration). 22. The VA has "located no documentation in the files that shows that S&M was given

permission--by the contracting officer or anyone else working for the VA--not to replace the compensator it damaged in Manhole 18C." Def. App. 510 (Lancto Declaration ¶ 11). 23. The contract provides two separate warranty clauses. First, pursuant to FAR 52.246-21,

the contract states that "the Contractor warrants . . . that work performed under this contract . . . is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor . . ." Def. App. 80. The contract obligates the contractor to "remedy at the Contractor's expense any failure to conform, or any defect." Id. This clause is then repeated in the "general requirements" section of the contract. Def. App. 115-16.

4

Case 1:06-cv-00155-MMS

Document 16

Filed 03/15/2007

Page 5 of 9

24.

The contract also contains a guarantee clause, FAR 852.236-75, which provides that the

"contractor guarantees that when installed all materials and equipment will be free from defects and will remain so for a period of at least one year from the date of acceptance by the Government." Def. App. 87. 25. The contract contains a restoration clause requiring that "[u]pon completion of the

contract, the Contractor shall deliver the work complete and undamaged." Def. App. 111. 26. The drawing for Manhole 25 shows two new steam lines exiting the manhole in the

direction of Manhole 25B. Def. App. 505. 27. Instead of replacing these steam lines in their entirety and connecting to the main trunk

line with a new valve, S&M terminated the new piping outside of the manhole in the trench. Def. App. 383, 510 (Lancto Declaration ¶ 12). 28. As a result of S&M's fabrication of a joint outside the manhole, repairs of the joint may

be impossible without excavation. Def. App. 510 (Lancto Declaration ¶ 12). 29. The contract required that S&M "[c]onnect new work to existing work in a neat and

workmanlike manner." Def. App. 299. 30. The VA has "located no documentation in the files that shows that S&M was given

permission--by the contracting officer or anyone else working for the VA--to install these pipes in this manner." Id. 31. S&M was required by the contract to install two new manholes, manholes 18B and 18E.

Def. App. 288, 506. 32. In an attempt to accomplish this contract requirement, S&M installed two pre-cast

concrete manholes. Def. App. 379-380.

5

Case 1:06-cv-00155-MMS

Document 16

Filed 03/15/2007

Page 6 of 9

33.

The contract required S&M to place a "waterproof membrane between mud slab and

bottom concrete slab, and continue up sides to top of side walls." Def. App. 288. The specifications for this membrane were detailed in a separate section of the specifications. Def. App. 335. 34. The purpose of the membrane is to prevent water from leaking into the manhole and

doing damage to the pipes inside. Def. App. 511 (Lancto Declaration ¶ 15). 35. S&M did not install any waterproof membrane on manholes 18B or 18E. Id.;

Def. App. 383-84. 36. The VA has "located no documentation in the files that shows that S&M was given

permission--by the contracting officer or anyone else working for the VA--not to install waterproofing on these manholes." Id. 37. The tops of the manholes that S&M installed also do not sit flush with the ground. Def.

App. 510-11 (Lancto Declaration ¶¶ 13-14), 529 (Exhibit I to Lancto Declaration). 38. The contract contains no specific requirement that manholes be installed in such a

manner, but common trade practice dictates such an installation. Def. App. 511 (Lancto Declaration ¶ 14). 39. The specifications define the type of insulation required in trenches and manholes.

Def. App. 304. 40. In both locations, "calcium silicate pipe insulation, glass cloth or aluminum jacket" is

required. Id. 41. The specifications draw a distinction between trenches and manholes and "[e]xposed

piping in walk-through tunnels," which must be "insulated with fiberglass pipe insulation, all

6

Case 1:06-cv-00155-MMS

Document 16

Filed 03/15/2007

Page 7 of 9

purpose jacket." Id. 42. The types of insulation "jacket" are defined elsewhere in the specifications. Def. App.

299. Jackets for "Insulation Exposed to Weather" are defined as possessing minimum "0.016inch thick aluminum with locking longitudinal joints." Id. 43. An all-purpose jacket is defined as "White kraft bonded to aluminum foil, fiberglass

reinforced, pressure sensitive adhesive closure." Id. 44. S&M installed an "all-purpose jacket" in the trenches and manholes, not "calcium silicate

pipe insulation, glass cloth or aluminum jacket." Def. App. 511 (Lancto Declaration ¶ 16). 45. The type of insulation that S&M installed is inappropriate for trenches and manholes,

which are potentially exposed to the elements. Id. 46. The VA has "located no documentation in the files that shows that S&M was given

permission--by the contracting officer or anyone else working for the VA--to install the type of insulation it installed in the trenches." Id. 47. The contracting officer's delegation of authority to Michael Shaughnessy provided that

one of Mr. Shaughnessy's duties was "[a]ssuring that changes in work under a contract are not implemented before written authorization or a contract modification is issued by the Contracting Officer." Def. App. 530. 48. The delegation explicitly forbade Mr. Shaughnessy from "[m]aking changes to contract

provisions." Def. App. 531. 49. S&M signed an acknowledgment of this delegation. Def. App. 532.

7

Case 1:06-cv-00155-MMS

Document 16

Filed 03/15/2007

Page 8 of 9

Respectfully submitted, PETER D. KEISLER Assistant Attorney General JEANNE E. DAVIDSON Director s/ Franklin E. White, Jr. FRANKLIN E. WHITE, JR. Assistant Director s/ Sean B. McNamara SEAN B. McNAMARA Trial Attorney Commercial Litigation Branch Civil Division Department of Justice Attn: Classification Unit, 8th Floor 1100 L St., NW Washington, D.C. 20530 Tele: (202) 305-7573 Fax: (202) 514-8624 March 15, 2007 Attorneys for Defendant

8

Case 1:06-cv-00155-MMS

Document 16

Filed 03/15/2007

Page 9 of 9

CERTIFICATE OF FILING I hereby certify that on this 15th day of March, 2007, a copy of the foregoing "DEFENDANT'S PROPOSED FINDINGS OF UNCONTROVERTED FACT" was filed electronically. I understand that notice of this filing will be sent to all parties by operation of the Court's electronic filing system. The parties may access this filing through the Court's system.

s/ Sean B. McNamara