Free Motion to Dismiss - Rule 12(b)(1) - District Court of Federal Claims - federal


File Size: 1,818.7 kB
Pages: 49
Date: February 7, 2008
File Format: PDF
State: federal
Category: District
Author: unknown
Word Count: 10,336 Words, 65,557 Characters
Page Size: Letter (8 1/2" x 11")
URL

https://www.findforms.com/pdf_files/cofc/22103/44-10.pdf

Download Motion to Dismiss - Rule 12(b)(1) - District Court of Federal Claims ( 1,818.7 kB)


Preview Motion to Dismiss - Rule 12(b)(1) - District Court of Federal Claims
Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 1 1 of 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page of 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

MARIE L. FIALA (CA BAR NO. 79676) RUSSELL P. COHEN (CA BAR NO. 213105) INGRID S. LEVERETT (CA BAR NO. 148813) HELLER EHRMAN LLP 333 Bush Street San Francisco, CA 94104-2878 Telephone: (415) 772-6000 Facsimile: (415) 772-6268 [email protected] [email protected] [email protected] Attorneys for Plaintiff PACIFIC GAS & ELECTRIC COMPANY [ADDITIONAL PARTIES AND COUNSEL SHOWN ON SIGNATURE PAGE]

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF CALIFORNIA, SACRAMENTO DIVISION Pacific Gas and Electric Company, Southern California Edison Company, and California Electricity Oversight Board, Plaintiffs, v. Arizona Electric Power Cooperative, Inc.; City of Anaheim; City of Azusa; City of Banning; City of Burbank; City of Glendale; City of Los Angeles; City of Pasadena; City of Riverside; City of Santa Clara; City of Seattle; City of Vernon; Eugene Water and Electric Board; Los Angeles Department of Water and Power; Modesto Irrigation District; Northern California Power Agency; Public Utility District No. 2 of Grant County; Sacramento Municipal Utility District; Salt River Project Agricultural Improvement and Power District; and Turlock Irrigation District, Defendants. COMPLAINT FOR DAMAGES AND/OR RESTITUTION AND DECLARATORY RELIEF AND JURY DEMAND Plaintiffs hereby demand trial by jury of all issues properly triable thereby. Case No. COMPLAINT FOR DAMAGES AND/OR RESTITUTION AND DECLARATORY RELIEF AND JURY DEMAND

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

A1365

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 2 2 of 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page of 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

Plaintiffs Pacific Gas and Electric Company ("PG&E"), Southern California Edison Company ("SCE"), and the California Electricity Oversight Board ("EOB") (collectively, "the California Parties") allege: JURISDICTION 1. This Court has jurisdiction of this action pursuant to 28 U.S.C. § 1331. Plaintiffs'

claims require resolution of a disputed and substantial issue of federal law in that plaintiffs' claims arise out of defendants' sales of electric power in wholesale electricity markets that are within the Federal Energy Regulatory Commission's ("FERC") exclusive regulatory jurisdiction, and plaintiffs are suing to recover for defendants' breaches of their contractual obligations contained in tariffs filed with and regulated by FERC. SUMMARY 2. This is an action for damages and declaratory relief against the following defendants:

Arizona Electric Power Cooperative, Inc.; City of Anaheim; City of Azusa; City of Banning; City of Burbank; City of Glendale; City of Los Angeles; City of Pasadena; City of Riverside; City of Santa Clara; City of Seattle (Seattle City Light Department); City of Vernon; Eugene Water and Electric Board; Los Angeles Department of Water and Power; Modesto Irrigation District; Northern California Power Agency; Public Utility District No. 2 of Grant County; Sacramento Municipal Utility District; Salt River Project Agricultural Improvement and Power District; and Turlock Irrigation District (collectively, "the Governmental Entities"). PG&E and SCE's (the "California IOUs") claims in this action arise out of their wholesale purchases of electric power and ancillary services (hereinafter "electric power") and the Governmental Entities' sales of electric power in the California wholesale electric power markets from May 1, 2000 through June 20, 2001. The California wholesale markets were operated by the California Independent System Operator Corporation ("ISO") and California Power Exchange Corporation ("PX") under tariffs filed with and approved by the FERC. 3. The Governmental Entities' voluntary sales of electric power into the California

wholesale markets pursuant to the ISO and PX tariffs and pursuant to certain written agreements gave rise to binding contractual obligations owed by the defendants to the other market participants,
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 2

A1366

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 3 3 of 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page of 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

including the California IOUs. The California IOUs are direct parties to and expressly intended beneficiaries of the Governmental Entities' contractual obligations. The Governmental Entities have breached their contractual obligations, entitling the California IOUs to the relief requested in this Complaint. 4. FERC has determined that sellers in the California wholesale electric markets charged

rates that were unjust, unreasonable, and unlawful. Pursuant to the tariffs governing those markets, FERC has corrected and reduced the rates that all sellers, including the Governmental Entities, were entitled to charge for those sales for the period October 2, 2000 through June 20, 2001 ("the Refund Period"). To correct the harm caused by the unlawful prices, FERC ordered all sellers in the California markets to pay refunds for their unlawful overcharges. On September 6, 2005, however, the Ninth Circuit Court of Appeals ("Ninth Circuit") held that FERC's statutory refund authority did not extend to the Governmental Entities. The Ninth Circuit's order put the Governmental Entities in a unique position among ISO and PX market participants in that they alone may seek to benefit from refunds paid by others while escaping liability for their own unlawful overcharges. The Ninth Circuit noted, however, that market participants could bring claims in court directly against the Governmental Entities to enforce the contractual obligations created by FERC tariffs and related agreements under which the Governmental Entities sold power in the ISO and PX markets. Thus, the Governmental Entities are now contractually obligated to reimburse the California IOUs for the difference between the rates that the Governmental Entities charged during the Refund Period and the lawful, corrected rates under the tariffs. 5. Amounts recovered by the California Parties will ultimately benefit California

ratepayers in the manner determined by the California Public Utilities Commission ("CPUC "). PARTIES 6. PG&E is a corporation formed under the laws of the State of California with its

principal place of business in San Francisco, California. PG&E is a subsidiary of PG&E Corporation. PG&E is engaged in the purchase, transmission, distribution and sale of electric power to the public at wholesale and retail within the State of California, and is a "public utility" within the meaning of the California Public Utilities Code and the Federal Power Act ("FPA").
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 3

A1367

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 4 4 of 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page of 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

PG&E provides retail electric service to approximately 4.9 million customers in Northern and Central California. 7. SCE is a corporation formed under the laws of the State of California with its principal

place of business in Rosemead, California. SCE is a subsidiary of Edison International. SCE is engaged in the purchase, transmission, distribution and sale of electric power at wholesale and retail within the State of California, and is a "public utility" within the meaning of the California Public Utilities Code and the FPA. SCE provides retail electric service to approximately 4.6 million customers in a 50,000 square- mile area of Central, Coastal, and Southern California, excluding the City of Los Angeles and certain other cities. 8. The EOB was created by California statute to oversee the ISO and PX, and to

"investigate any matter related to the wholesale market for electric power to ensure that the interests of California 's citizens and consumers are served, protected, and represented in relation to the availability of electric transmission and generation and related costs, during periods of peak demand." Cal. Pub. Util. Code § 335. The EOB joins this action pursuant to its statutory authority to sue and to participate in all proceedings relevant to the purposes of the electricity restructuring provisions in the California Public Utilities Code, Cal. Pub. Util. Code §§ 330-398.5. 9. Defendant Arizona Electric Power Cooperative, Inc. ("AEPCO") is a rural electric

generation and transmission cooperative incorporated in Arizona with its principal place of business in Benson, Arizona. AEPCO provides its generation and transmission services to member distribution cooperatives located in Arizona and California, and is registered to do business in California. 10. Defendants the City of Anaheim; the City of Azusa; the City of Banning; the City of

Burbank; the City of Glendale; the City of Los Angeles; the City of Pasadena; the City of Riverside; the City of Santa Clara; and the City of Vernon are California cities. 11. Defendant City of Seattle (Seattle City Light Department) is a city located in the State

of Washington. 12. Defendant Eugene Water and Electric Board ("EWEB") is a municipal utility located

in Eugene, Oregon.
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 4

A1368

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 5 5 of 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page of 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

13.

Defendant Los Angeles Department of Water and Power ("LADWP") is a municipal

utility and a proprietary department of the City of Los Angeles located in Los Angeles, California. 14. Defendant Modesto Irrigation District is a California irrigatio n district located in

Modesto, California. 15. Defendant Northern California Power Agency is a California agency located in

Roseville, California that assists municipalities, rural electric cooperatives, irrigation districts, and other publicly owned entities with the purchase, aggregation, scheduling, and management of electric power. 16. Defendant Public Utility District No. 2 of Grant County ("Grant County PUD") is a

public utility district located in Ephrata, Washington. 17. Defendant Sacramento Municipal Utility District is a municipal electric utility located

in Sacramento, California. 18. Defendant Salt River Project Agricultural Improvement and Power District ("Salt

River Project") is an agricultural improvement district located in the State of Arizona. 19. Defendant Turlock Irrigation District is a California irrigation district located in

Turlock, California. 20. All defendants engage or engaged in the business of wholesale and/or retail

generation, transmission, distribution, purchase and/or sale of electric power in California and, in particular, voluntarily elected to transact sales in the ISO and PX markets during the relevant time period. PERSONAL JURISDICTION AND VENUE 21. Personal jurisdiction is proper in this district over each Governmental Entity because

each Governmental Entity has made sales of electric power in this district, because this controversy arises out of each Governmental Entity's sales of electric power within this district, and because each Governmental Entity has consented to the jurisdiction of this Court in connection with this action pursuant to ISO Tariff § 20.7 and/or PX Tariff § 19.6, as to which the Governmental Entities agreed to be bound.

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

5

A1369

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 6 6 of 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page of 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

22.

Venue is proper in this district pursuant to 28 U.S.C. § 1391(b) because defendants are

subject to personal jurisdiction in this district and therefore are deemed to reside in this district, because a substantial part of the events or omissions on which the claims are based occurred in this district, and because this is a district wherein an act or transaction constituting the violation occurred. Venue is also proper in this district pursuant to ISO Tariff § 20.7 and/or PX Tariff § 19.6, as to which the Governmental Entities agreed to be bound. COMMON ALLEGATIONS 23. The California IOUs' claims arise out of the Governmental Entities' sales of electric

power from May 1, 2000 through June 20, 2001, in wholesale markets operated by the ISO and PX under tariffs filed with FERC. FERC has determined that all sellers in those markets charged rates that were unjust, unreasonable, and unlawful and, pursuant to the tariffs governing those markets, has corrected and reduced the rates that all sellers, including the Governmental Entities, were entitled to charge for various sales during the Refund Period. As a result of FERC's modification of the tariffs, the Governmental Entities are now contractually obligated to reimburse the California IOUs for the difference between the rates that the Governmental Entities charged and the lawful, corrected rates. The ISO and PX Markets 24. In 1996, California enacted Assembly Bill 1890 ("AB 1890") to restructure

California's electric power markets in order to facilitate the development of competition for the generation and sale of electric power. AB 1890 separated the California utilities' vertically integrated generation, transmission, and distribution functions into unbundled functions. PG&E and SCE divested themselves of a substantial portion of their generation facilities. Under applicable California law, all California investor-owned utilities, including the California IOUs, were required to supply electric power to all retail customers that did not affirmatively elect to purchase electric power elsewhere. 25. AB 1890 provided for the creation of two new wholesale market institutions to

facilitate the buying and selling of electric power: the ISO and the PX, which are non-profit, public

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

6

A1370

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 7 7 of 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page of 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

benefit corporations organized under California law, and subject to the exclusive regulatory jurisdiction of the FERC. 26. Under rules promulgated by the CPUC and approved by FERC, the California IOUs

were required, in general, to purchase through the ISO and the PX substantially all of the wholesale electric power that they needed to provide service to their retail customers, including electric energy and associated reserves and other ancillary services. Ancillary services are services such as reserve generating capacity that are necessary to maintain the reliability of the transmission of electricity from generators to customers. Other entities, including the Governmental Entities, were permitted voluntarily to buy or sell electric power in the ISO and/or PX markets. 27. The ISO and PX are "public utilities" under the FPA, and are therefore subject to

FERC's jurisdiction. During all relevant times, all sales and purchases in the ISO and PX markets were required to be made pursuant to tariffs filed with and approved by FERC that prescribed the terms and conditions of, and contained formulas used to establish prices for, all transactions in these markets. The ISO and PX Tariffs are the legal equivalent of federal regulations and also establish contractual obligations among the market participants, prescribing the rules, requirements and pricing formulas for all transactions in the ISO and PX markets. 28. The PX was created to function as California 's principal power market. The PX acted

as a clearinghouse for daily and hourly markets and submitted schedules of electric power to the ISO in which scheduled generation for the following day equaled scheduled demand. Pursuant to the PX Tariff, sellers in the PX market -- including the Governmental Entities -- submitted offers to sell electric power, and purchasers submitted demand bids for the quantity of electric power that they wanted to buy. The PX conducted day-ahead and same-day auctions that allowed parties to adjust their hourly commitments based on changing needs and availability. Under its tariff, the PX was charged with responsibility for, among other things, settling energy trades between PX market participants and preparing and distributing to PX market participants invoices reflecting the amounts payable and receivable by them in connection with their trading through the PX. 29. In general, the PX determined, for each hour in each of the markets that it operated, a

single market-clearing price that all electric power suppliers were paid under the auction provisions
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 7

A1371

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 8 8 of 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page of 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

of the PX Tariff. The PX matched offers to buy and sell beginning with the lowest-priced bids and continuing up to the highest-priced bids until the amount of power accepted matched the amount sought by purchasers at that price. The price of the last (and therefore the highest-priced) accepted bid set the price for the entire market. All sellers of electric power in a given auction received the same market-clearing price, even if the seller had offered to sell at a lower price. Thus, any distortions that inflated the market-clearing price affected the prices received by each and every seller in the market, including the Governmental Entities. 30. Although the role of the ISO has changed over time, it was created as the entity

responsible for operating and maintaining California's electric transmission grid, including resolving transmission congestion and purchasing electric power to maintain system reliability. To meet these obligations, the ISO operated, and still operates, wholesale markets for real-time energy purchases and ancillary services. 31. In general, in operating its real-time market, the ISO set a single market-clearing price

based on bids submitted by sellers pursuant to the ISO Tariff. As in the PX market, every seller in the ISO market received the same market-clearing price set by the ISO for any given interval, even if a seller had offered to sell at a lower price. 32. Thus, the PX operated a day-ahead and a day-of market intended to supply the electric

power needed to meet electric power demand as projected before the operating ho ur. The ISO accepted the PX schedules, then procured electric power needed to make the necessary adjustments in real time in order to ensure that the electric grid operated properly and safely. The ISO also charged market participants, including the California IOUs, for these products and services pursuant to its FERC-approved tariff. Ultimately, as a result of market dysfunction and manipulation, and resulting power shortages, vast quantities of electric power were purchased and sold through the ISO market during the relevant time period. 33. In order to obtain sufficient electric power to maintain reliability of California's

electric grid, the ISO at times was required to procure electric power through mechanisms other than its regular auction. During the period at issue, the ISO was often forced to solicit such emergency electric power, known as "out-of- market" or "OOM" electric power, to meet the State's
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 8

A1372

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 9 9 of 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page of 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

demand for electric power. The ISO Tariff permitted the ISO to solicit this electric power through extraordinary means, such as telephone calls to electric power marketers and generators, including the Governmental Entities. These purchases were subject to certain price caps applicable in the ISO markets, which price caps varied during the relevant period and were intended to prevent price gouging; but suppliers of OOM electric power regularly demanded more than the FERC-approved price cap for such sales to the ISO. In order to maintain the reliability of the State's electric grid, the ISO procured the electric power at whatever price it was offered, even if that price exceeded its price caps, and then charged market participants, including the California IOUs, for these products and services. 34. The ISO and the PX Tariffs filed with FERC contained the only terms and conditions,

including the pricing formulas, upon which transactions in the ISO and the PX could lawfully be conducted. The Governmental Entities voluntarily elected to transact sales in the ISO and PX markets and thereby are charged with knowledge of and are deemed to have accepted the terms of the Tariffs, which set forth the mutual rights and obligations among market participants. These obligations may be enforced by market participants against one another. 35. In addition, the PX Tariff required all PX market participants, including the

Governmental Entities, to execute a PX Participation Agreement. The PX Participation Agreement was prescribed by the PX Tariff and provided that, inter alia, the PX market participant "will abide by and will perform all of the obligations under the PX Tariff in respect of all matters set forth therein including, without limitation, all matters relating to the trading of Energy by it through the PX market." PX Tariff Appendix A, Participation Agreement, § II(B). The PX Participation Agreement further provided that "[t]he PX Tariff is incorporated herein and made a part hereof. " PX Tariff Appendix A, Participation Agreement, § 8. 36. The ISO Tariff contemplated that each market participant, including Governmental

Entities, would execute an ISO Scheduling Coordinator Agreement. The Scheduling Coordinator Agreement was prescribed by the ISO Tariff and provided that, inter alia, the ISO Scheduling Coordinator "will abide by, and will perform all of the obligations under the ISO Tariff placed on Scheduling Coordinators in respect of all matters set forth therein including, without limitation, all
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 9

A1373

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 10 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 10 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

matters relating to the scheduling of Energy and Ancillary Services on the ISO controlled grid, . . . [and] billing and payments . . . ." ISO Tariff Appendix B, Scheduling Coordinator Agreement, § 2(B). The Scheduling Coordinator Agreement further provided that "[t]he ISO Tariff is incorporated herein and made a part hereof." ISO Tariff Appendix B, Scheduling Coordinator Agreement, § 8. 37. Many market participants both bought and sold electric power in the ISO and PX

markets during the relevant time period. As a prerequisite to trading in the ISO and PX markets, the tariffs provided that all market participants would be required to meet stated collateral requirements in the ISO and PX to ensure that the y would meet their obligations to the other market participants arising from their purchases and sales. 38. Each month during the relevant time period, the ISO and the PX calculated the total

amount of electric power supplied and purchased by each market participant, including the Governmental Entities. The ISO and the PX then issued individual billing statements, invoices, and supporting data, specifying amounts due to or from each market participant. 39. The California IOUs, as market purchasers, are counterparties to sales by

Governmental Entities in the ISO and PX markets and have standing to enforce the Governmental Entities' contractual obligations under the ISO and PX Tariffs and related agreements. The ISO and the PX operated as revenue- neutral clearinghouses, and were not themselves counterparties to any market transactions. 40. Under their respective tariffs, the ISO and the PX pass through liability for market

shortfalls to market participants, including the California IOUs, that bought or sold power in the markets during the period for which there is a shortfall of funds. A market shortfall may result if one market participant defaults on a payment, causing a shortage of total funds collected by either the ISO or the PX for distribution to the other market participants. An entity that fails to pay its bill becomes responsible for a market shortfall, and is deemed an "ISO Debtor" or a "PX Debtor." An entity that is owed money because of the market shortfalls is deemed an "ISO Creditor" or "PX Creditor," with the right to enforce its contractual right to payment against an ISO or PX Debtor.

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

10

A1374

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 11 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 11 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

41.

In summary, the ISO and PX Tariffs provided the mechanisms through which electric

power was bought and sold by market participants, with the ISO and the PX acting as clearinghouses for electric power bought and sold by market participants, holding collateral for market participants, and settling the accounts of all market participants. FERC's Exclusive Jurisdiction Over the ISO and PX Tariffs 42. Because the ISO and the PX are "public utilities" under the FPA, 16 U.S.C. § 824(e),

the tariffs under which they operate were filed with and approved by FERC, and are subject to FERC's exclusive jurisdiction, continual oversight and regulation. These tariffs were subject to amendment or revision by FERC, and, in fact, FERC repeatedly revised them during the relevant time period. 43. As entities regulated by FERC, the ISO and the PX were not permitted to act on any

terms or conditions other than those contained in the ISO and PX Tariffs. The ISO and PX Tariffs required each participant in the ISO and PX markets to comply with all rules, conditions and provisions of the ISO and PX Tariffs. 44. Pursuant to the FPA, FERC has exclusive authority to regulate wholesale sales of

electric power to ensure, among other things, that the rates charged are just, reasonable , and lawful. FERC thus has exclusive authority to regulate the rates, terms, and conditions of sales made under the ISO and PX Tariffs and to recalculate and correct such rates, terms, and conditions if FERC determines that they are not just, reasonable, and lawful. The ISO and PX Tariffs provide that parties retain the right to petition FERC to review rates charged under the tariffs and provide for recalculation of charges and resettlement of the accounts of buyers and sellers under the tariffs in the event that FERC determines that any rates charged under the tariffs were unjust, unreasonable, or otherwise unlawful, and thus subject to correction. 45. By voluntarily electing to sell electric power in the ISO and PX markets, the

Governmental Entities agreed to be bound by the provisions of the ISO and PX Tariffs and any modifications thereof, including FERC's orders correcting the rates that sellers could lawfully charge for sales governed by those tariffs. Almost all of the Governmental Entities also executed written contracts, including ISO Scheduling Coordinator Agreements, and/or PX Participation
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 11

A1375

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 12 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 12 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

Agreements, and/or other agreements with the ISO or PX, expressly agreeing to abide by the provisions of the ISO and/or PX Tariffs. The California IOUs are direct parties to and expressly intended beneficiaries of the Governmental Entities' contractual obligations. Because the tariffs are subject to FERC's exclusive jurisdiction, all market participants, including the Governmental Entities, recognized that FERC would exercise its regulatory authority over the tariffs. If the price charged by sellers was found by FERC to be unjust and unreasonable or otherwise unlawful, all market sellers were contractually bound to refund or credit to purchasers the difference between the price charged and the lawful, corrected rate determined by FERC. Thus, all market participants were contractually bound to honor the terms and conditions of the tariffs, as revised by FERC, and these terms and conditions can be contractually enforced by the market participants against one another. The Governmental Entities' obligation to refund or credit their unlawful overcharges is the same obligation owed by all sellers in the ISO and PX markets, although the California IOUs' obligations for their purchases of electric power and other services in the ISO and PX markets remain under FERC's exclusive jurisdiction. The Powe r Crisis 46. Beginning in May 2000, the prices demanded by sellers in the ISO and PX markets

rose dramatically and sellers continued to demand unprecedented high prices for over a year, resulting in rates far in excess of those charged in prior and later periods. As a result of the auction provisions of the ISO and PX Tariffs, these extremely high prices were charged by all sellers in the markets, even if individual sellers had offered to sell their power in the auctions at lower prices. The power crisis had severe negative effects on the stability and financial integrity of the California IOUs, and ultimately imposed billions of dollars in additional costs on ratepayers, including business and residential customers throughout the State. 47. The first ratepayer impacts of these extraordinarily high prices were felt in the San

Diego area, because San Diego Gas & Electric Company's ("SDG&E's") rates in the summer of 2000 provided for immediate, direct pass-through to ratepayers of the increased wholesale electric power costs. By January 2001, PG&E and SCE had amassed crippling debt in order to finance the

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

12

A1376

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 13 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 13 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

costs of buying electric power, costs that they were not permitted to immediately pass through to their customers. PG&E and SCE became unable to pay the PX in January 2001. 48. The surge in electric power prices also affected the reliability of the electric grid. On

June 14, 2000, electric power consumers in Northern California experienced their first wave of rolling blackouts. These blackouts foreshadowed the rolling blackouts and near-continuous power emergencies that California electric customers experienced over the next year. 49. The crisis did not subside with the arrival of cooler weather in the fall of 2000.

Although California 's peak electric power usage historically declines by roughly 25 to 33 percent during the cooler months, prices continued to rise throughout the last quarter of 2000 and the first part of 2001. 50. By January 2001, a confluence of events led to the collapse of reliable electric service

in California. At times in January 2001, the ISO ordered rolling blackouts throughout large areas of California in order to maintain the reliability of the transmission grid. The crisis became a state of emergency, threatening the safety and welfare of California citizens. 51. On December 15, 2000, FERC issued an order eliminating the requirement that the

California IOUs purchase all of their needed electric power through the PX, and the PX ceased operatio ns of its core markets on January 30, 2001. On or about January 5, 2001, the credit ratings of PG&E and SCE fell below investment grade, making PG&E and SCE ineligible to purchase power through the ISO and PX. The State of California was forced to step in as the buyer of last resort to buy electric power on behalf of the California IOUs to ensure continued service to retail customers throughout the territories served by the California IOUs. Unrelenting high prices caused PG&E and SCE to become insolvent. 52. The power crisis ultimately ended when FERC, on June 19, 2001, imposed "must-

offer" requirements on electric power generators prohibiting them from withholding generation, and imposed price caps on wholesale sellers of electric power across all western states effective June 21, 2001 ("June 19, 2001 Order"). San Diego Gas & Electric Co., et al., 95 FERC ¶ 61,418 at 62,558, 62,569 (2001). The remedies in the June 19, 2001 Order put an end to the rolling blackouts, catastrophically high prices, and near-continuous power emergencies.
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 13

A1377

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 14 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 14 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

53.

The bulk of the crippling costs of the crisis have been passed through to, and paid by,

the residential and commercial ratepayers of the California IOUs. These costs are included in current rates assessed to customers of the California IOUs, and will continue to be included in rates until the costs of the crisis have been paid off. By this Complaint, the California IOUs are seeking to recover from the Governmental Entities the amounts that each Governmental Entity received in excess of the lawful rates for its wholesale sales of electric power to the California IOUs in the ISO and PX markets. Amounts recovered by the California IOUs will ultimately benefit California ratepayers in the manner determined by the CPUC. The California Parties Seek Relief From FERC 54. On August 2, 2000, when it became clear that the extremely high wholesale prices

were not returning to the lower levels that had prevailed historically, SDG&E filed a complaint with FERC under the FPA against all sellers of energy and ancillary services into markets operated by the ISO and PX. FERC Docket No. EL00-95. PG&E, SCE, and the EOB intervened in that proceeding on August 14, 2000. The Governmental Entities were also parties to that proceeding. In that proceeding, the California Parties requested that FERC investigate the justness, reasonableness, and lawfulness of rates being charged in the California ISO and PX markets and that FERC order refunds to the extent that FERC determined that sellers had charged unjust, unreasonable, or otherwise unlawful rates. 55. In response to SDG&E's complaint, FERC commenced its own investigation into the

sellers' rates, which it consolidated with SDG&E's complaint. Collectively, the associated proceedings are referred to as the "Remedy Proceeding. " In an order issued July 25, 2001 (the "July 25, 2001 Order"), FERC ruled that sellers of electric power in the ISO and PX markets (including the Governmental Entities) had sold electric power at unjust, unreasonable, and unlawful rates, and that the rates charged in the ISO and PX markets should be corrected for the Refund Period. FERC Docket No. EL00-98-000. See San Diego Gas & Electric Co., 96 FERC ¶ 61,120 (2001). 56. In the July 25, 2001 Order, FERC held: "Our action here establishes a revised method

for calculating the just and reasonable clearing prices to be applied in those markets for the period
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 14

A1378

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 15 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 15 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

beginning October 2, 2000. This is pursuant to the Commission's authority under FPA section 206 to fix the just and reasonable rate. Our action thus revises the market clearing prices that all market participants previously agreed to accept for their sales. In this context, we see no reason to treat [the Governmental Entities] differently, as they are receiving the same price, the just and reasonable market clearing price established pursuant to market rules approved by this Commission, that they expected to obtain for their wholesale sales in the centralized ISO and PX spot markets." July 25, 2001 Order, 96 FERC at 61,512. 57. FERC also concluded that, on the record before it, its statutory mandate did not grant

it authority to order refunds for the Summer Period (i.e., May 1, 2000 through October 1, 2000), and thus denied relief for the Summer Period. FERC also refused to correct the rates for "energy exchange " transactions (in which blocks of electric power were sold to the ISO for payment inkind) and sales to the ISO or the PX of greater than twenty- four hours (i.e., "multi-day" sales under FERC's definition) made during the Refund Period. See July 25, 2001 Order, 96 FERC at 61,499; see also San Diego Gas & Electric Co., 102 FERC ¶ 61,317 at 62,065 (2003). The California Parties have appealed to the Ninth Circuit FERC's decisions to limit refunds to the Refund Period and to certain transactions during the Refund Period, and that appeal is currently pending. 58. In order to remedy the unlawful prices charged in the market during the Refund

Period, FERC has, in a series of orders beginning with the July 21, 2005 Order, adopted a methodology to recalculate, on a market-wide basis, the just and reasonable prices that all sellers should have received under the ISO and PX Tariffs. In lieu of the auction pricing mechanism previously provided in the ISO and PX Tariffs, which resulted in unlawful prices, FERC's methodology effectively revised the ISO and PX Tariffs to determine the corrected, maximum rates that could be charged under those tariffs. These corrected, maximum rates were called the "Mitigated Market Clearing Price," or "MMCP." FERC ordered the ISO and PX to apply the MMCP to sales during the Re fund Period, including to OOM sales, in order to recalculate the charges that all sellers should have received for each interval during the Refund Period in place of the previous unlawful prices.

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

15

A1379

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 16 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 16 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

59.

The ISO was ordered to calculate the amounts that sellers were required to refund or

credit to buyers under the July 25, 2001 Order. July 25, 2001 Order, 96 FERC at 61,516. Pursuant to FERC's direction, the ISO and the PX have recalculated the accounts of all sellers and buyers in the ISO and PX markets to reflect the corrected rates for the Refund Period in accordance with the July 25, 2001 Order and the subsequent related FERC orders. 60. The California Parties have petitioned the Ninth Circuit for review of the July 25,

2001 Order and subsequent FERC rehearing orders on the ground, inter alia, that FERC was also required to correct the rates for sales made during the Summer Period. That petition for review has been briefed and argued and is now pending for decision in the Ninth Circuit. Public Util. Comm'n of Cal. v. Federal Energy Regulatory Comm'n, Case No. 01-71051, et al. The California Parties have also appealed the July 25, 2001 Order on the ground that FERC was required to correct the rates for energy exchange transactions and multi-day sales made during the Refund Period. The California Parties' challenges to FERC's rulings on energy exchanges and multi-day sales are pending in the Ninth Circuit in the same case. 61. The question of relief for the Summer Period and other non-mitigated Refund Period

transactions also was at issue in a second FERC proceeding, separate from the Remedy Proceeding. In a petition to the Ninth Circuit for review of orders in that FERC proceeding, the Ninth Circuit held that FERC had erred by concluding that it lacked authority to order refunds for the Summer Period transactions and for other non- mitigated transactions during the Refund Period, and remanded the case so that FERC, "in the first instance," could reconsider whether refunds are appropriate for those transactions. California, ex rel. Lockyer v. FERC, 383 F.3d 1006, 1016-18 (9th Cir. 2004), pet. for reh'g pending. Market Manipulation Resulted in Windfall Profits for All Sellers 62. FERC recognized early on that market manipulation could have negatively affected

the California markets. On November 1, 2000, FERC noted that "there is clear evidence that the California market structure and rules provide the opportunity for sellers to exercise market power when supply is tight and can result in unjust and unreasonable rates under the [Federal Power Act]." San Diego Gas & Electric Co., 93 FERC ¶ 61,121 at 61,350 (2000) ("November 1 Order").
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 16

A1380

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 17 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 17 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

63.

FERC initially refused the California Parties' attempts to obtain discovery and

introduce into the Remedy Proceeding evidence of sellers' market manipulation and tariff violations, but in May 2002, acting in a separate non-public docket, FERC released memoranda that described how Enron and other sellers had manipulated the ISO and PX markets in order to increase prices throughout the power crisis. In response, FERC propounded discovery requests to all sellers in the ISO and PX markets regarding market manipulation. On August 23, 2002, the Ninth Circuit directed FERC to allow the California Parties to adduce in the Remedy Proceeding evidence of sellers' market manipulation and tariff violations. As a result of the Ninth Circuit's order, the California Parties conducted discovery from late 2002 to early 2003 of sellers in the ISO and PX markets, including the Governmental Entities. That discovery provided evidence of a pattern of market manipulation and tariff violations involving numerous sellers in the ISO and PX markets. 64. The California Parties' discovery uncovered evidence that certain sellers in the market

engaged in various forms of market manipulation and tariff violations that created the false perception of scarcity in the market and that drove up market prices. For example, sellers practiced physical and economic withholding of generation. This allowed suppliers to increase the price of electricity by keeping large amounts of electric power off the market. Physical withholding occurred when a generator refused to place a supply bid with the PX even when it had power available, or when it falsely reported an outage at a generating plant. Economic withholding occurred when a seller placed high bids unrelated to its generation costs to create the false appearance of scarcity, and so to drive prices higher than true competitive levels would have provided. 65. Certain sellers in the market engaged in other gaming strategies -- the infamous "Fat

Boy," "Death Star," and "Ricochet" schemes, among others -- and often used other market participants to assist them with these gaming strategies. Notes and tapes of telephone conversations among energy traders revealed discussions about traders' submission of "fake load" in the market, about their intent to "push the price up and keep the price up," and about their implementation of

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

17

A1381

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 18 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 18 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

bidding strategies that would signal other market participants to withhold electric power from the market through physical or economic means. 66. Once this information was available, it became evident that market fraud and

manipulation were significant causes of the California Energy Crisis. Since the end of the California Energy Crisis, numerous energy traders and executives have pled guilty to, or been indicted on, criminal charges, and many have specifically admitted to market manipulation activities. 67. Because all sellers received the same market-clearing prices set by the ISO and PX

auctions, the artificially inflated prices created windfall profits for all sellers in the ISO and PX markets, benefiting even those sellers that did not engage in market manipulation. FERC's July 25, 2001 Order and subsequent orders have ameliorated the effects of market manipulation on the transactions that they addressed by correcting the pricing under the ISO and PX Tariffs to reduce the prices that all sellers were authorized to retain for those sales. The Ninth Circuit's Bonneville Decision 68. FERC ruled in a series of decisions that its power to enforce sellers' payment of

refunds under the FPA extended to governmental entities and rural electric cooperatives, such as the Governmental Entities. Certain of the Governmental Entities appealed this decision to the Ninth Circuit. On September 6, 2005, the Ninth Circuit ruled that FERC lacked statutory authority directly to enforce the Governmental Entities' refund obligations under the ISO and PX Tariffs. Bonneville Power Admin. v. Federal Energy Regulatory Comm'n, 422 F.3d 908 (9th Cir. 2005). The Court noted, however, that market participants had, as an alternative remedy, the ability to bring claims in court directly against the Governmental Entities to enforce the contractual obligations created by the operative tariffs and related agreements. Bonneville Power Admin., 422 F.3d at 925-926. 69. The Ninth Circuit observed that the Governmental Entities' agreement to abide by the

ISO and PX Tariffs "[serves] to demonstrate that the remedy, if any, may rest in a contract action, not a refund action. Such an approach is not novel . . . ." id. at 925 (citing Alliant Energy v. Neb. Pub. Power Dist., 347 F.3d 1046, at 1050-51 (8th Cir. 2003)). The Ninth Circuit quoted with
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 18

A1382

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 19 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 19 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

approval the Eighth Circuit's holding in Alliant Energy that "[w]hen a contract provides that its terms are subject to a regulatory body, all parties to that contract are bound by the actions of the regulatory body . . . . As a result, we are not enforcing the FERC order; instead, we are enforcing an agreement, which [the Governmental Entity] freely entered.") Bonneville, 422 F.3d at 926 (quoting Alliant Energy, 347 F.3d at 1050). The Ninth Circuit has not yet issued the mandate in the Bonneville proceeding. 70. In this Complaint, the California Parties seek to enforce in this Court the

Governmental Entities' contractual obligations to refund the amounts they charged in excess of the lawful corrected rates, as suggested by the Ninth Circuit in its Bonneville decision. 71. On December 2, 2005, without conceding that they were required to take such action

at that time, the California Parties complied with state claims presentment statutes by serving copies of written claims on all California defendants and on the Salt River Project, providing them with notice of the California Parties' present claims for relief. Cal. Gov't Code § 910; Ariz. Rev. Stat. 12-821-01. The Arizona claims presentment statutes do not apply to RUS-financed cooperatives; consequently, no notice of claim was presented to AEPCO. On the same date, the California Parties also served claims on EWEB, the City of Seattle, and Grant County PUD, in light of ambiguity as to whether the California Parties were required to present these claims under Oregon and Washington law. Ore. Rev. Stat. § 30.275; Rev. Code. Wash. 4.96.010-020. 72. The waiting periods prescribed by the applicable claims presentment statutes have

elapsed. The Cities of Anaheim, Azusa, Banning, Burbank, Glendale, Pasadena, Riverside, Santa Clara, Los Angeles, Seattle and Vernon, and the LADWP, Modesto Irrigation District, Turlock Irrigation District, the Northern California Power Agency, and the Sacramento Municipal Utility District have denied the California Parties' claims. The California Parties' claims presented to Grant County and Salt River Project are deemed denied by operation of law because the statutory period for a decision by these entities has expired. The California Parties' claims against EWEB remain unsatisfied, and Oregon law does not require any formal action by EWEB prior to commencement of suit.

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

19

A1383

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 20 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 20 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

73.

Prior to the Ninth Circuit's Bonneville order, which was issued on September 6, 2005,

FERC asserted and exercised exclusive jurisdiction over claims for refunds from all sellers, including the Go vernmental Entities. Thus, in accordance with the July 25, 2001 Order and under FERC's rulings and Ninth Circuit authority, the FERC proceedings were the exclusive forum for the California Parties' refund claims, including claims for refunds from the Gove rnmental Entities. No claim accrued and no limitations period commenced to run until September 6, 2005, when the Ninth Circuit ruled, for the first time, that FERC did not, in fact, have jurisdiction to enforce the refund liability of the Governmental Ent ities. 74. Alternatively, to the extent that any limitations period had commenced to run on the

California Parties' right to sue in a court to enforce the Governmental Entities' refund obligations prior to the Bonneville order, the limitations period was tolled, at a minimum, from the time the California Parties initiated refund proceedings with FERC on August 2, 2000, through the time the Ninth Circuit issued its decision in Bonneville on September 6, 2005. 75. This lawsuit is based on the same facts that were at issue in the Remedy Proceeding

and in the various Ninth Circuit appeals from the Remedy Proceeding: the sellers' (including the Governmental Entities') receipt and retention of rates for sales of wholesale electric power in the ISO and PX markets that are unlawful and unauthorized under the ISO and PX Tariffs. The California Parties acted promptly, reasonably, and in good faith in seeking relief from FERC against all sellers in the California markets, including the Governmental Entities. The Governmental Entities were active parties to the FERC Remedy Proceeding, and have had notice throughout the FERC proceedings of the need to gather and preserve relevant evidence. Following the Ninth Circuit's Bonneville decision, the California Parties acted expeditiously to present claims to the Governmental Entities and to commence this action.

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

20

A1384

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 21 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 21 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

CLAIMS FOR RELIEF FIRST CLAIM Breach of Contract 76. 77. The California Parties incorporate by reference the allegations set forth above. All sellers in the ISO and PX markets, including the Governmental Entities, were

charged with knowledge that the market-clearing prices, and the formulas and market rules that set the prices, were subject to correction if they were found by FERC to contravene the requirements of the FPA. By voluntarily choosing to sell electric power at wholesale in the ISO and PX markets, and/or by executing ISO Scheduling Coordinator Agreements, PX Participation Agreements, or other agreements with the ISO or PX, the Governmental Entities contractually agreed to be bound by the provisions of the ISO and PX Tariffs, which incorporate FERC's power to correct prices that it determines to be unjust, unreasonable, or unlawful. 78. Pursuant to its authority under the FPA, FERC revised the tariffs and corrected the

prices that market participants were entitled to receive for their sales during the Refund Period by adopting the MMCP. Upon FERC's correction of the rates charged and received by sellers, including the Governmental Entities, in the ISO and PX markets, the corrected rates became the only lawful and authorized rates for those sales under the applicable tariffs. 79. The Governmental Entities are now contractually obligated to reimburse the California

IOUs for the difference between the rates that the Governmental Entities initially charged for their sales in the ISO and PX markets and the MMCP. The Governmental Entities have refused to refund, and continue to refuse to refund, to the California IOUs the amounts that they received in excess of the MMCP during the Refund Period. 80. The Governmental Entities' conduct constitutes a breach of their contractual

obligations to the California IOUs, entitling the California IOUs to judgment against each Governmental Entity for all amounts that each Governmental Entity received in excess of the lawful rate attributable to its wholesale sales of electric power to the California IOUs in the ISO and PX markets during the Refund Period, plus associated interest.

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

21

A1385

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 22 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 22 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

SECOND CLAIM Anticipatory Breach of Contract 81. 82. The California Parties incorporate by reference the allegations set forth above. This Claim is pleaded in the alternative to the First Claim. If it is determined that the

date by which the Governmental Entities would be obligated under the applicable contracts to refund to the California IOUs the amounts that they received in excess of the MMCP during the Refund Period has not yet occurred, the Governmental Entities have nonetheless become obligated to make such refunds immediately, and in advance of such date, because they have wrongfully denied and repudiated any legal duty to so repay the California IOUs. Specifically, the Governmental Entities have repudiated, in the FERC proceedings, in appeals from FERC orders, and by their denial of the California IOUs' duly-presented claims, their contractual obligations to the California IOUs, including their obligation to comply with the revised Tariff provisions by refunding their unlawful overcharges. 83. The Governmental Entities' conduct constitutes an anticipatory breach of their

contractual obligations to the California IOUs, entitling the California IOUs to judgment against each Governmental Entity for all amounts that each Governmental Entity received in excess of the lawful rate attributable to its wholesale sales of electric power to the California IOUs in the ISO and PX markets during the Refund Period, plus associated interest. THIRD CLAIM Unjust Enrichment Arising from Contract 84. 85. The California Parties incorporate by reference the allegations set forth above. By accepting and retaining prices that are now unlawful under the ISO and PX Tariffs,

and by denying their obligations to refund or credit overcharges to buyers in the ISO and PX markets, the Governmental Entities have unjustly enriched themselves at the expense of market purchasers, including the California IOUs and, ultimately, the IOUs' customers, who paid inflated and unlawful prices for electric power. The Governmental Entities' retention of those unlawful prices violates their contractual duty to abide by the provisions of the ISO and PX Tariffs.
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 22

A1386

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 23 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 23 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

86.

In addition, the Governmental Entities' retention of prices in excess of the MMCP that

are unauthorized under the tariffs is inequitable and unfair: For transactions where they were buyers, the Governmental Entities are seeking refunds from other sellers of prices they paid in excess of the lawful, corrected rate. By contrast, for transactions where they were sellers, the Governmental Entities deny any obligation to pay refunds, and seek to retain the windfall benefits of the original unlawful prices they charged other market participants. 87. The Governmental Entities have been unfairly enriched, entitling the California IOUs

to judgment against each Governmental Entity for all amounts that each Governmental Entity received in excess of the lawful rate attributable to its wholesale sales of electric power to California IOUs in the ISO and the PX markets during the Refund Period, plus associated interest. FOURTH CLAIM Money Had and Received 88. 89. The California Parties incorporate by reference the allegations set forth above. By accepting and retaining prices that are unlawful under the ISO and PX Tariffs, and

by denying their obligations to refund or credit overcharges to those buyers in the ISO and PX markets, the Governmental Entities ha ve accepted the benefit of illegal profits that rightfully belong to purchasers in the ISO and PX markets, including the California IOUs, that were harmed by the unlawful prices. Any overcharges received by a Governmental Entity from the California IOUs as a result of unlawful prices rightfully belong to and should be returned to the California IOUs. 90. The Governmental Entities are accordingly liable to the California IOUs for all

amounts each Governmental Entity received in excess of the lawful rate attributable to its wholesale sales of electric power to the California IOUs in the ISO and PX markets during the Refund Period, plus associated interest. FIFTH CLAIM Declaratory Relief (Refund Period) 91. The California Parties incorporate by reference the allegatio ns set forth above.

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

23

A1387

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 24 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 24 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

92.

A controversy has arisen in that the Governmental Entities have denied any liability to

the California IOUs for overcharges associated with transactions during the Refund Period for which FERC has ordered relief. The California Partie s seek a declaratory judgment that the California IOUs are contractually entitled to recover from each Governmental Entity all amounts that each Governmental Entity charged in excess of the lawful rate attributable to its sales to the California IOUs in the ISO and PX markets during the Refund Period. SIXTH CLAIM Declaratory Relief (Energy Exchanges and Multi-Day Sales) 93. 94. The California Parties incorporate by reference the allegations set forth above. A controversy has arisen in that the Governmental Entities have denied that they will

have any liability to the California IOUs to refund their overcharges associated with energy exchanges and multi-day sales if FERC corrects the prices for these transactions. The California Parties seek a declaratory judgment that at such time as FERC finds that the rates charged by sellers for energy exchanges or multi-day sales were unlawful, the California IOUs will be entitled to recover from the Governmental Entities the difference between the rates the Governmental Entities charged and the lawful rates as ultimately determined by FERC, plus associated interest. SEVENTH CLAIM Declaratory Relief (Summer Period) 95. 96. The California Parties incorporate by reference the allegations set forth above. A controversy has arisen in that the Governmental Entities have denied that they will

have any liability to the California IOUs to refund their overcharges associated with their sales during the Summer Period if FERC corrects the prices for the Summer Period. The California Parties seek a declaratory judgment that at such time as FERC finds that the rates charged by sellers during the Summer Period were unlawful, the California IOUs will be entitled to recover from the Governmental Entities the difference between the rates that the Governmental Entities originally charged and the lawful rates as ultimately determined by FERC, plus associated interest.

COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND

24

A1388

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 25 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 25 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

EIGHTH CLAIM Declaratory Relief (Contractual and Equitable Indemnification) 97. 98. The California Parties incorporate by reference the allegations set forth above. Because the ISO and PX are revenue- neutral entities, the Governmental Entities'

refusal to honor their repayment obligations will result in a shortfall of funds needed to settle the accounts of ISO and PX participants. Under the terms of the ISO and PX Tariffs, other market participants, including the California IOUs, may therefore be required to indemnify the ISO and PX for the resulting shortfall. 99. Any reductions in the California IOUs' accounts to indemnify the ISO and PX for the

Governmental Entities' refusal to honor their repayment obligations will constitute amounts due and owing by the Governmental Entities, as ISO Debtors and PX Debtors, to the California IOUs as ISO Creditors and PX Creditors. The California IOUs, as market participants, are entitled under the ISO and PX Tariffs to bring proceedings directly against the Governmental Entities to recover these amounts owed. A controversy has arisen in that the Governmental Entities have denied that they have any obligation to disgorge amounts they received in excess of the lawful rate. 100. The California IOUs seek a declaratory judgment that the Governmental Entities will be liable to the California IOUs on grounds of contractual and equitable indemnification for any amount assessed against the California IOUs' accounts due to the Governmental Entities' refusal to honor their repayment obligations, as well as for all additional costs and expenses incurred by the California IOUs as a result of the Governmental Entities' refusal to hono r their repayment obligations. NINTH CLAIM Declaratory Relief (ISO and PX Accounts) 101. The California Parties incorporate by reference the allegations set forth above. 102. This Claim is pleaded in the alternative to the First through Eighth Claims. 103. A controversy has arisen in that the Governmental Entities have denied that they have any liability to the California IOUs to refund their overcharges associated with their sales during the
COMPLAINT FOR DAMAGES AND/OR RESTITUTION & DECL. RELIEF , JURY DEMAND 25

A1389

Case 2:06-cv-00559-MCE-KJM Document 1-1 Filed 03/28/2008 Page 26 ofof 30 Case 1:07-cv-00184-LAS Document 44-10 Filed 03/16/2006 Page 26 49

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Heller 28 Ehrman LLP

Refund Period, and that they will have any liability to the California IOUs to refund their overcharges associated with Energy Exchanges and Multi- Day Sales and sales during the Summer Period if FERC corrects the prices for t