Case 1:08-cv-00195-CFL
Document 10
Filed 09/09/2008
Page 1 of 1
IN THE UNITED STATES COURT OF FEDERAL CLAIMS No. 08-195T (Filed: September 9, 2008) ____________________________________ ) DOMINION RESOURCES, INC., ) ) Plaintiff, ) ) v. ) ) UNITED STATES, ) ) Defendant. ) ____________________________________) SCHEDULING ORDER The court acknowledges the joint preliminary status report filed by the parties on September 8, 2008. The parties have proposed a schedule for discovery in this case. In light of the parties' Joint Preliminary Status Report, and for good cause shown, discovery in this case will proceed according to the following schedule: Action Completion of discovery Joint Status Report Deadline March 9, 2009 April 13, 2009
It is so ORDERED. s/ Charles F. Lettow Judge